Difference: ShutdownChecklist (1 vs. 2)

Revision 22015-08-24 - MarkusJoos

Line: 1 to 1
 
META TOPICPARENT name="WebHome"
Added:
>
>

To access the T9 zone when beam is on:

 
  • Unchecked checkbox Stop data acquisition
Added:
>
>
  • Unchecked checkbox Power down MNP17 magnet (from control room on the first floor)
  • Unchecked checkbox Put beam stopper in
  • Unchecked checkbox Switch T9 door to "free access" or "key access"
  • Unchecked checkbox One CERN member goes to T9 and check the magnetic fields
  • Unchecked checkbox If T9 is safe students may enter

Shut down at the end of the day

  • Unchecked checkbox Stop data acquisition
  • Unchecked checkbox Power down MNP17 magnet (from control room on the first floor)
 
  • Unchecked checkbox Powerdown high voltage module
  • Unchecked checkbox Put beam stopper in
  • Unchecked checkbox Call CCC to stop beam

Revision 12015-08-20 - MarkusJoos

Line: 1 to 1
Added:
>
>
META TOPICPARENT name="WebHome"
  • Unchecked checkbox Stop data acquisition
  • Unchecked checkbox Powerdown high voltage module
  • Unchecked checkbox Put beam stopper in
  • Unchecked checkbox Call CCC to stop beam

-- TimBrooks - 2015-08-20

 