Site activities

Line: 11 to 11
 
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 big grin done
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   big grin done
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   big grin done
Changed:
<
<
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18 95% done Waiting for Ne tubes smile started
>
>
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18 97% Network OK and temporary lighting available smile started
 
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected big grin done
3894 Public Relation Poster Bernard 2009-09-07   big grin done
3894 Infrastructure Screen and plug bars Berni 2009-09-11   big grin done
Line: 27 to 27
 
UXB Detector Dismount OT scintillator support Cedric 2009-10-01   big grin done
UXB Detector Fixation of SAMs Gerard 2009-10-09   big grin done
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   big grin done
Changed:
<
<
SX8 Refurbishment Follow up of electricity in common lab Berni 2009-10-30   smile started
>
>
SX8 Refurbishment Follow up of electricity in common lab Berni 2009-10-30 Waiting for raacks (to come week 48) smile started
 
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   big grin done
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09 Nacelle in UX on 28-29/11 big grin done
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Surface Infrastructure Modifications to staircase daniel 2009-10-09   big grin done
SX8 Infrastructure Emergency doors daniel 2009-10-07 Round handle to be installed outside smile started
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   big grin done
Changed:
<
<
SX8 Refurbishment Painting structure daniel 2009-10-16   smile started
>
>
SX8 Refurbishment Painting structure daniel 2009-10-16   big grin done
 
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06 Start on 02/11 big grin done
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   big grin done
Changed:
<
<
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 95% smile started
>
>
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 Two labels missing (contact Rolf) smile started
 
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   big grin done
Changed:
<
<
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   smile started
>
>
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23 50% done (alim D4) smile started
 
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-27 scaffolding needed big grin done
Changed:
<
<
UXB Access RICH 2 tower modif. Cedric 2009-10-30 Waiting for rough material roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screens in conference room Gerard (+ Berni for cable) 2009-10-23 Waiting for material. 90% done smile started
>
>
UXB Access RICH 2 tower modif. Cedric 2009-10-30 Waiting for rough material. Cedric will provide an estimate of the delay. roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screens in conference room Gerard (+ Berni for cable) 2009-10-23 Waiting for material. 90% done big grin done
 
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   big grin done
UXB Detector BCAM reference points Cedric 2009-10-23   big grin done
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23 UXB before Nov 7. UXA before Nov 14 big grin done
SX8 Public Relation Staircase Olivier Callot Berni 2009-10-30   big grin done
Changed:
<
<
UXB Civil Engineering Pumping and cleaning UGC Daniel / Vallier 2009-10-28   roll eyes (sarcastic) in preparation
>
>
UXB Civil Engineering Pumping and cleaning UGC Daniel / Vallier 2009-10-28   big grin done
 
SX8 Access Common Lab, access to roof, crane, fire detection and balustarde Bernard + Daniel 2009-11-02   smile started
Changed:
<
<
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02 Material arriving. Cosmi will install roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs to common lab Bernard 2009-10-26   big grin done
>
>
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02 Material arriving. Cosmi will install. Expected for week 49 roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs to common lab Bernard 2009-10-26   smile started
 
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   big grin done
UXB Detector Lights-Muon (install protections for tubes) Daniel 2009-11-02 OK for Muon big grin done
UXB Detector Moedal detector installation Daniel 2009-11-05   big grin done
Line: 60 to 60
 
SX8 Infrastructure Cooling pipes installation in common lab Berni + Levrier 2009-11-16 Ongoing, 50% big grin done
UXB Infrastructure Telex shielding wall for Webcam Gerard 2009-11-09 After work below completed big grin done
SX8 Infrastructure New lab - Detection Incendie Bernard 2009-11-23    
Changed:
<
<
SX8 Infrastructure Barrettes de prises supplementaires+raccordement nouveau UPS online Laurent 2009-11-20   roll eyes (sarcastic) in preparation
>
>
SX8 Infrastructure Barrettes de prises supplementaires+raccordement nouveau UPS online Laurent 2009-11-20 50% (UPS still to be connected) smile started
 
