LHCb Computing Project Management Team

Changed:
<
<
The computing project management team consists of the following roles and people:
  • Project Leader (Marco Cattaneo, from Dec 2009 to Dec 2011)
  • Deputy Project Leader (Peter Clarke, from Oct 2010)
  • Resources Coordinator (Ricardo Graziani, from Jan 2011)
  • Distributed Computing Coordinator (Philippe Charpentier, from Mar 2011)
>
>
The structure, roles and people involved in the computing management team can be found at http://lhcb-comp.web.cern.ch/lhcb-comp/Organisation/Contacts.htm
  The team can be collectively reached at lhcb-comp-mgmt@cernNOSPAMPLEASE.ch (posting restricted to members of LHCb)

The team meets weekly. Agendas and Minutes are confidential, but the action list is public, see below.

Actions outstanding

Changed:
<
<
Action Minuted Who? Status
1 Provide data management overview information. To be acceptance tested by PCl and released in LHCbDirac 13/04/11 RG Need proper testing infrastructure. MC will follow up
2 Discuss requirements for permanent displays of data management information 13/04/11 RG, PCl Depends on 1. RG to request plots as minuted 27/04/11
4 Ask Stefan to request that LHCb SAM tests be included in glexec testing infrastructure 13/04/11 RG Done. Now waiting for DIRAC release to test glexec at the sites.
6 Finish documenting computing project roles 27/04/11 MC Manpower spreadsheet updated 9th June
7 Review steps needed to close a production 27/04/11 PCl Draft document with Federico for review
8 Regularly review manpower, identify current and future needs 27/04/11 MC Needs last minuted on 27/04/11
9 Define model for reprocessing at T2 11/05/11 PCl PCh will make a technical plan. PCl is organizing meetings to push this forward
15 Define model for WG productions 11/05/11 PCl Software for configuring test production released. PCl will create the step and see what happens
16 Prepare standard abstract for submission at future physics conferences 11/05/11 Use next generic abstract submitted to a conference. Prepare also a gallery of standard plots, depends on actions 1. and 2
17 Define abstracts for ACAT conference, deadline is 2nd July 01/06/11 MC MC has asked core software team to provide one or two abstracts. PhC will discuss with LHCbDIRAC team
20 Discuss with Federico how to adapt LHCbDIRAC Gaudi application plugin to support ROOT persistency, and with Zoltan to put the technical changes in the book-keepin 01/06/11 PCh PhC has discussed with Federico. Work is starting
21 Ask for some 2011 disk to be installed at NIKHEF, propose how space should be shared between NIKHEF and SARA 01/06/11 RG PCl to ask Geoff Templon to define constraints from site
23 Work with Tier1 sites to understand if/how they can provide pledged shares 01/06/11 RG RG to monitor situation and follow up with sites individually
24 Prepare LHCb session of WLCG workshop 01/06/11 MC, PCl, RG MC to ask LHCbDIRAC developers if they would like to go. PCl and RG will define agenda for LHCb session and prepare introduction talks
26 Set up piquet service for DIRAC third level support 15/06/11 RG RG to discuss with Andrei
>
>
Planning for the computing project can be found at https://its.cern.ch/jira/projects/LBCOMP/summary
  -- MarcoCattaneo - 16-Jun-2011
 