Difference: LHCbShutdown2010 (1 vs. 7)

Revision 72010-02-09 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
Changed:
<
<
--+ Shutdown activities
>
>

Shutdown activities

 

Infrastructure

TASK Build. DATE DOCUMENTS PERSONNEL COMMENTS- IMPACT STATUS
HVAC units for D3 A and D3 B UX85A and B Weeks 2 and 3 AOC 4251907 VIC 14/12 EN/CV (+Initiative + Cerclim) - EN/EL - ALTEAD Shielding Wall Mobile blug open from 04/01 Greene nacelle needed A side Ongoing
Changed:
<
<
SG8 / RICH1 cooling / Buffer volume SG8 Week 3 or 4 (TBC)   EN/CV (+Initiative ) No mixed water in SG for 1 day Prep
>
>
SG8 / RICH1 cooling / Buffer volume SG8 Week 3 or 4 (TBC)   EN/CV (+Initiative ) No mixed water in SG for 1 day Postoned to 01/03/2010
 
Detector Cooling - Maintenance (UPS) UX85A 04/01   EN/CV F. Corbaz All 4 Detector cooling plants off Done
Detector Cooling - Consolidation (Hydraulic ) UX85A TBD   EN/CV F. Corbaz All 4 Detector coling plants off POSTPONED
Detector Cooling - Maintenance (Hydraulic - Leaking valve ) UX85A TBD   EN/CV F. Corbaz RICH2 off Done
Changed:
<
<
Rich 1 and 2 gas system maintenance (membrane + recovery + purif) SG8 TBD   PH/DT S.Pavis 1h unavailibility during mambranne replacment
RAMSES probes in extraction ducts SX8 01/02/2010   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!)
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 7   EN/ CV G. Morard No redudency in primary cooling for ~1 w
Change of communication card on ventillation PLC SUX8 TBD   G. Morard Stop of ventillation for 10'. To be scheduled before 08:00 or after 18:00
>
>
Rich 1 and 2 gas system maintenance (membrane + recovery + purif) SG8 TBD   PH/DT S.Pavis 1h unavailibility during mambranne replacment Done
RAMSES probes in extraction ducts SX8 01/02/2010   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!) Done
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 7   EN/ CV G. Morard No redudency in primary cooling for ~1 w Ongoing
Change of communication card on ventillation PLC SUX8 Week 6   G. Morard Stop of ventillation for 10'. To be scheduled before 08:00 or after 18:00
 
Ventillation monitoring Safe Area PZ85 05/02/2010   G. Morard No impact Ongoing

Safety Systems

Revision 62010-02-05 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
--+ Shutdown activities

Infrastructure

Line: 14 to 14
 
RAMSES probes in extraction ducts SX8 01/02/2010   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!)
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 7   EN/ CV G. Morard No redudency in primary cooling for ~1 w
Change of communication card on ventillation PLC SUX8 TBD   G. Morard Stop of ventillation for 10'. To be scheduled before 08:00 or after 18:00
Changed:
<
<
>
>
Ventillation monitoring Safe Area PZ85 05/02/2010   G. Morard No impact Ongoing
 

Safety Systems

Revision 52010-02-01 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
--+ Shutdown activities

Infrastructure

Line: 9 to 9
 
SG8 / RICH1 cooling / Buffer volume SG8 Week 3 or 4 (TBC)   EN/CV (+Initiative ) No mixed water in SG for 1 day Prep
Detector Cooling - Maintenance (UPS) UX85A 04/01   EN/CV F. Corbaz All 4 Detector cooling plants off Done
Detector Cooling - Consolidation (Hydraulic ) UX85A TBD   EN/CV F. Corbaz All 4 Detector coling plants off POSTPONED
Changed:
<
<
Detector Cooling - Maintenance (Hydraulic - Leaking valve ) UX85A TBD   EN/CV F. Corbaz RICH2 off
>
>
Detector Cooling - Maintenance (Hydraulic - Leaking valve ) UX85A TBD   EN/CV F. Corbaz RICH2 off Done
 