SX8 Access 2eme cable a installer pour system d'acces Labo 2eme etage Laurent 2009-12-04   big grin done
Changed:
<
<
SG8 Infrastructure Connection direct Centrale detection->EXD Laurent 2009-11-20    
>
>
SG8 Infrastructure Connection direct Centrale detection->EXD Laurent 2009-11-20   smile started
 
UXA Infrastructure Connection 3 cables HV Muon a DSS + cable AUG Laurent 2009-11-20   roll eyes (sarcastic) in preparation
UXA Infrastructure Connection PLC EL-Borniers-cables pour remonter info sur synoptique surface Laurent 2009-11-27   smile started
UXB Detector Resoudre probleme de lecture Muon Turbines Laurent 2009-11-27   roll eyes (sarcastic) in preparation
Changed:
<
<
156 Detector Arrange storage for Sub detectors All 2009-11-28   roll eyes (sarcastic) in preparation
>
>
156 Detector Arrange storage for Sub detectors All 2009-11-28   smile started
 
<!--edittable1-->
<!--edittable1-->

Revision 152009-11-16 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 6 to 6
 
Changed:
<
<
<!-- /editTable -->
>
>
<!-- /editTable -->
 
Location Type Task Responsible end_DATE COMMENTS STATUS
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 big grin done
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   big grin done
Line: 15 to 15
 
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected big grin done
3894 Public Relation Poster Bernard 2009-09-07   big grin done
3894 Infrastructure Screen and plug bars Berni 2009-09-11   big grin done
Changed:
<
<
3894 Access Veranda Bernard 2009-09-25 waiting for offer roll eyes (sarcastic) in preparation
>
>
3894 Access Veranda Bernard 2009-09-25 waiting for offer smile started
 
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   big grin done
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards big grin done
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible big grin done
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-10-8   big grin done
Changed:
<
<
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 B1 remains to be done smile started
>
>
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 B1 remains to be done big grin done
 
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG big grin done
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG big grin done
Changed:
<
<
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23 B1 Muon A+C and Balcony remain to be done smile started
>
>
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23 B1 Muon A+C and Balcony remain to be done big grin done
 
UXB Detector Dismount OT scintillator support Cedric 2009-10-01   big grin done
UXB Detector Fixation of SAMs Gerard 2009-10-09   big grin done
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   big grin done
Line: 32 to 32
 
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09 Nacelle in UX on 28-29/11 big grin done
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Surface Infrastructure Modifications to staircase daniel 2009-10-09   big grin done
Changed:
<
<
SX8 Infrastructure Emergency doors daniel 2009-10-07 Rond handle to be installed outside smile started
>
>
SX8 Infrastructure Emergency doors daniel 2009-10-07 Round handle to be installed outside smile started
 
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   big grin done
SX8 Refurbishment Painting structure daniel 2009-10-16   smile started
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
Changed:
<
<
UXB Infrastructure Painting ground daniel 2009-11-06 Start on 02/11 roll eyes (sarcastic) in preparation
>
>
UXB Infrastructure Painting ground daniel 2009-11-06 Start on 02/11 big grin done
 
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   big grin done
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 95% smile started
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   big grin done
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   smile started
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-27 scaffolding needed big grin done
Changed:
<
<
UXB Access RICH 2 tower mofif. Cedric 2009-10-30 Waiting for rough material roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screens in conference room Gerard (+ Berni for cable) 2009-10-23 Waiting for material. 90% done roll eyes (sarcastic) in preparation
>
>
UXB Access RICH 2 tower modif. Cedric 2009-10-30 Waiting for rough material roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screens in conference room Gerard (+ Berni for cable) 2009-10-23 Waiting for material. 90% done smile started
 
