Difference: WLCGOpsMinutes130919 (24 vs. 25)

Revision 252013-09-19 - StefanRoiser

Line: 1 to 1
 
META TOPICPARENT name="WLCGOpsCoordination"

WLCG Operations Coordination Minutes - 19 September 2013

Line: 123 to 123
 
    • After the router upgrade campaign in the CERN CC many Dirac services needed to be restarted because they lost connections.
  • Experiment Activities
    • Incremental stripping campaign close to start, last tests on the output rates are carried out by end of this week. Likely to (slowly) start the campaign by next week. Tentative duration ~ 8 weeks. Lots of stress on the sites tape systems.
Added:
>
>
    • Requested throughput rates for an incremental stripping campaign lasting 60 days

Total Rate (MB/s)
CERN 50
CNAF 153
GRIDKA 124
IN2P3 134
PIC 39
RAL 111
SARA 104
 

Task Force reports

SHA-2 migration

 