Rich 1 and 2 gas system maintenance (membrane + recovery + purif) SG8 TBD   PH/DT S.Pavis 1h unavailibility during mambranne replacment
Changed:
<
<
RAMSES probes in extraction ducts SX8 TBD   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!)
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 4 (TBC)   EN/ CV G. Morard No redudency in primary cooling for ~1 w
>
>
RAMSES probes in extraction ducts SX8 01/02/2010   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!)
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 7   EN/ CV G. Morard No redudency in primary cooling for ~1 w
 
Change of communication card on ventillation PLC SUX8 TBD   G. Morard Stop of ventillation for 10'. To be scheduled before 08:00 or after 18:00

Safety Systems

TASK Build. DATE DOCUMENTS PERSONNEL COMMENTS STATUS
Changed:
<
<
Water Mist valve protection UX85B TBD   PH - LBO B. Chadaj Inhibit DSS and Close Safety valve on magnet PREP
>
>
Water Mist valve protection UX85B Week 4   PH - LBO B. Chadaj Inhibit DSS and Close Safety valve on magnet Done
 
IS37 test of ODH and EVAC UX85 22/12/2009   GS/SEM D. Raffour No access to UX85 Done
PZ85 latency UX85 23/12/2009   EN/HE JP Lappe No access to UX85 Done
Flammable gas Cabling SG8 05/01   EN/EL L. Roy Gas system stops (1h am and 10' pm) Done
RAMSES installation in air exhaust ducts UX85 01/02   EN/CV G.Morard Ventillation degraded in UX85. No work underground on 01/02
SNIFFER IS37 maintenance and test UX85A 8-12/02   GS/ASE D. Raffourt System not available 2h for each line - detector
Added:
>
>
CO2 system Calibration and maint. UX85A, UX85B Week 5 EDMS L. Roy On site work Done
  -- EricThomas - 04-Jan-2010 \ No newline at end of file

Revision 42010-01-20 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
--+ Shutdown activities

Infrastructure

Line: 24 to 24
 
PZ85 latency UX85 23/12/2009   EN/HE JP Lappe No access to UX85 Done
Flammable gas Cabling SG8 05/01   EN/EL L. Roy Gas system stops (1h am and 10' pm) Done
RAMSES installation in air exhaust ducts UX85 01/02   EN/CV G.Morard Ventillation degraded in UX85. No work underground on 01/02
Added:
>
>
SNIFFER IS37 maintenance and test UX85A 8-12/02   GS/ASE D. Raffourt System not available 2h for each line - detector
  -- EricThomas - 04-Jan-2010 \ No newline at end of file

Revision 32010-01-18 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
--+ Shutdown activities

Infrastructure

Line: 22 to 22
 
Water Mist valve protection UX85B TBD   PH - LBO B. Chadaj Inhibit DSS and Close Safety valve on magnet PREP
IS37 test of ODH and EVAC UX85 22/12/2009   GS/SEM D. Raffour No access to UX85 Done
PZ85 latency UX85 23/12/2009   EN/HE JP Lappe No access to UX85 Done
Changed:
<
<
Flammable gas Cabling SG8 05/01   EN/EL L. Roy Gas system stops (1h am and 10' pm) Ongoing
>
>
Flammable gas Cabling SG8 05/01   EN/EL L. Roy Gas system stops (1h am and 10' pm) Done
 
RAMSES installation in air exhaust ducts UX85 01/02   EN/CV G.Morard Ventillation degraded in UX85. No work underground on 01/02

-- EricThomas - 04-Jan-2010

Revision 22010-01-06 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
--+ Shutdown activities

Infrastructure

Changed:
<
<
TASK Build. DATE DOCUMENTS PERSONNEL COMMENTS STATUS
>
>
TASK Build. DATE DOCUMENTS PERSONNEL COMMENTS- IMPACT STATUS
 