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   big grin done
Changed:
<
<
UXB Detector BCAM reference points Cedric 2009-10-23   smile started
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23 UXB before Nov 7. UXA before Nov 14 roll eyes (sarcastic) in preparation
SX8 Public Relation Staircase Olivier Callot Berni 2009-10-30 95% done smile started
>
>
UXB Detector BCAM reference points Cedric 2009-10-23   big grin done
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23 UXB before Nov 7. UXA before Nov 14 big grin done
SX8 Public Relation Staircase Olivier Callot Berni 2009-10-30   big grin done
 
UXB Civil Engineering Pumping and cleaning UGC Daniel / Vallier 2009-10-28   roll eyes (sarcastic) in preparation
SX8 Access Common Lab, access to roof, crane, fire detection and balustarde Bernard + Daniel 2009-11-02   smile started
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02 Material arriving. Cosmi will install roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs to common lab Bernard 2009-10-26   big grin done
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   big grin done
Changed:
<
<
UXB Detector Lights-Muon (install protections for tubes) Daniel 2009-11-02 OK for Muon roll eyes (sarcastic) in preparation
UXB Detector Moedal detector installation Daniel 2009-11-05   roll eyes (sarcastic) in preparation
UXB Detector Fixation of 2 additional SAMs (gantry + water mist Gerard 2009-11-09   roll eyes (sarcastic) in preparation
SX8 Refurbishment New lab: reinstallation of pnone lines Berni 2009-11-09   roll eyes (sarcastic) in preparation
SX8 Infrastructure Cooling pipes installation in common lab Berni + Levrier 2009-11-16 Ongoing, 50% smile started
UXB Infrastructure Telex shielding wall for Webcam Gerard 2009-11-09 After work below completed roll eyes (sarcastic) in preparation
>
>
UXB Detector Lights-Muon (install protections for tubes) Daniel 2009-11-02 OK for Muon big grin done
UXB Detector Moedal detector installation Daniel 2009-11-05   big grin done
UXB Detector Fixation of 2 additional SAMs (gantry + water mist Gerard 2009-11-09 missing label big grin done
SX8 Refurbishment New lab: reinstallation of pnone lines Berni 2009-11-09   smile started
SX8 Infrastructure Cooling pipes installation in common lab Berni + Levrier 2009-11-16 Ongoing, 50% big grin done
UXB Infrastructure Telex shielding wall for Webcam Gerard 2009-11-09 After work below completed big grin done
 
SX8 Infrastructure New lab - Detection Incendie Bernard 2009-11-23    
SX8 Infrastructure Barrettes de prises supplementaires+raccordement nouveau UPS online Laurent 2009-11-20   roll eyes (sarcastic) in preparation
Changed:
<
<
SX8 Access 2eme cable a installer pour system d'acces Labo 2eme etage Laurent 2009-12-04   roll eyes (sarcastic) in preparation
>
>
SX8 Access 2eme cable a installer pour system d'acces Labo 2eme etage Laurent 2009-12-04   big grin done
 
SG8 Infrastructure Connection direct Centrale detection->EXD Laurent 2009-11-20    
UXA Infrastructure Connection 3 cables HV Muon a DSS + cable AUG Laurent 2009-11-20   roll eyes (sarcastic) in preparation
UXA Infrastructure Connection PLC EL-Borniers-cables pour remonter info sur synoptique surface Laurent 2009-11-27   smile started
UXB Detector Resoudre probleme de lecture Muon Turbines Laurent 2009-11-27   roll eyes (sarcastic) in preparation
Added:
>
>
156 Detector Arrange storage for Sub detectors All 2009-11-28   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 142009-11-13 - LaurentROY

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 29 to 29
 
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   big grin done
SX8 Refurbishment Follow up of electricity in common lab Berni 2009-10-30   smile started
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   big grin done
Changed:
<
<
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09 Nacelle in UX on 28-29/11 smile started
>
>
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09 Nacelle in UX on 28-29/11 big grin done
 
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Surface Infrastructure Modifications to staircase daniel 2009-10-09   big grin done
SX8 Infrastructure Emergency doors daniel 2009-10-07 Rond handle to be installed outside smile started
Line: 38 to 38
 
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06 Start on 02/11 roll eyes (sarcastic) in preparation
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   big grin done
Changed:
<
<
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 50% smile started
>
>
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 95% smile started
 
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   big grin done
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   smile started
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-27 scaffolding needed big grin done
Line: 52 to 52
 
SX8 Access Common Lab, access to roof, crane, fire detection and balustarde Bernard + Daniel 2009-11-02   smile started
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02 Material arriving. Cosmi will install roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs to common lab Bernard 2009-10-26   big grin done
Changed:
<
<
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   smile started
>
>
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   big grin done
 
UXB Detector Lights-Muon (install protections for tubes) Daniel 2009-11-02 OK for Muon roll eyes (sarcastic) in preparation
UXB Detector Moedal detector installation Daniel 2009-11-05   roll eyes (sarcastic) in preparation
UXB Detector Fixation of 2 additional SAMs (gantry + water mist Gerard 2009-11-09   roll eyes (sarcastic) in preparation
Line: 60 to 60
 
SX8 Infrastructure Cooling pipes installation in common lab Berni + Levrier 2009-11-16 Ongoing, 50% smile started
UXB Infrastructure Telex shielding wall for Webcam Gerard 2009-11-09 After work below completed roll eyes (sarcastic) in preparation
SX8 Infrastructure New lab - Detection Incendie Bernard 2009-11-23    
Added:
>
>
SX8 Infrastructure Barrettes de prises supplementaires+raccordement nouveau UPS online Laurent 2009-11-20   roll eyes (sarcastic) in preparation
SX8 Access 2eme cable a installer pour system d'acces Labo 2eme etage Laurent 2009-12-04   roll eyes (sarcastic) in preparation
SG8 Infrastructure Connection direct Centrale detection->EXD Laurent 2009-11-20    
UXA Infrastructure Connection 3 cables HV Muon a DSS + cable AUG Laurent 2009-11-20   roll eyes (sarcastic) in preparation
UXA Infrastructure Connection PLC EL-Borniers-cables pour remonter info sur synoptique surface Laurent 2009-11-27   smile started
UXB Detector Resoudre probleme de lecture Muon Turbines Laurent 2009-11-27   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 132009-11-02 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 11 to 11
 
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 big grin done
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   big grin done
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   big grin done
Changed:
<
<
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18 95% done smile started
>
>
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18 95% done Waiting for Ne tubes smile started
 
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected big grin done
3894 Public Relation Poster Bernard 2009-09-07   big grin done
3894 Infrastructure Screen and plug bars Berni 2009-09-11   big grin done
Line: 23 to 23
 
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 B1 remains to be done smile started
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG big grin done
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG big grin done
Changed:
<
<
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23 B1 and Muon-C remain to be done smile started
>
>
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23 B1 Muon A+C and Balcony remain to be done smile started
 
UXB Detector Dismount OT scintillator support Cedric 2009-10-01   big grin done
UXB Detector Fixation of SAMs Gerard 2009-10-09   big grin done
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   big grin done
Changed:
<
<
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30   smile started
>
>
SX8 Refurbishment Follow up of electricity in common lab Berni 2009-10-30   smile started
 
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   big grin done
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09 Nacelle in UX on 28-29/11 smile started
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Line: 37 to 37
 
SX8 Refurbishment Painting structure daniel 2009-10-16   smile started
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06 Start on 02/11 roll eyes (sarcastic) in preparation
Changed:
<
<
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   smile started
>
>
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   big grin done
 
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 50% smile started
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   big grin done
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   smile started
Changed:
<
<
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-27 scaffolding needed roll eyes (sarcastic) in preparation
>
>
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-27 scaffolding needed big grin done
 
UXB Access RICH 2 tower mofif. Cedric 2009-10-30 Waiting for rough material roll eyes (sarcastic) in preparation
Changed:
<
<
3894 Refurbishment 3 Screens in cnference room Gerard 2009-10-23 Waiting for material. roll eyes (sarcastic) in preparation
>
>
3894 Refurbishment 3 Screens in conference room Gerard (+ Berni for cable) 2009-10-23 Waiting for material. 90% done roll eyes (sarcastic) in preparation
 