HVAC units for D3 A and D3 B UX85A and B Weeks 2 and 3 AOC 4251907 VIC 14/12 EN/CV (+Initiative + Cerclim) - EN/EL - ALTEAD Shielding Wall Mobile blug open from 04/01 Greene nacelle needed A side Ongoing
SG8 / RICH1 cooling / Buffer volume SG8 Week 3 or 4 (TBC)   EN/CV (+Initiative ) No mixed water in SG for 1 day Prep
Detector Cooling - Maintenance (UPS) UX85A 04/01   EN/CV F. Corbaz All 4 Detector cooling plants off Done
Detector Cooling - Consolidation (Hydraulic ) UX85A TBD   EN/CV F. Corbaz All 4 Detector coling plants off POSTPONED
Changed:
<
<
Detector Cooling - Maintenance (Hydraulic - Leaking valve ) UX85A TBD   EN/CV F. Corbaz RICH2 off PREP
Rich 1 and 2 gas system maintenance (membrane + recovery + purif) SG8 TBD   PH/DT S.Pavis 1h unavailibility during mambranne replacment PREP
RAMSES probes in extraction ducts SX8 TBD   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!) TBD
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 4 (TBC)   EN/ CV G. Morard No redudency in primary cooling for ~1 w TBD
>
>
Detector Cooling - Maintenance (Hydraulic - Leaking valve ) UX85A TBD   EN/CV F. Corbaz RICH2 off
Rich 1 and 2 gas system maintenance (membrane + recovery + purif) SG8 TBD   PH/DT S.Pavis 1h unavailibility during mambranne replacment
RAMSES probes in extraction ducts SX8 TBD   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!)
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 4 (TBC)   EN/ CV G. Morard No redudency in primary cooling for ~1 w
Change of communication card on ventillation PLC SUX8 TBD   G. Morard Stop of ventillation for 10'. To be scheduled before 08:00 or after 18:00
 

Safety Systems

Line: 22 to 23
 
IS37 test of ODH and EVAC UX85 22/12/2009   GS/SEM D. Raffour No access to UX85 Done
PZ85 latency UX85 23/12/2009   EN/HE JP Lappe No access to UX85 Done
Flammable gas Cabling SG8 05/01   EN/EL L. Roy Gas system stops (1h am and 10' pm) Ongoing
Added:
>
>
RAMSES installation in air exhaust ducts UX85 01/02   EN/CV G.Morard Ventillation degraded in UX85. No work underground on 01/02
  -- EricThomas - 04-Jan-2010

Revision 12010-01-04 - EricThomas

Line: 1 to 1
Added:
>
>
META TOPICPARENT name="LHCbTechnicalCoordination"
--+ Shutdown activities

Infrastructure

TASK Build. DATE DOCUMENTS PERSONNEL COMMENTS STATUS
CV primary cooling maintenance and consolidation: SF8 by-pass + Trane 801,802 and 803 P8 Week 4 (TBC)   EN/ CV G. Morard No redudency in primary cooling for ~1 w TBD
HVAC units for D3 A and D3 B UX85A and B Weeks 2 and 3 AOC 4251907 VIC 14/12 EN/CV (+Initiative + Cerclim) - EN/EL - ALTEAD Shielding Wall Mobile blug open from 04/01 Greene nacelle needed A side Ongoing
SG8 / RICH1 cooling / Buffer volume SG8 Week 3 or 4 (TBC)   EN/CV (+Initiative ) No mixed water in SG for 1 day Prep
Detector Cooling - Maintenance (UPS) UX85A 04/01   EN/CV F. Corbaz All 4 Detector cooling plants off Done
Detector Cooling - Consolidation (Hydraulic ) UX85A TBD   EN/CV F. Corbaz All 4 Detector coling plants off POSTPONED
Detector Cooling - Maintenance (Hydraulic - Leaking valve ) UX85A TBD   EN/CV F. Corbaz RICH2 off PREP
Rich 1 and 2 gas system maintenance (membrane + recovery + purif) SG8 TBD   PH/DT S.Pavis 1h unavailibility during mambranne replacment PREP
RAMSES probes in extraction ducts SX8 TBD   EN/ CV G. Morard No air extraction in UX and SX (Limited or No work in UX!) TBD

Safety Systems

TASK Build. DATE DOCUMENTS PERSONNEL COMMENTS STATUS
Flammable gas Cabling SG8 05/01   EN/EL L. Roy Gas system stops (1h am and 10' pm) Ongoing
Water Mist valve protection UX85B TBD   PH - LBO B. Chadaj Inhibit DSS and Close Safety valve on magnet PREP
IS37 test of ODH and EVAC UX85 22/12/2009   GS/SEM D. Raffour No access to UX85 Done
PZ85 latency UX85 23/12/2009   EN/HE JP Lappe No access to UX85 Done

-- EricThomas - 04-Jan-2010

 