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   big grin done
UXB Detector BCAM reference points Cedric 2009-10-23   smile started
Changed:
<
<
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23 After the magnet leak fix roll eyes (sarcastic) in preparation
>
>
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23 UXB before Nov 7. UXA before Nov 14 roll eyes (sarcastic) in preparation
 
SX8 Public Relation Staircase Olivier Callot Berni 2009-10-30 95% done smile started
UXB Civil Engineering Pumping and cleaning UGC Daniel / Vallier 2009-10-28   roll eyes (sarcastic) in preparation
SX8 Access Common Lab, access to roof, crane, fire detection and balustarde Bernard + Daniel 2009-11-02   smile started
Changed:
<
<
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02   roll eyes (sarcastic) in preparation
>
>
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02 Material arriving. Cosmi will install roll eyes (sarcastic) in preparation
 
SX8 Refurbishment Stairs to common lab Bernard 2009-10-26   big grin done
Changed:
<
<
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   roll eyes (sarcastic) in preparation
>
>
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   smile started
 
UXB Detector Lights-Muon (install protections for tubes) Daniel 2009-11-02 OK for Muon roll eyes (sarcastic) in preparation
UXB Detector Moedal detector installation Daniel 2009-11-05   roll eyes (sarcastic) in preparation
Added:
>
>
UXB Detector Fixation of 2 additional SAMs (gantry + water mist Gerard 2009-11-09   roll eyes (sarcastic) in preparation
SX8 Refurbishment New lab: reinstallation of pnone lines Berni 2009-11-09   roll eyes (sarcastic) in preparation
SX8 Infrastructure Cooling pipes installation in common lab Berni + Levrier 2009-11-16 Ongoing, 50% smile started
UXB Infrastructure Telex shielding wall for Webcam Gerard 2009-11-09 After work below completed roll eyes (sarcastic) in preparation
SX8 Infrastructure New lab - Detection Incendie Bernard 2009-11-23    
 
<!--edittable1-->
<!--edittable1-->

Revision 122009-10-26 - EricThomas

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 11 to 11
 
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 big grin done
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   big grin done
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   big grin done
Changed:
<
<
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18   smile started
>
>
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18 95% done smile started
 
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected big grin done
3894 Public Relation Poster Bernard 2009-09-07   big grin done
Changed:
<
<
3894 Infrastructure Screen and plug bars Berni 2009-09-11   smile started
>
>
3894 Infrastructure Screen and plug bars Berni 2009-09-11   big grin done
 
3894 Access Veranda Bernard 2009-09-25 waiting for offer roll eyes (sarcastic) in preparation
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   big grin done
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards big grin done
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible big grin done
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-10-8   big grin done
Changed:
<
<
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 Regularly check to be performed smile started
>
>
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 B1 remains to be done smile started
 
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG big grin done
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG big grin done
Changed:
<
<
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23   smile started
>
>
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23 B1 and Muon-C remain to be done smile started
 
UXB Detector Dismount OT scintillator support Cedric 2009-10-01   big grin done
Changed:
<
<
UXB Detector Fixation of SAMs Gerard 2009-10-09   smile started
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   smile started
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30   roll eyes (sarcastic) in preparation
>
>
UXB Detector Fixation of SAMs Gerard 2009-10-09   big grin done
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   big grin done
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30   smile started
 
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   big grin done
Changed:
<
<
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09   roll eyes (sarcastic) in preparation
>
>
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09 Nacelle in UX on 28-29/11 smile started
 
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Surface Infrastructure Modifications to staircase daniel 2009-10-09   big grin done
Changed:
<
<
SX8 Infrastructure Emergency doors daniel 2009-10-07   smile started
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   smile started
SX8 Refurbishment Painting structure daniel 2009-10-16   roll eyes (sarcastic) in preparation
>
>
SX8 Infrastructure Emergency doors daniel 2009-10-07 Rond handle to be installed outside smile started
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   big grin done
SX8 Refurbishment Painting structure daniel 2009-10-16   smile started
 
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
Changed:
<
<
UXB Infrastructure Painting ground daniel 2009-11-06   roll eyes (sarcastic) in preparation
>
>
UXB Infrastructure Painting ground daniel 2009-11-06 Start on 02/11 roll eyes (sarcastic) in preparation
 
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   smile started
Changed:
<
<
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16   smile started
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   roll eyes (sarcastic) in preparation
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   roll eyes (sarcastic) in preparation
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-22 scaffolding needed roll eyes (sarcastic) in preparation
UXB Access RICH 2 tower mofif. Cedric 2009-10-30   roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screen in cnference room Gerard 2009-10-23   roll eyes (sarcastic) in preparation
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   roll eyes (sarcastic) in preparation
UXB Detector BCAM reference points Cedric 2009-10-23   roll eyes (sarcastic) in preparation
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23   roll eyes (sarcastic) in preparation
>
>
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 50% smile started
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   big grin done
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   smile started
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-27 scaffolding needed roll eyes (sarcastic) in preparation
UXB Access RICH 2 tower mofif. Cedric 2009-10-30 Waiting for rough material roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screens in cnference room Gerard 2009-10-23 Waiting for material. roll eyes (sarcastic) in preparation
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   big grin done
UXB Detector BCAM reference points Cedric 2009-10-23   smile started
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23 After the magnet leak fix roll eyes (sarcastic) in preparation
SX8 Public Relation Staircase Olivier Callot Berni 2009-10-30 95% done smile started
UXB Civil Engineering Pumping and cleaning UGC Daniel / Vallier 2009-10-28   roll eyes (sarcastic) in preparation
SX8 Access Common Lab, access to roof, crane, fire detection and balustarde Bernard + Daniel 2009-11-02   smile started
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02   roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs to common lab Bernard 2009-10-26   big grin done
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   roll eyes (sarcastic) in preparation
UXB Detector Lights-Muon (install protections for tubes) Daniel 2009-11-02 OK for Muon roll eyes (sarcastic) in preparation
UXB Detector Moedal detector installation Daniel 2009-11-05   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 112009-10-12 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 46 to 46
 
3894 Refurbishment 3 Screen in cnference room Gerard 2009-10-23   roll eyes (sarcastic) in preparation
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   roll eyes (sarcastic) in preparation
UXB Detector BCAM reference points Cedric 2009-10-23   roll eyes (sarcastic) in preparation
Added:
>
>
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 102009-10-12 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 19 to 19
 
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   big grin done
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards big grin done
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible big grin done
Changed:
<
<
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-10-8   smile started
>
>
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-10-8   big grin done
 
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 Regularly check to be performed smile started
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG big grin done
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG big grin done
Line: 31 to 31
 
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   big grin done
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09   roll eyes (sarcastic) in preparation
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Changed:
<
<
Surface Infrastructure Modifications to staircase daniel 2009-10-09   smile started
SX8 Infrastructure Emergency doors daniel 2009-10-07   roll eyes (sarcastic) in preparation
>
>
Surface Infrastructure Modifications to staircase daniel 2009-10-09   big grin done
SX8 Infrastructure Emergency doors daniel 2009-10-07   smile started
 
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   smile started
SX8 Refurbishment Painting structure daniel 2009-10-16   roll eyes (sarcastic) in preparation
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06   roll eyes (sarcastic) in preparation
Changed:
<
<
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   roll eyes (sarcastic) in preparation
>
>
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   smile started
 
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16   smile started
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   roll eyes (sarcastic) in preparation
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   roll eyes (sarcastic) in preparation
Added:
>
>
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-22 scaffolding needed roll eyes (sarcastic) in preparation
UXB Access RICH 2 tower mofif. Cedric 2009-10-30   roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screen in cnference room Gerard 2009-10-23   roll eyes (sarcastic) in preparation
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   roll eyes (sarcastic) in preparation
UXB Detector BCAM reference points Cedric 2009-10-23   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 92009-10-09 - LaurentROY

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 28 to 28
 
UXB Detector Fixation of SAMs Gerard 2009-10-09   smile started
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   smile started
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30   roll eyes (sarcastic) in preparation
Changed:
<
<
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   smile started
>
>
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   big grin done
 
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09   roll eyes (sarcastic) in preparation
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Surface Infrastructure Modifications to staircase daniel 2009-10-09   smile started
Line: 38 to 38
 
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06   roll eyes (sarcastic) in preparation
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   roll eyes (sarcastic) in preparation
Added:
>
>
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16   smile started
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   roll eyes (sarcastic) in preparation
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 82009-10-07 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 20 to 20
 
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards big grin done
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible big grin done
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-10-8   smile started
Changed:
<
<
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 Regularly check to be performed roll eyes (sarcastic) in preparation
>
>
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 Regularly check to be performed smile started
 
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG big grin done
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG big grin done
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23   smile started
Changed:
<
<
UXB Detector Dismount OT scintillator support Cedric 2009-10-01    
>
>
UXB Detector Dismount OT scintillator support Cedric 2009-10-01   big grin done
 
UXB Detector Fixation of SAMs Gerard 2009-10-09   smile started
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   smile started
Changed:
<
<
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30    
>
>
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30   roll eyes (sarcastic) in preparation
 
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   smile started
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09   roll eyes (sarcastic) in preparation
Changed:
<
<
Underground Civil Engineering Cutting plates in UGX Berni 2009-10-07   roll eyes (sarcastic) in preparation
>
>
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
 
Surface Infrastructure Modifications to staircase daniel 2009-10-09   smile started
SX8 Infrastructure Emergency doors daniel 2009-10-07   roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   smile started

Revision 72009-10-01 - LaurentROY

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 29 to 29
 
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   smile started
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30    
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   smile started
Changed:
<
<
Underground Infrastructure Cables from UX85 A to B Laurent 2009-10-09   smile started
>
>
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09   roll eyes (sarcastic) in preparation
 
Underground Civil Engineering Cutting plates in UGX Berni 2009-10-07   roll eyes (sarcastic) in preparation
Surface Infrastructure Modifications to staircase daniel 2009-10-09   smile started
SX8 Infrastructure Emergency doors daniel 2009-10-07   roll eyes (sarcastic) in preparation
Line: 37 to 37
 
SX8 Refurbishment Painting structure daniel 2009-10-16   roll eyes (sarcastic) in preparation
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06   roll eyes (sarcastic) in preparation
Added:
>
>
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 62009-10-01 - DanLACARRERE

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 31 to 31
 
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   smile started
Underground Infrastructure Cables from UX85 A to B Laurent 2009-10-09   smile started
Underground Civil Engineering Cutting plates in UGX Berni 2009-10-07   roll eyes (sarcastic) in preparation
Added:
>
>
Surface Infrastructure Modifications to staircase daniel 2009-10-09   smile started
SX8 Infrastructure Emergency doors daniel 2009-10-07   roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   smile started
SX8 Refurbishment Painting structure daniel 2009-10-16   roll eyes (sarcastic) in preparation
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 52009-10-01 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 8 to 8
 

<!-- /editTable -->
Changed:
<
<
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 smile started
>
>
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 big grin done
 
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   big grin done
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   big grin done
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18   smile started
Line: 18 to 18
 
3894 Access Veranda Bernard 2009-09-25 waiting for offer roll eyes (sarcastic) in preparation
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   big grin done
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards big grin done
Changed:
<
<
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible roll eyes (sarcastic) in preparation
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-09-15   smile started
>
>
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible big grin done
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-10-8   smile started
 
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 Regularly check to be performed roll eyes (sarcastic) in preparation
Changed:
<
<
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG roll eyes (sarcastic) in preparation
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG roll eyes (sarcastic) in preparation
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23   roll eyes (sarcastic) in preparation
>
>
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG big grin done
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG big grin done
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23   smile started
UXB Detector Dismount OT scintillator support Cedric 2009-10-01    
UXB Detector Fixation of SAMs Gerard 2009-10-09   smile started
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   smile started
SX8 Refurbishment Folow up of electricity in common lab Berni 2009-10-30    
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   smile started
Underground Infrastructure Cables from UX85 A to B Laurent 2009-10-09   smile started
Underground Civil Engineering Cutting plates in UGX Berni 2009-10-07   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 42009-09-16 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 21 to 21
 
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible roll eyes (sarcastic) in preparation
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-09-15   smile started
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 Regularly check to be performed roll eyes (sarcastic) in preparation
Changed:
<
<
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16   roll eyes (sarcastic) in preparation
>
>
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG roll eyes (sarcastic) in preparation
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG roll eyes (sarcastic) in preparation
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 32009-09-15 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 9 to 9
 
Location Type Task Responsible end_DATE COMMENTS STATUS
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 smile started
<!-- /editTable -->
Changed:
<
<
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   smile started
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   roll eyes (sarcastic) in preparation
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18   roll eyes (sarcastic) in preparation
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected roll eyes (sarcastic) in preparation
>
>
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   big grin done
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   big grin done
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18   smile started
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected big grin done
 
3894 Public Relation Poster Bernard 2009-09-07   big grin done
3894 Infrastructure Screen and plug bars Berni 2009-09-11   smile started
3894 Access Veranda Bernard 2009-09-25 waiting for offer roll eyes (sarcastic) in preparation
Changed:
<
<
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   smile started
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards smile started
>
>
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   big grin done
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards big grin done
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible roll eyes (sarcastic) in preparation
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-09-15   smile started
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 Regularly check to be performed roll eyes (sarcastic) in preparation
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16   roll eyes (sarcastic) in preparation
 
<!--edittable1-->
<!--edittable1-->

Revision 22009-09-08 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

Line: 8 to 8
 

<!-- /editTable -->
Changed:
<
<
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 Side A completed: 9-9-09 smile started
SX8 Infrastructure Labo installation 2nd floor Bernard Co. 2009-09-11   smile started
>
>
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 smile started
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   smile started
 
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   roll eyes (sarcastic) in preparation
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18   roll eyes (sarcastic) in preparation
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected roll eyes (sarcastic) in preparation
Changed:
<
<
3894 Public Relation Poster Bernard 2009-09-07   smile started
>
>
3894 Public Relation Poster Bernard 2009-09-07   big grin done
 
3894 Infrastructure Screen and plug bars Berni 2009-09-11   smile started
3894 Access Veranda Bernard 2009-09-25 waiting for offer roll eyes (sarcastic) in preparation
Changed:
<
<
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-07   roll eyes (sarcastic) in preparation
>
>
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   smile started
 
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards smile started
<!--edittable1-->
<!--edittable1-->

Revision 12009-09-07 - RolfLindner

Line: 1 to 1
Added:
>
>
META TOPICPARENT name="LHCbTechnicalCoordination"
-- RolfLindner - 2009-09-07

Site activities

General support

Location Type Task Responsible end_DATE COMMENTS STATUS
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 Side A completed: 9-9-09 smile started
SX8 Infrastructure Labo installation 2nd floor Bernard Co. 2009-09-11   smile started
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   roll eyes (sarcastic) in preparation
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18   roll eyes (sarcastic) in preparation
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected roll eyes (sarcastic) in preparation
3894 Public Relation Poster Bernard 2009-09-07   smile started
3894 Infrastructure Screen and plug bars Berni 2009-09-11   smile started
3894 Access Veranda Bernard 2009-09-25 waiting for offer roll eyes (sarcastic) in preparation
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-07   roll eyes (sarcastic) in preparation
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards smile started
<!-- /editTable -->
<!--edittable1-->
<!--edittable1-->

-- RolfLindner - 05 Jan 2009

 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2019 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback