Difference: MilestonesList (1 vs. 25)

Revision 252018-11-27 - BlakeLeverington

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old

Revision 242016-05-09 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 33 to 33
 
RICH RICH1 Mechanics "EDR incl Gas encl. Phot boxes Phot funnel Interfaces" May-15 Feb-16 27 0 0  
RICH RICH2 mechanics EDR Nov-15 Feb-16 28 0 0  
UPSTREAM TRACKER Sensor SENSOR PRR Dec-15 Feb-16 29 0 0  
Changed:
<
<
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Jul-15 Feb-16 30 1 21  
DATA PROCESSING Optical fibres Long distance operational reliability Feb-16 Feb-16 31 1 22  
SCIFI "Fibres mats modules" Fibre mat PRR Jan-16 Mar-16 32 0 0  
>
>
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Jul-15 Feb-16 30 1 22  
DATA PROCESSING Optical fibres Long distance operational reliability Feb-16 Feb-16 31 1 23  
SCIFI "Fibres mats modules" Fibre mat PRR Jan-16 Mar-16 32 1 25  
 
UPSTREAM TRACKER Integration UT Box and frame EDR Mar-16 Mar-16 33 0 0  
MUON additional shielding EDR Oct-15 Apr-16 34 0 0  
Changed:
<
<
SCIFI SiPM + Electronics + ROB Joint EDR Dec-15 Apr-16 35 0 0  
>
>
SCIFI SiPM + Electronics + ROB Joint EDR Dec-15 Apr-16 35 1 26  
 
UPSTREAM TRACKER ELECTRONICS PEPI/DCB EDR Jan-16 Apr-16 36 0 0  
Changed:
<
<
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Oct-15 May-16 37 1 23  
>
>
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Oct-15 May-16 37 1 24  
 
RICH Photon Detector Module "EDR Optoelectronic chain module + assembly" Mar-15 May-16 38 0 0  
RICH Digital board "EDR DB hardware with basic firmware + ECS " Jan-15 May-16 39 0 0  
SCIFI "Fibres mats modules" Module PRR Mar-16 May-16 40 0 0  
Line: 134 to 134
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
milestones 2 2 2 3 3 5 9 12 13 13 13 15 21 21 23 31 33 36 44 50 50 51 57 59 61 66 71 71 79 82 85 86 87 90 90 92 95 95 96 97 99 100 101 102 104 106 106 106 107 107 109 110 112 115 115 116 117 117 117 117 117 118 118 118 118 119 119 119 120
Changed:
<
<
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21 22 22 23
>
>
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21 22 22 23 25 26
 -- RolfLindner - 2015-11-24 \ No newline at end of file

Revision 232016-03-02 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 40 to 40
 
MUON additional shielding EDR Oct-15 Apr-16 34 0 0  
SCIFI SiPM + Electronics + ROB Joint EDR Dec-15 Apr-16 35 0 0  
UPSTREAM TRACKER ELECTRONICS PEPI/DCB EDR Jan-16 Apr-16 36 0 0  
Changed:
<
<
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Oct-15 May-16 37 0 0  
>
>
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Oct-15 May-16 37 1 23  
 
RICH Photon Detector Module "EDR Optoelectronic chain module + assembly" Mar-15 May-16 38 0 0  
RICH Digital board "EDR DB hardware with basic firmware + ECS " Jan-15 May-16 39 0 0  
SCIFI "Fibres mats modules" Module PRR Mar-16 May-16 40 0 0  
Line: 134 to 134
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
milestones 2 2 2 3 3 5 9 12 13 13 13 15 21 21 23 31 33 36 44 50 50 51 57 59 61 66 71 71 79 82 85 86 87 90 90 92 95 95 96 97 99 100 101 102 104 106 106 106 107 107 109 110 112 115 115 116 117 117 117 117 117 118 118 118 118 119 119 119 120
Changed:
<
<
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21 22 22
>
>
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21 22 22 23
 -- RolfLindner - 2015-11-24

Revision 222016-02-29 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 33 to 33
 
RICH RICH1 Mechanics "EDR incl Gas encl. Phot boxes Phot funnel Interfaces" May-15 Feb-16 27 0 0  
RICH RICH2 mechanics EDR Nov-15 Feb-16 28 0 0  
UPSTREAM TRACKER Sensor SENSOR PRR Dec-15 Feb-16 29 0 0  
Changed:
<
<
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Jul-15 Feb-16 30 0 0  
DATA PROCESSING Optical fibres Long distance operational reliability Feb-16 Feb-16 31 0 0  
>
>
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Jul-15 Feb-16 30 1 21  
DATA PROCESSING Optical fibres Long distance operational reliability Feb-16 Feb-16 31 1 22  
 
SCIFI "Fibres mats modules" Fibre mat PRR Jan-16 Mar-16 32 0 0  
UPSTREAM TRACKER Integration UT Box and frame EDR Mar-16 Mar-16 33 0 0  
MUON additional shielding EDR Oct-15 Apr-16 34 0 0  
Line: 134 to 134
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
milestones 2 2 2 3 3 5 9 12 13 13 13 15 21 21 23 31 33 36 44 50 50 51 57 59 61 66 71 71 79 82 85 86 87 90 90 92 95 95 96 97 99 100 101 102 104 106 106 106 107 107 109 110 112 115 115 116 117 117 117 117 117 118 118 118 118 119 119 119 120
Changed:
<
<
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21 23 23
>
>
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21 22 22
 -- RolfLindner - 2015-11-24

Revision 212016-02-27 - GiovanniPassaleva

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 24 to 24
 
MUON nPDM EDR Jun-15 Nov-15 18 1 17  
MUON nSB EDR Jun-15 Nov-15 19 1 18  
VELO electronics hybrid EDR Jul-15 Nov-15 20 1 19  
Changed:
<
<
VELO electronics Velopix submission 1 Nov-15 Nov-15 21 0 20  
>
>
VELO electronics Velopix submission 1 Nov-15 Nov-15 21 0 0  
 
RICH CLARO + Front-End Board PRR Jan-15 Jan-16 22 0 0  
Changed:
<
<
UPSTREAM TRACKER Integration Cooling EDR Oct-15 Jan-16 23 0 21  
>
>
UPSTREAM TRACKER Integration Cooling EDR Oct-15 Jan-16 23 1 20  
 
DATA PROCESSING Trigger "1st Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)" Feb-16 Feb-16 24 0 0  
Changed:
<
<
MUON nSYNC prototype submission Jul-15 Feb-16 25 0 0  
>
>
MUON nSYNC prototype submission Jul-15 Feb-16 25 1 21  
 
RICH Elementary Cell PRR Jan-15 Feb-16 26 0 0  
RICH RICH1 Mechanics "EDR incl Gas encl. Phot boxes Phot funnel Interfaces" May-15 Feb-16 27 0 0  
RICH RICH2 mechanics EDR Nov-15 Feb-16 28 0 0  
Line: 128 to 128
 
<!--edittable1-->

ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.

Changed:
<
<
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
>
>
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
 

year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
milestones 2 2 2 3 3 5 9 12 13 13 13 15 21 21 23 31 33 36 44 50 50 51 57 59 61 66 71 71 79 82 85 86 87 90 90 92 95 95 96 97 99 100 101 102 104 106 106 106 107 107 109 110 112 115 115 116 117 117 117 117 117 118 118 118 118 119 119 119 120
Changed:
<
<
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21
>
>
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21 23 23
 -- RolfLindner - 2015-11-24

Revision 202015-12-10 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 127 to 127
 
<!--edittable1-->
Changed:
<
<
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
>
>
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
 

Revision 192015-12-09 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 127 to 127
 
<!--edittable1-->
Changed:
<
<
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
>
>
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
 

Revision 182015-12-08 - GiovanniPassaleva

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 26 to 26
 
VELO electronics hybrid EDR Jul-15 Nov-15 20 1 19  
VELO electronics Velopix submission 1 Nov-15 Nov-15 21 0 20  
RICH CLARO + Front-End Board PRR Jan-15 Jan-16 22 0 0  
Changed:
<
<
UPSTREAM TRACKER Integration Cooling EDR Oct-15 Jan-16 23 0 0  
>
>
UPSTREAM TRACKER Integration Cooling EDR Oct-15 Jan-16 23 0 21  
 
DATA PROCESSING Trigger "1st Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)" Feb-16 Feb-16 24 0 0  
MUON nSYNC prototype submission Jul-15 Feb-16 25 0 0  
RICH Elementary Cell PRR Jan-15 Feb-16 26 0 0  
Line: 134 to 134
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
milestones 2 2 2 3 3 5 9 12 13 13 13 15 21 21 23 31 33 36 44 50 50 51 57 59 61 66 71 71 79 82 85 86 87 90 90 92 95 95 96 97 99 100 101 102 104 106 106 106 107 107 109 110 112 115 115 116 117 117 117 117 117 118 118 118 118 119 119 119 120
Changed:
<
<
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 20
>
>
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 21 21
 -- RolfLindner - 2015-11-24

Revision 172015-11-27 - GiovanniPassaleva

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old
Line: 18 to 18
 
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jun-15 Jun-15 12 1 12 https://indico.cern.ch/event/394628/
VELO electronics ASIC EDR Jul-15 Jul-15 13 1 13  
RICH MaPMT Place MaPMT order and start production Mar-15 Oct-15 14 1 14  
Changed:
<
<
VELO cooling substrate Cooling Substrate EDR Jun-15 Oct-15 15 0 14  
>
>
VELO cooling substrate Cooling Substrate EDR Jun-15 Oct-15 15 1 14  
 
MUON nSYNC EDR Jun-15 Nov-15 16 1 15  
MUON nODE EDR Jun-15 Nov-15 17 1 16  
MUON nPDM EDR Jun-15 Nov-15 18 1 17  

Revision 162015-11-24 - GiovanniPassaleva

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
Changed:
<
<
* Milestones as project planning old
>
>
* Milestones as project planning old
 
SYSTEM item milestone 2014 Sept-2015 number fraction achieved integral comment
RICH CLARO + Front-End Board "EDR 7th of Oct" Oct-14 Oct-14 1 1 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell "EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Oct-14 Oct-14 2 1 2 https://indico.cern.ch/event/344560/
MUON Spare MWPC start production (PRR) Feb-15 Feb-15 3 1 3 24-Feb
<!-- /editTable -->
Changed:
<
<
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) Apr-15 Apr-15 4 1 4 https://indico.cern.ch/event/406444/
>
>
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) Apr-15 Apr-15 4 1 4 https://indico.cern.ch/event/406444/
 
CALORIMETER Front-End ASIC EDR Apr-15 Apr-15 5 1 5 was 24 April
VELO sensors Sensor and thinned bump bonding EDR Apr-15 May-15 6 1 6 https://indico.cern.ch/event/396256/timetable/#20150601
UPSTREAM TRACKER SALT Chip SALT EDR May-15 May-15 7 1 7 https://indico.cern.ch/event/394628/
Line: 18 to 19
 
VELO electronics ASIC EDR Jul-15 Jul-15 13 1 13  
RICH MaPMT Place MaPMT order and start production Mar-15 Oct-15 14 1 14  
VELO cooling substrate Cooling Substrate EDR Jun-15 Oct-15 15 0 14  
Changed:
<
<
MUON nSYNC EDR Jun-15 Nov-15 16 0 14  
MUON nODE EDR Jun-15 Nov-15 17 0 14  
MUON nPDM EDR Jun-15 Nov-15 18 0 14  
MUON nSB EDR Jun-15 Nov-15 19 0 14  
VELO electronics hybrid EDR Jul-15 Nov-15 20 0 14  
VELO electronics Velopix submission 1 Nov-15 Nov-15 21 0 14  
>
>
MUON nSYNC EDR Jun-15 Nov-15 16 1 15  
MUON nODE EDR Jun-15 Nov-15 17 1 16  
MUON nPDM EDR Jun-15 Nov-15 18 1 17  
MUON nSB EDR Jun-15 Nov-15 19 1 18  
VELO electronics hybrid EDR Jul-15 Nov-15 20 1 19  
VELO electronics Velopix submission 1 Nov-15 Nov-15 21 0 20  
 
RICH CLARO + Front-End Board PRR Jan-15 Jan-16 22 0 0  
UPSTREAM TRACKER Integration Cooling EDR Oct-15 Jan-16 23 0 0  
DATA PROCESSING Trigger "1st Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)" Feb-16 Feb-16 24 0 0  
Line: 136 to 134
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
milestones 2 2 2 3 3 5 9 12 13 13 13 15 21 21 23 31 33 36 44 50 50 51 57 59 61 66 71 71 79 82 85 86 87 90 90 92 95 95 96 97 99 100 101 102 104 106 106 106 107 107 109 110 112 115 115 116 117 117 117 117 117 118 118 118 118 119 119 119 120
Changed:
<
<
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 14

>
>
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 20
 
Deleted:
<
<
-- RolfLindner - 2014-12-08
 \ No newline at end of file
Added:
>
>
-- RolfLindner - 2015-11-24

Revision 152015-11-23 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning old

<!-- /editTable -->

Revision 142015-11-20 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
Changed:
<
<
* Milestones as project planning
>
>
* Milestones as project planning old
 
<!-- /editTable -->
Added:
>
>
SYSTEM item milestone 2014 Sept-2015 number fraction achieved integral comment
RICH CLARO + Front-End Board "EDR 7th of Oct" Oct-14 Oct-14 1 1 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell "EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Oct-14 Oct-14 2 1 2 https://indico.cern.ch/event/344560/
MUON Spare MWPC start production (PRR) Feb-15 Feb-15 3 1 3 24-Feb
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) Apr-15 Apr-15 4 1 4 https://indico.cern.ch/event/406444/
CALORIMETER Front-End ASIC EDR Apr-15 Apr-15 5 1 5 was 24 April
VELO sensors Sensor and thinned bump bonding EDR Apr-15 May-15 6 1 6 https://indico.cern.ch/event/396256/timetable/#20150601
UPSTREAM TRACKER SALT Chip SALT EDR May-15 May-15 7 1 7 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER FLEX cables FLEX CABLE EDR May-15 May-15 8 1 8 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER Staves Stave EDR May-15 May-15 9 1 9 https://indico.cern.ch/event/394628/
SCIFI "Fibres mats modules" Joint EDR Jun-15 Jun-15 10 1 10 https://indico.cern.ch/event/406444/
UPSTREAM TRACKER Sensor SENSOR EDR Jun-15 Jun-15 11 1 11 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jun-15 Jun-15 12 1 12 https://indico.cern.ch/event/394628/
VELO electronics ASIC EDR Jul-15 Jul-15 13 1 13  
RICH MaPMT Place MaPMT order and start production Mar-15 Oct-15 14 1 14  
VELO cooling substrate Cooling Substrate EDR Jun-15 Oct-15 15 0 14  
MUON nSYNC EDR Jun-15 Nov-15 16 0 14  
MUON nODE EDR Jun-15 Nov-15 17 0 14  
MUON nPDM EDR Jun-15 Nov-15 18 0 14  
MUON nSB EDR Jun-15 Nov-15 19 0 14  
VELO electronics hybrid EDR Jul-15 Nov-15 20 0 14  
VELO electronics Velopix submission 1 Nov-15 Nov-15 21 0 14  
RICH CLARO + Front-End Board PRR Jan-15 Jan-16 22 0 0  
UPSTREAM TRACKER Integration Cooling EDR Oct-15 Jan-16 23 0 0  
DATA PROCESSING Trigger "1st Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)" Feb-16 Feb-16 24 0 0  
MUON nSYNC prototype submission Jul-15 Feb-16 25 0 0  
RICH Elementary Cell PRR Jan-15 Feb-16 26 0 0  
RICH RICH1 Mechanics "EDR incl Gas encl. Phot boxes Phot funnel Interfaces" May-15 Feb-16 27 0 0  
RICH RICH2 mechanics EDR Nov-15 Feb-16 28 0 0  
UPSTREAM TRACKER Sensor SENSOR PRR Dec-15 Feb-16 29 0 0  
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Jul-15 Feb-16 30 0 0  
DATA PROCESSING Optical fibres Long distance operational reliability Feb-16 Feb-16 31 0 0  
SCIFI "Fibres mats modules" Fibre mat PRR Jan-16 Mar-16 32 0 0  
UPSTREAM TRACKER Integration UT Box and frame EDR Mar-16 Mar-16 33 0 0  
MUON additional shielding EDR Oct-15 Apr-16 34 0 0  
SCIFI SiPM + Electronics + ROB Joint EDR Dec-15 Apr-16 35 0 0  
UPSTREAM TRACKER ELECTRONICS PEPI/DCB EDR Jan-16 Apr-16 36 0 0  
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Oct-15 May-16 37 0 0  
RICH Photon Detector Module "EDR Optoelectronic chain module + assembly" Mar-15 May-16 38 0 0  
RICH Digital board "EDR DB hardware with basic firmware + ECS " Jan-15 May-16 39 0 0  
SCIFI "Fibres mats modules" Module PRR Mar-16 May-16 40 0 0  
UPSTREAM TRACKER Sensor type A prepr subm. Jul-15 May-16 41 0 0  
UPSTREAM TRACKER Staves Instrumented stave PRR Feb-16 May-16 42 0 0  
VELO sensors Sensor PRR Oct-15 May-16 43 0 0  
DATA PROCESSING Event-building Software scalability 600 nodes May-16 May-16 44 0 0  
CALORIMETER Front-End board (FEB) EDR Sep-15 Jun-16 45 0 0  
CALORIMETER Control Board (CB) EDR Jan-16 Jun-16 46 0 0  
CALORIMETER "HV Monitoring Calib GBT" EDR Jan-16 Jun-16 47 0 0  
SCIFI SiPM + Electronics + ROB Cold box and ROB EDR Feb-16 Jun-16 48 0 0  
UPSTREAM TRACKER FLEX cables FLEX CABLE PRR Jan-16 Jun-16 49 0 0  
VELO cooling substrate Colling Substrate PRR Sep-15 Jun-16 50 0 0  
MUON additional shielding launch order (PRR) Feb-16 Aug-16 51 0 0  
CALORIMETER Front-End ASIC PRR Sep-15 Sep-16 52 0 0  
RICH RICH1 Mechanics PRR Oct-15 Sep-16 53 0 0  
RICH RICH2 mechanics PRR Jun-16 Sep-16 54 0 0  
UPSTREAM TRACKER Hybrid 128 CH HYBRID EDR Oct-15 Sep-16 55 0 0  
UPSTREAM TRACKER SALT Chip SALT PRR Mar-16 Sep-16 56 0 0  
VELO electronics Velopix Submission 2.1 (final submission) (PRR) Apr-16 Sep-16 57 0 0  
UPSTREAM TRACKER SALT Chip SALT production starts Oct-16 Oct-16 58 0 0  
VELO electronics "Data cable hybrid OPB PRR" Oct-16 Oct-16 59 0 0  
CALORIMETER Front-End ASIC start production Nov-16 Nov-16 60 0 0  
MUON electronics Full electronics chain tested Jun-16 Nov-16 61 0 0  
CALORIMETER Front-End board (FEB) PRR Jan-16 Dec-16 62 0 0  
RICH Digital board PRR Aug-15 Dec-16 63 0 0  
SCIFI Frames EDR Oct-16 Dec-16 64 0 0  
UPSTREAM TRACKER Hybrid 128 CH HYBRID PRR May-16 Dec-16 65 0 0  
VELO detector mechanics detector mechanics EDR Oct-15 Dec-16 66 0 0  
CALORIMETER Control Board (CB) PRR Jul-16 Jan-17 67 0 0  
CALORIMETER "HV Monitoring Calib GBT" PRR Jul-16 Jan-17 68 0 0  
CALORIMETER "HV Monitoring Calib GBT" production Jan-17 Jan-17 69 0 0  
UPSTREAM TRACKER Hybrid hybrid production starts Jan-17 Jan-17 70 0 0  
VELO module Module EDR Nov-15 Jan-17 71 0 0  
MUON nSYNC Final submission (PRR) Dec-16 Mar-17 72 0 0  
MUON nODE start production (PRR) Dec-16 Mar-17 73 0 0  
MUON nPDM start production (PRR) Dec-16 Mar-17 74 0 0  
MUON nSB start production (PRR) Dec-16 Mar-17 75 0 0  
UPSTREAM TRACKER FLEX cables first batch of cable production completed Mar-17 Mar-17 76 0 0  
UPSTREAM TRACKER ELECTRONICS PEPI electronics PRR Nov-16 Mar-17 77 0 0  
VELO RF foil RF foil PRR Sep-16 Mar-17 78 0 0  
VELO detector mechanics detector mechanics PRR Feb-16 Mar-17 79 0 0  
SCIFI SiPM + Electronics + ROB ROB Finish production of components Apr-17 Apr-17 80 0 0  
SCIFI SiPM + Electronics + ROB SiPM Series (100%) delivered Apr-17 Apr-17 81 0 0  
SCIFI SiPM + Electronics + ROB PACIFIC+electronics PRR Sep-16 Apr-17 82 0 0  
DATA PROCESSING Generic readout board 10% of boards produced and tested Feb-16 May-17 83 0 0  
SCIFI "Fibres mats modules" 100% fibres delivered (11'000 km) May-17 May-17 84 0 0  
DATA PROCESSING Farm and Data centre Conteiner selected; start construction of data centre building May-17 May-17 85 0 0  
SCIFI Frames Assembly zone at P8 available and equipped Jun-17 Jun-17 86 0 0  
UPSTREAM TRACKER FLEX cables FLEX cable production completed Jul-17 Jul-17 87 0 0  
CALORIMETER Front-End board (FEB) start production Aug-17 Aug-17 88 0 0  
SCIFI "Fibres mats modules" 100% modules produced Aug-17 Aug-17 89 0 0  
VELO module Module PRR Jul-16 Aug-17 90 0 0  
VELO module Module production site qualification Oct-17 Oct-17 91 0 0  
DATA PROCESSING Event-building "Test in HPC 400 nodes at least 20 Tb/s" Oct-17 Oct-17 92 0 0  
CALORIMETER Control Board (CB) start production Nov-17 Nov-17 93 0 0  
DATA PROCESSING Generic readout board Production start Nov-17 Nov-17 94 0 0  
DATA PROCESSING Computing TDR Feb-17 Nov-17 95 0 0  
SCIFI SiPM + Electronics + ROB PACIFIC first production chips available for mounting Jan-18 Jan-18 96 0 0  
DATA PROCESSING Trigger "2nd Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)" Feb-18 Feb-18 97 0 0  
VELO module Module-base integration PRR Mar-18 Mar-18 98 0 0  
SCIFI Frames Start module installation on C frames Apr-18 Apr-18 99 0 0  
UPSTREAM TRACKER Hybrid hybrid mounting completed May-18 May-18 100 0 0  
SCIFI Frames "12 frames mechanics assembled" Jun-18 Jun-18 101 0 0  
UPSTREAM TRACKER Sensor sensor production completed Jul-18 Jul-18 102 0 0  
UPSTREAM TRACKER Staves 1/2 half of instrumented modules ready Aug-18 Aug-18 103 0 0  
DATA PROCESSING Computing Computing model for the Run 3 Aug-18 Aug-18 104 0 0  
DATA PROCESSING Farm and Data centre Decide on readout network technology Sep-18 Sep-18 105 0 0  
DATA PROCESSING Trigger Decision on output bandwidth and on output data flows Sep-18 Sep-18 106 0 0  
VELO module Module production complete Dec-18 Dec-18 107 0 0  
CALORIMETER Installation ready for installation Aug-18 Feb-19 108 0 0  
MUON Installation ready for installation Aug-18 Feb-19 109 0 0  
UPSTREAM TRACKER Staves stave instrumentation completed Mar-19 Mar-19 110 0 0  
RICH Installation ready for installation Aug-18 Apr-19 111 0 0  
UPSTREAM TRACKER ELECTRONICS PEPI electronics completed and ready Apr-19 Apr-19 112 0 0  
DATA PROCESSING Generic readout board Production is over May-19 May-19 113 0 0  
SCIFI   ready for installation Aug-18 May-19 114 0 0  
UPSTREAM TRACKER Installation ready for installation Jan-19 Jun-19 115 0 0  
VELO module Module-Base integration complete Jul-19 Jul-19 116 0 0  
DATA PROCESSING installation Online ready for sub-detectors commissioning Jan-19 Aug-19 117 0 0  
VELO Installation ready for installation Aug-18 Jan-20 118 0 0  
DATA PROCESSING Trigger Trigger configuration for startup Jan-19 May-20 119 0 0  
DATA PROCESSING Installation Online system ready for data-taking Jan-20 Aug-20 120 0 0  
 
Deleted:
<
<
System item milestone date (Sep. 2015) date (2014) number fraction achieved integral comments
RICH CLARO + Front-End Board "EDR 7th of Oct"Jan-00 Nov-14 Jan-00 1 1 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell "EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal"Jan-00 Nov-14 Jan-00 2 1 2 https://indico.cern.ch/event/344560/
MUON Spare MWPC start production (PRR)Jan-00 Mar-15 Jan-00 3 1 3 24-Feb
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2)Jan-00 May-15 Jan-00 4 1 4 https://indico.cern.ch/event/406444/
CALORIMETER Front-End ASIC EDRJan-00 May-15 Jan-00 5 1 5 was 24 April
VELO sensors Sensor and thinned bump bonding EDRJan-00 May-15 Jan-00 6 1 6 https://indico.cern.ch/event/396256/timetable/#20150601
UPSTREAM TRACKER SALT Chip SALT EDRJan-00 Jun-15 Jan-00 7 1 7 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER FLEX cables FLEX CABLE EDRJan-00 Jun-15 Jan-00 8 1 8 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER Staves Stave EDRJan-00 Jun-15 Jan-00 9 1 9 https://indico.cern.ch/event/394628/
SCIFI "Fibres mats modules" Joint EDRJan-00 Jul-15 Jan-00 10 1 10 https://indico.cern.ch/event/406444/
UPSTREAM TRACKER Sensor SENSOR EDRJan-00 Jul-15 Jan-00 11 1 11 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDRJan-00 Jul-15 Jan-00 12 1 12 https://indico.cern.ch/event/394628/
VELO electronics ASIC EDRJan-00 Aug-15 Jan-00 13 1 13
RICH MaPMT Place MaPMT order and start productionJan-00 Apr-15 Jan-00 14 1 14
VELO cooling substrate Cooling Substrate EDRJan-00 Jul-15 Jan-00 15 0 14
MUON nSYNC EDRJan-00 Jul-15 Jan-00 16 0 14
MUON nODE EDRJan-00 Jul-15 Jan-00 17 0 14
MUON nPDM EDRJan-00 Jul-15 Jan-00 18 0 14
MUON nSB EDRJan-00 Jul-15 Jan-00 19 0 14
VELO electronics hybrid EDRJan-00 Aug-15 Jan-00 20 0 14
VELO electronics Velopix submission 1Jan-00 Jan-00 21 0 14
RICH CLARO + Front-End Board PRRJan-00 Feb-15 Jan-00 22 0 14
UPSTREAM TRACKER Integration Cooling EDRJan-00 Nov-15 Jan-00 23 0 14
DATA PROCESSING Trigger "1st Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)"Jan-00 Jan-00 24 0 14
MUON nSYNC prototype submissionJan-00 Aug-15 Jan-00 25 0 14
RICH Elementary Cell PRRJan-00 Feb-15 Jan-00 26 0 14
RICH RICH1 Mechanics "EDR incl Gas encl. Phot boxes Phot funnel Interfaces"Jan-00 Dec-15 Jan-00 27 0 14
RICH RICH2 mechanics EDRJan-00 Jan-00 28 0 14
UPSTREAM TRACKER Sensor SENSOR PRRJan-00 Jan-16 Jan-00 29 0 14
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submissionJan-00 Jan-00 30 0 14
DATA PROCESSING Optical fibres Long distance operational reliabilityJan-00 Aug-15 Jan-00 31 0 14
SCIFI "Fibres mats modules" Fibre mat PRRJan-00 Feb-16 Jan-00 32 0 14
UPSTREAM TRACKER Integration UT Box and frame EDRJan-00 Apr-16 Jan-00 33 0 14
MUON additional shielding EDRJan-00 Mar-16 Jan-00 34 0 14
SCIFI SiPM + Electronics + ROB Joint EDRJan-00 Jan-16 Jan-00 35 0 14
UPSTREAM TRACKER ELECTRONICS PEPI/DCB EDRJan-00 Jan-00 36 0 14
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technologyJan-00 Nov-15 Jan-00 37 0 14
RICH|Photon Detector Module|"EDR Optoelectronic chain module + assembly"Jan-00|Apr-15|Jan-00|38|0|14|| RICH|Digital board|"EDR DB hardware with basic firmware + ECS "Jan-00|Feb-15|Jan-00|39|0|14|| SCIFI|"Fibres mats modules"|Module PRRJan-00|Apr-16|Jan-00|40|0|14|| UPSTREAM TRACKER|Sensor|type A prepr subm.Jan-00|Aug-15|Jan-00|41|0|14|| UPSTREAM TRACKER|Staves|Instrumented stave PRRJan-00||Jan-00|42|0|14|| VELO|sensors|Sensor PRRJan-00|Nov-15|Jan-00|43|0|14|| DATA PROCESSING|Event-building|Software scalability 600 nodesJan-00|Jun-16|Jan-00|44|0|14|| CALORIMETER|Front-End board (FEB)|EDRJan-00|Oct-15|Jan-00|45|0|14|| CALORIMETER|Control Board (CB)|EDRJan-00|Feb-16|Jan-00|46|0|14|| CALORIMETER|"HV Monitoring Calib GBT"|EDRJan-00|Feb-16|Jan-00|47|0|14|| SCIFI|SiPM + Electronics + ROB|Cold box and ROB EDRJan-00|Jan-16|Jan-00|48|0|14|| UPSTREAM TRACKER|FLEX cables|FLEX CABLE PRRJan-00|Feb-16|Jan-00|49|0|14|| VELO|cooling substrate|Colling Substrate PRRJan-00|Oct-15|Jan-00|50|0|14|| MUON|additional shielding|launch order (PRR)Jan-00|Nov-15|Jan-00|51|0|14|| CALORIMETER|Front-End ASIC|PRRJan-00|Feb-16|Jan-00|52|0|14|| RICH|RICH1 Mechanics|PRRJan-00|Jul-16|Jan-00|53|0|14|| RICH|RICH2 mechanics|PRRJan-00|Jul-16|Jan-00|54|0|14|| UPSTREAM TRACKER|Hybrid|128 CH HYBRID EDRJan-00||Jan-00|55|0|14|| UPSTREAM TRACKER|SALT Chip|SALT PRR Jan-00|Apr-16|Jan-00|56|0|14|| VELO|electronics|Velopix Submission 2.1 (final submission) (PRR)Jan-00|May-16|Jan-00|57|0|14|| UPSTREAM TRACKER|SALT Chip|SALT production startsJan-00||Jan-00|58|0|14|| VELO|electronics|"Data cable hybrid OPB PRR"Jan-00||Jan-00|59|0|14|| CALORIMETER|Front-End ASIC|start productionJan-00||Jan-00|60|0|14|| MUON|electronics|Full electronics chain testedJan-00|Jul-16|Jan-00|61|0|14|| CALORIMETER|Front-End board (FEB)|PRRJan-00||Jan-00|62|0|14|| RICH|Digital board|PRRJan-00|Sep-15|Jan-00|63|0|14|| SCIFI|Frames|EDRJan-00|Nov-16|Jan-00|64|0|14|| UPSTREAM TRACKER|Hybrid|128 CH HYBRID PRRJan-00|Jun-16|Jan-00|65|0|14|| VELO|detector mechanics|detector mechanics EDRJan-00|Nov-16|Jan-00|66|0|14|| CALORIMETER|Control Board (CB)|PRRJan-00|Aug-16|Jan-00|67|0|14|| CALORIMETER|"HV Monitoring Calib GBT"|PRRJan-00|Aug-16|Jan-00|68|0|14|| CALORIMETER|"HV Monitoring Calib GBT"|productionJan-00||Jan-00|69|0|14|| UPSTREAM TRACKER|Hybrid|hybrid production startsJan-00||Jan-00|70|0|14|| VELO|module|Module EDRJan-00|Dec-15|Jan-00|71|0|14|| MUON|nSYNC|Final submission (PRR)Jan-00|Jan-17|Jan-00|72|0|14|| MUON|nODE|start production (PRR)Jan-00|Jan-17|Jan-00|73|0|14|| MUON|nPDM|start production (PRR)Jan-00|Jan-17|Jan-00|74|0|14|| MUON|nSB|start production (PRR)Jan-00|Jan-17|Jan-00|75|0|14|| UPSTREAM TRACKER|FLEX cables|first batch of cable production completedJan-00||Jan-00|76|0|14|| UPSTREAM TRACKER|ELECTRONICS|PEPI electronics PRRJan-00|Jul-16|Jan-00|77|0|14|| VELO|RF foil|RF foil PRRJan-00|Oct-16|Jan-00|78|0|14|| VELO|detector mechanics|detector mechanics PRRJan-00||Jan-00|79|0|14|| SCIFI|SiPM + Electronics + ROB|ROB Finish production of componentsJan-00||Jan-00|80|0|14|| SCIFI|SiPM + Electronics + ROB|SiPM Series (100%) deliveredJan-00||Jan-00|81|0|14|| SCIFI|SiPM + Electronics + ROB|PACIFIC+electronics PRRJan-00||Jan-00|82|0|14|| DATA PROCESSING|Generic readout board|10% of boards produced and testedJan-00||Jan-00|83|0|14|| SCIFI|"Fibres mats modules"|100% fibres delivered (11'000 km)Jan-00||Jan-00|84|0|14|| DATA PROCESSING|Farm and Data centre|Conteiner selected; start construction of data centre buildingJan-00||Jan-00|85|0|14|| SCIFI|Frames|Assembly zone at P8 available and equippedJan-00||Jan-00|86|0|14|| UPSTREAM TRACKER|FLEX cables|FLEX cable production completedJan-00||Jan-00|87|0|14|| CALORIMETER|Front-End board (FEB)|start productionJan-00||Jan-00|88|0|14|| SCIFI|"Fibres mats modules"|100% modules producedJan-00||Jan-00|89|0|14|| VELO|module|Module PRRJan-00|Aug-16|Jan-00|90|0|14|| VELO|module|Module production site qualificationJan-00||Jan-00|91|0|14|| DATA PROCESSING|Event-building|"Test in HPC 400 nodes at least 20 Tb/s"Jan-00|Nov-17|Jan-00|92|0|14|| CALORIMETER|Control Board (CB)|start productionJan-00||Jan-00|93|0|14|| DATA PROCESSING|Generic readout board|Production startJan-00||Jan-00|94|0|14|| DATA PROCESSING|Computing|TDRJan-00|Mar-17|Jan-00|95|0|14|| SCIFI|SiPM + Electronics + ROB|PACIFIC first production chips available for mountingJan-00||Jan-00|96|0|14|| DATA PROCESSING|Trigger|"2nd Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)"Jan-00|Oct-18|Jan-00|97|0|14|| VELO|module|Module-base integration PRRJan-00||Jan-00|98|0|14|| SCIFI|Frames|Start module installation on C framesJan-00||Jan-00|99|0|14|| UPSTREAM TRACKER|Hybrid|hybrid mounting completedJan-00||Jan-00|100|0|14|| SCIFI|Frames|"12 frames mechanics assembled"Jan-00||Jan-00|101|0|14|| UPSTREAM TRACKER|Sensor|sensor production completedJan-00||Jan-00|102|0|14|| UPSTREAM TRACKER|Staves|1/2 half of instrumented modules readyJan-00||Jan-00|103|0|14|| DATA PROCESSING|Computing|Computing model for the Run 3Jan-00||Jan-00|104|0|14|| DATA PROCESSING|Farm and Data centre|Decide on readout network technologyJan-00|Oct-18|Jan-00|105|0|14|| DATA PROCESSING|Trigger|Decision on output bandwidth and on output data flowsJan-00|Oct-18|Jan-00|106|0|14|| VELO|module|Module production completeJan-00||Jan-00|107|0|14|| CALORIMETER|Installation|ready for installationJan-00|Sep-18|Jan-00|108|0|14|| MUON|Installation|ready for installationJan-00|Sep-18|Jan-00|109|0|14|| UPSTREAM TRACKER|Staves|stave instrumentation completedJan-00||Jan-00|110|0|14|| RICH|Installation|ready for installationJan-00|Sep-18|Jan-00|111|0|14|| UPSTREAM TRACKER|ELECTRONICS|PEPI electronics completed and readyJan-00||Jan-00|112|0|14|| DATA PROCESSING|Generic readout board|Production is overJan-00||Jan-00|113|0|14|| SCIFI||ready for installationJan-00|Sep-18|Jan-00|114|0|14|| UPSTREAM TRACKER|Installation|ready for installationJan-00|Feb-19|Jan-00|115|0|14|| VELO|module|Module-Base integration completeJan-00||Jan-00|116|0|14|| DATA PROCESSING|installation|Online ready for sub-detectors commissioningJan-00|Feb-19|Jan-00|117|0|14|| VELO|Installation|ready for installationJan-00|Sep-18|Jan-00|118|0|14|| DATA PROCESSING|Trigger|Trigger configuration for startupJan-00|Feb-19|Jan-00|119|0|14|| DATA PROCESSING|Installation|Online system ready for data-takingJan-00|Feb-10|Jan-00|120|0|14||
 
<!--edittable1-->
Changed:
<
<
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
>
>
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
 
Changed:
<
<
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
milestones 2 2 2 5 6 8 11 15 23 27 28 32 39 42 44 49 55 59 60 63 66 70 70 73 74 75 79 79 80 80 80 81 81 81 81 81 82 82 82 82 82 82 82 82 82 82 88 91 91 91 91 94 94 94 94 94 94 94 94 94 94 94 94 95 95 95 95
milestones achieved 2 2 2 3 3 4 6 11 12
>
>
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
milestones 2 2 2 3 3 5 9 12 13 13 13 15 21 21 23 31 33 36 44 50 50 51 57 59 61 66 71 71 79 82 85 86 87 90 90 92 95 95 96 97 99 100 101 102 104 106 106 106 107 107 109 110 112 115 115 116 117 117 117 117 117 118 118 118 118 119 119 119 120
milestones achieved 2 2 2 3 3 5 9 12 13 13 13 14 14
 

Revision 132015-11-20 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning
Changed:
<
<
System item milestone date (2014) date (Sep. 2016) number comments
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2 https://indico.cern.ch/event/344560/
RICH CLARO + Front-End Board PRR Feb-15 3 will be moved
RICH Elementary Cell PRR Feb-15 4 will be moved
RICH Digital board EDR DB hardware with basic firmware + ECS Feb-15 5 will be moved
MUON Spare MWPC start production (PRR) Mar-15 6 24 February
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7 will be moved
RICH MaPMT Place MaPMT order and start production Apr-15 8 moved to August?
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9 https://indico.cern.ch/event/406444/
VELO sensors Sensor and thinned bump bonding EDR May-15 10 https://indico.cern.ch/event/396256/timetable/#20150601
CALORIMETER Front-End ASIC EDR May-15 11 was 24 April
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14 https://indico.cern.ch/event/394628/
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15 will be moved
SCIFI Fibres, mats, modules Joint EDR Jul-15 16 https://indico.cern.ch/event/406444/
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18 https://indico.cern.ch/event/394628/
VELO cooling substrate Cooling Substrate EDR Jul-15 19  
MUON nSYNC EDR Jul-15 20 to be moved to October
MUON nODE EDR Jul-15 21 to be moved to October
MUON nPDM EDR Jul-15 22 to be moved to October
MUON nSB EDR Jul-15 23 to be moved to October
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Aug-15 24 probably not before Nov 2015
VELO electronics ASIC, hybrid EDR Aug-15 25  
MUON nSYNC prototype submission Aug-15 26  
UPSTREAM TRACKER Sensor type A prepr subm. Aug-15 27  
RICH Digital board PRR Sep-15 28  
VELO cooling substrate Colling Substrate PRR Oct-15 29  
VELO cooling Cooling EDR Oct-15 30  
CALORIMETER Front-End ASIC PRR Oct-15 31  
CALORIMETER Front-End board (FEB) EDR Oct-15 32  
UPSTREAM TRACKER Sensor 128 CH HYBRID EDR Nov-15 33  
UPSTREAM TRACKER Integration Cooling EDR Nov-15 34  
VELO sensors Sensor PRR Nov-15 35  
VELO detector base, hood Detector base, hood and evaporator EDR Nov-15 36  
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Nov-15 37  
MUON additional shielding EDR Nov-15 38  
RICH RICH1 Mirrors + Supports PRR Nov-15 39  
VELO module Module EDR Dec-15 40  
RICH RICH mechanics EDR, incl Gas encl., Phot boxes, Phot funnel Interfaces Dec-15 41  
UPSTREAM TRACKER Sensor 128 ch asic hybrid submission Dec-15 42  
SCIFI SiPM + Electronics + ROB Joint EDR Jan-16 43  
UPSTREAM TRACKER Sensor SENSOR PRR Jan-16 44  
SCIFI   Fibre mats PRR Feb-16 45  
UPSTREAM TRACKER ELECTRONICS FLEX CABLE PRR Feb-16 46  
CALORIMETER Front-End board (FEB) PRR Feb-16 47  
CALORIMETER Control Board (CB) EDR Feb-16 48  
CALORIMETER HV , Monitoring, Calib, GBT EDR Feb-16 49  
SCIFI   ROB PRR Mar-16 50  
VELO detector base hood Detector base, hood & Evaporator PRR Mar-16 51  
DATA PROCESSING Generic readout board preseries completed and qualified Mar-16 52  
DATA PROCESSING Optical fibres Long distance operational reliability Mar-16 53  
MUON additional shielding launch order (PRR) Mar-16 54  
UPSTREAM TRACKER Mechanics and cooling Instrumented stave PRR Mar-16 55  
SCIFI   Module PRR Apr-16 56  
UPSTREAM TRACKER SALT Chip SALT PRR Apr-16 57  
UPSTREAM TRACKER Integration UT Box and frame EDR Apr-16 58  
VELO electronics ASIC, hybrid PRR Apr-16 59  
VELO electronics Velopix Submission 2.1 (PRR) May-16 60  
UPSTREAM TRACKER Sensor 128 CH HYBRID PRR Jun-16 61  
DATA PROCESSING Event-building Software scalability 600 nodes Jun-16 62  
DATA PROCESSING Trigger 1st Bi-annual update (CPU growth, code performance, strategy, alternative plateforms, review optimisation tasks, bandwidth optimization) Jun-16 63  
UPSTREAM TRACKER ELECTRONICS PEPI/LV PRR Jul-16 64  
MUON electronics Full electronics chain tested Jul-16 65  
RICH RICH mechanics PRR Jul-16 66  
SCIFI   SIPM PRR Aug-16 67  
VELO module Module PRR Aug-16 68  
CALORIMETER Control Board (CB) PRR Aug-16 69  
CALORIMETER HV, Monitoring, Calib, GBT PRR Aug-16 70  
SCIFI   PACIFIC PRR Oct-16 71  
VELO RF foil RF foil PRR Oct-16 72  
VELO cooling Cooling PRR Oct-16 73  
SCIFI Frames EDR Nov-16 74  
SCIFI cooling cooling plants PRR Dec-16 75  
MUON nSYNC Final submission (PRR) Jan-17 76  
MUON nODE start production (PRR) Jan-17 77  
MUON nPDM start production (PRR) Jan-17 78  
MUON nSB start production (PRR) Jan-17 79  
DATA PROCESSING Computing TDR Mar-17 80  
DATA PROCESSING Farm and Data centre Conteiner selected; start construction of data centre building Jun-17 81  
DATA PROCESSING Event-building Test in HPC, 400 nodes at least 20 Tb/s Nov-17 82  
CALORIMETER Installation ready for installation Sep-18 83  
DATA PROCESSING Computing Computing model for the Run 3 Sep-18 84  
MUON Installation ready for installation Sep-18 85  
RICH Installation ready for installation Sep-18 86  
SCIFI   ready for installation Sep-18 87  
VELO Installation ready for installation Sep-18 88  
DATA PROCESSING Farm and Data centre Decide on readout network technology Oct-18 89  
DATA PROCESSING Trigger 2nd Bi-annual update (CPU growth, code performance, strategy, alternative platforms, review optimisation tasks, bandwidth optimization) Oct-18 90  
DATA PROCESSING Trigger Decision on output bandwidth and on output data flows Oct-18 91  
DATA PROCESSING Installation Online ready for sub-detectors commissioning Feb-19 92  
DATA PROCESSING Trigger Trigger configuration for startup Feb-19 93  
UPSTREAM TRACKER Installation ready for installation Feb-19 94  
DATA PROCESSING Installation Online system ready for data-taking Feb-20 95  
<!-- /editTable -->
>
>
<!-- /editTable -->

System item milestone date (Sep. 2015) date (2014) number fraction achieved integral comments
RICH CLARO + Front-End Board "EDR 7th of Oct"Jan-00 Nov-14 Jan-00 1 1 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell "EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal"Jan-00 Nov-14 Jan-00 2 1 2 https://indico.cern.ch/event/344560/
MUON Spare MWPC start production (PRR)Jan-00 Mar-15 Jan-00 3 1 3 24-Feb
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2)Jan-00 May-15 Jan-00 4 1 4 https://indico.cern.ch/event/406444/
CALORIMETER Front-End ASIC EDRJan-00 May-15 Jan-00 5 1 5 was 24 April
VELO sensors Sensor and thinned bump bonding EDRJan-00 May-15 Jan-00 6 1 6 https://indico.cern.ch/event/396256/timetable/#20150601
UPSTREAM TRACKER SALT Chip SALT EDRJan-00 Jun-15 Jan-00 7 1 7 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER FLEX cables FLEX CABLE EDRJan-00 Jun-15 Jan-00 8 1 8 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER Staves Stave EDRJan-00 Jun-15 Jan-00 9 1 9 https://indico.cern.ch/event/394628/
SCIFI "Fibres mats modules" Joint EDRJan-00 Jul-15 Jan-00 10 1 10 https://indico.cern.ch/event/406444/
UPSTREAM TRACKER Sensor SENSOR EDRJan-00 Jul-15 Jan-00 11 1 11 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDRJan-00 Jul-15 Jan-00 12 1 12 https://indico.cern.ch/event/394628/
VELO electronics ASIC EDRJan-00 Aug-15 Jan-00 13 1 13
RICH MaPMT Place MaPMT order and start productionJan-00 Apr-15 Jan-00 14 1 14
VELO cooling substrate Cooling Substrate EDRJan-00 Jul-15 Jan-00 15 0 14
MUON nSYNC EDRJan-00 Jul-15 Jan-00 16 0 14
MUON nODE EDRJan-00 Jul-15 Jan-00 17 0 14
MUON nPDM EDRJan-00 Jul-15 Jan-00 18 0 14
MUON nSB EDRJan-00 Jul-15 Jan-00 19 0 14
VELO electronics hybrid EDRJan-00 Aug-15 Jan-00 20 0 14
VELO electronics Velopix submission 1Jan-00 Jan-00 21 0 14
RICH CLARO + Front-End Board PRRJan-00 Feb-15 Jan-00 22 0 14
UPSTREAM TRACKER Integration Cooling EDRJan-00 Nov-15 Jan-00 23 0 14
DATA PROCESSING Trigger "1st Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)"Jan-00 Jan-00 24 0 14
MUON nSYNC prototype submissionJan-00 Aug-15 Jan-00 25 0 14
RICH Elementary Cell PRRJan-00 Feb-15 Jan-00 26 0 14
RICH RICH1 Mechanics "EDR incl Gas encl. Phot boxes Phot funnel Interfaces"Jan-00 Dec-15 Jan-00 27 0 14
RICH RICH2 mechanics EDRJan-00 Jan-00 28 0 14
UPSTREAM TRACKER Sensor SENSOR PRRJan-00 Jan-16 Jan-00 29 0 14
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submissionJan-00 Jan-00 30 0 14
DATA PROCESSING Optical fibres Long distance operational reliabilityJan-00 Aug-15 Jan-00 31 0 14
SCIFI "Fibres mats modules" Fibre mat PRRJan-00 Feb-16 Jan-00 32 0 14
UPSTREAM TRACKER Integration UT Box and frame EDRJan-00 Apr-16 Jan-00 33 0 14
MUON additional shielding EDRJan-00 Mar-16 Jan-00 34 0 14
SCIFI SiPM + Electronics + ROB Joint EDRJan-00 Jan-16 Jan-00 35 0 14
UPSTREAM TRACKER ELECTRONICS PEPI/DCB EDRJan-00 Jan-00 36 0 14
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technologyJan-00 Nov-15 Jan-00 37 0 14
RICH|Photon Detector Module|"EDR Optoelectronic chain module + assembly"Jan-00|Apr-15|Jan-00|38|0|14|| RICH|Digital board|"EDR DB hardware with basic firmware + ECS "Jan-00|Feb-15|Jan-00|39|0|14|| SCIFI|"Fibres mats modules"|Module PRRJan-00|Apr-16|Jan-00|40|0|14|| UPSTREAM TRACKER|Sensor|type A prepr subm.Jan-00|Aug-15|Jan-00|41|0|14|| UPSTREAM TRACKER|Staves|Instrumented stave PRRJan-00||Jan-00|42|0|14|| VELO|sensors|Sensor PRRJan-00|Nov-15|Jan-00|43|0|14|| DATA PROCESSING|Event-building|Software scalability 600 nodesJan-00|Jun-16|Jan-00|44|0|14|| CALORIMETER|Front-End board (FEB)|EDRJan-00|Oct-15|Jan-00|45|0|14|| CALORIMETER|Control Board (CB)|EDRJan-00|Feb-16|Jan-00|46|0|14|| CALORIMETER|"HV Monitoring Calib GBT"|EDRJan-00|Feb-16|Jan-00|47|0|14|| SCIFI|SiPM + Electronics + ROB|Cold box and ROB EDRJan-00|Jan-16|Jan-00|48|0|14|| UPSTREAM TRACKER|FLEX cables|FLEX CABLE PRRJan-00|Feb-16|Jan-00|49|0|14|| VELO|cooling substrate|Colling Substrate PRRJan-00|Oct-15|Jan-00|50|0|14|| MUON|additional shielding|launch order (PRR)Jan-00|Nov-15|Jan-00|51|0|14|| CALORIMETER|Front-End ASIC|PRRJan-00|Feb-16|Jan-00|52|0|14|| RICH|RICH1 Mechanics|PRRJan-00|Jul-16|Jan-00|53|0|14|| RICH|RICH2 mechanics|PRRJan-00|Jul-16|Jan-00|54|0|14|| UPSTREAM TRACKER|Hybrid|128 CH HYBRID EDRJan-00||Jan-00|55|0|14|| UPSTREAM TRACKER|SALT Chip|SALT PRR Jan-00|Apr-16|Jan-00|56|0|14|| VELO|electronics|Velopix Submission 2.1 (final submission) (PRR)Jan-00|May-16|Jan-00|57|0|14|| UPSTREAM TRACKER|SALT Chip|SALT production startsJan-00||Jan-00|58|0|14|| VELO|electronics|"Data cable hybrid OPB PRR"Jan-00||Jan-00|59|0|14|| CALORIMETER|Front-End ASIC|start productionJan-00||Jan-00|60|0|14|| MUON|electronics|Full electronics chain testedJan-00|Jul-16|Jan-00|61|0|14|| CALORIMETER|Front-End board (FEB)|PRRJan-00||Jan-00|62|0|14|| RICH|Digital board|PRRJan-00|Sep-15|Jan-00|63|0|14|| SCIFI|Frames|EDRJan-00|Nov-16|Jan-00|64|0|14|| UPSTREAM TRACKER|Hybrid|128 CH HYBRID PRRJan-00|Jun-16|Jan-00|65|0|14|| VELO|detector mechanics|detector mechanics EDRJan-00|Nov-16|Jan-00|66|0|14|| CALORIMETER|Control Board (CB)|PRRJan-00|Aug-16|Jan-00|67|0|14|| CALORIMETER|"HV Monitoring Calib GBT"|PRRJan-00|Aug-16|Jan-00|68|0|14|| CALORIMETER|"HV Monitoring Calib GBT"|productionJan-00||Jan-00|69|0|14|| UPSTREAM TRACKER|Hybrid|hybrid production startsJan-00||Jan-00|70|0|14|| VELO|module|Module EDRJan-00|Dec-15|Jan-00|71|0|14|| MUON|nSYNC|Final submission (PRR)Jan-00|Jan-17|Jan-00|72|0|14|| MUON|nODE|start production (PRR)Jan-00|Jan-17|Jan-00|73|0|14|| MUON|nPDM|start production (PRR)Jan-00|Jan-17|Jan-00|74|0|14|| MUON|nSB|start production (PRR)Jan-00|Jan-17|Jan-00|75|0|14|| UPSTREAM TRACKER|FLEX cables|first batch of cable production completedJan-00||Jan-00|76|0|14|| UPSTREAM TRACKER|ELECTRONICS|PEPI electronics PRRJan-00|Jul-16|Jan-00|77|0|14|| VELO|RF foil|RF foil PRRJan-00|Oct-16|Jan-00|78|0|14|| VELO|detector mechanics|detector mechanics PRRJan-00||Jan-00|79|0|14|| SCIFI|SiPM + Electronics + ROB|ROB Finish production of componentsJan-00||Jan-00|80|0|14|| SCIFI|SiPM + Electronics + ROB|SiPM Series (100%) deliveredJan-00||Jan-00|81|0|14|| SCIFI|SiPM + Electronics + ROB|PACIFIC+electronics PRRJan-00||Jan-00|82|0|14|| DATA PROCESSING|Generic readout board|10% of boards produced and testedJan-00||Jan-00|83|0|14|| SCIFI|"Fibres mats modules"|100% fibres delivered (11'000 km)Jan-00||Jan-00|84|0|14|| DATA PROCESSING|Farm and Data centre|Conteiner selected; start construction of data centre buildingJan-00||Jan-00|85|0|14|| SCIFI|Frames|Assembly zone at P8 available and equippedJan-00||Jan-00|86|0|14|| UPSTREAM TRACKER|FLEX cables|FLEX cable production completedJan-00||Jan-00|87|0|14|| CALORIMETER|Front-End board (FEB)|start productionJan-00||Jan-00|88|0|14|| SCIFI|"Fibres mats modules"|100% modules producedJan-00||Jan-00|89|0|14|| VELO|module|Module PRRJan-00|Aug-16|Jan-00|90|0|14|| VELO|module|Module production site qualificationJan-00||Jan-00|91|0|14|| DATA PROCESSING|Event-building|"Test in HPC 400 nodes at least 20 Tb/s"Jan-00|Nov-17|Jan-00|92|0|14|| CALORIMETER|Control Board (CB)|start productionJan-00||Jan-00|93|0|14|| DATA PROCESSING|Generic readout board|Production startJan-00||Jan-00|94|0|14|| DATA PROCESSING|Computing|TDRJan-00|Mar-17|Jan-00|95|0|14|| SCIFI|SiPM + Electronics + ROB|PACIFIC first production chips available for mountingJan-00||Jan-00|96|0|14|| DATA PROCESSING|Trigger|"2nd Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)"Jan-00|Oct-18|Jan-00|97|0|14|| VELO|module|Module-base integration PRRJan-00||Jan-00|98|0|14|| SCIFI|Frames|Start module installation on C framesJan-00||Jan-00|99|0|14|| UPSTREAM TRACKER|Hybrid|hybrid mounting completedJan-00||Jan-00|100|0|14|| SCIFI|Frames|"12 frames mechanics assembled"Jan-00||Jan-00|101|0|14|| UPSTREAM TRACKER|Sensor|sensor production completedJan-00||Jan-00|102|0|14|| UPSTREAM TRACKER|Staves|1/2 half of instrumented modules readyJan-00||Jan-00|103|0|14|| DATA PROCESSING|Computing|Computing model for the Run 3Jan-00||Jan-00|104|0|14|| DATA PROCESSING|Farm and Data centre|Decide on readout network technologyJan-00|Oct-18|Jan-00|105|0|14|| DATA PROCESSING|Trigger|Decision on output bandwidth and on output data flowsJan-00|Oct-18|Jan-00|106|0|14|| VELO|module|Module production completeJan-00||Jan-00|107|0|14|| CALORIMETER|Installation|ready for installationJan-00|Sep-18|Jan-00|108|0|14|| MUON|Installation|ready for installationJan-00|Sep-18|Jan-00|109|0|14|| UPSTREAM TRACKER|Staves|stave instrumentation completedJan-00||Jan-00|110|0|14|| RICH|Installation|ready for installationJan-00|Sep-18|Jan-00|111|0|14|| UPSTREAM TRACKER|ELECTRONICS|PEPI electronics completed and readyJan-00||Jan-00|112|0|14|| DATA PROCESSING|Generic readout board|Production is overJan-00||Jan-00|113|0|14|| SCIFI||ready for installationJan-00|Sep-18|Jan-00|114|0|14|| UPSTREAM TRACKER|Installation|ready for installationJan-00|Feb-19|Jan-00|115|0|14|| VELO|module|Module-Base integration completeJan-00||Jan-00|116|0|14|| DATA PROCESSING|installation|Online ready for sub-detectors commissioningJan-00|Feb-19|Jan-00|117|0|14|| VELO|Installation|ready for installationJan-00|Sep-18|Jan-00|118|0|14|| DATA PROCESSING|Trigger|Trigger configuration for startupJan-00|Feb-19|Jan-00|119|0|14|| DATA PROCESSING|Installation|Online system ready for data-takingJan-00|Feb-10|Jan-00|120|0|14||
 
<!--edittable1-->

ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.

Revision 122015-11-18 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning
Changed:
<
<
<!-- /editTable -->
>
>
<!-- /editTable -->
 
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2 https://indico.cern.ch/event/344560/
RICH CLARO + Front-End Board PRR Feb-15 3 will be moved

Revision 112015-07-28 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning

<!-- /editTable -->
Line: 7 to 7
 
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2 https://indico.cern.ch/event/344560/
RICH CLARO + Front-End Board PRR Feb-15 3 will be moved
RICH Elementary Cell PRR Feb-15 4 will be moved
Changed:
<
<
RICH Digital board EDR DB hardware with basic firmware + ECS Feb-15 5  
MUON Spare MWPC start production (PRR) Mar-15 6 Feb-15
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7  
RICH MaPMT Place MaPMT order and start production Apr-15 8  
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9 scheduled between 13-17 July
VELO sensors Sensor and thinned bump bonding EDR May-15 10 scheduled for June
>
>
RICH Digital board EDR DB hardware with basic firmware + ECS Feb-15 5 will be moved
MUON Spare MWPC start production (PRR) Mar-15 6 24 February
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7 will be moved
RICH MaPMT Place MaPMT order and start production Apr-15 8 moved to August?
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9 https://indico.cern.ch/event/406444/
VELO sensors Sensor and thinned bump bonding EDR May-15 10 https://indico.cern.ch/event/396256/timetable/#20150601
 
CALORIMETER Front-End ASIC EDR May-15 11 was 24 April
Changed:
<
<
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12 Scheduled for 18-23 June
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13 Scheduled for 18-23 June
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14 Scheduled for 18-23 June
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15  
SCIFI Fibres, mats, modules Joint EDR Jul-15 16 scheduled
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17  
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18  
>
>
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14 https://indico.cern.ch/event/394628/
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15 will be moved
SCIFI Fibres, mats, modules Joint EDR Jul-15 16 https://indico.cern.ch/event/406444/
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17 https://indico.cern.ch/event/394628/
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18 https://indico.cern.ch/event/394628/
 
VELO cooling substrate Cooling Substrate EDR Jul-15 19  
MUON nSYNC EDR Jul-15 20 to be moved to October
MUON nODE EDR Jul-15 21 to be moved to October
Line: 101 to 101
 
<!--edittable1-->

ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.

Changed:
<
<
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
>
>
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
 

year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
milestones 2 2 2 5 6 8 11 15 23 27 28 32 39 42 44 49 55 59 60 63 66 70 70 73 74 75 79 79 80 80 80 81 81 81 81 81 82 82 82 82 82 82 82 82 82 82 88 91 91 91 91 94 94 94 94 94 94 94 94 94 94 94 94 95 95 95 95
Changed:
<
<
milestones achieved 2 2 2 3 3 4
>
>
milestones achieved 2 2 2 3 3 4 6 11 12
 

Revision 102015-05-26 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
* Milestones as project planning

<!-- /editTable -->
Line: 12 to 12
 
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7  
RICH MaPMT Place MaPMT order and start production Apr-15 8  
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9 scheduled between 13-17 July
Changed:
<
<
VELO sensors Sensor and thinned bump bonding EDR May-15 10  
>
>
VELO sensors Sensor and thinned bump bonding EDR May-15 10 scheduled for June
 
CALORIMETER Front-End ASIC EDR May-15 11 was 24 April
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12 Scheduled for 18-23 June
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13 Scheduled for 18-23 June
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14 Scheduled for 18-23 June
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15  
Changed:
<
<
SCIFI Fibres, mats, modules Joint EDR Jul-15 16  
>
>
SCIFI Fibres, mats, modules Joint EDR Jul-15 16 scheduled
 
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17  
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18  
VELO cooling substrate Cooling Substrate EDR Jul-15 19  
Line: 26 to 26
 
MUON nODE EDR Jul-15 21 to be moved to October
MUON nPDM EDR Jul-15 22 to be moved to October
MUON nSB EDR Jul-15 23 to be moved to October
Changed:
<
<
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Aug-15 24  
>
>
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Aug-15 24 probably not before Nov 2015
 
VELO electronics ASIC, hybrid EDR Aug-15 25  
MUON nSYNC prototype submission Aug-15 26  
UPSTREAM TRACKER Sensor type A prepr subm. Aug-15 27  

Revision 92015-05-04 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
Deleted:
<
<
 * Milestones as project planning

<!-- /editTable -->
Line: 12 to 11
 
MUON Spare MWPC start production (PRR) Mar-15 6 Feb-15
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7  
RICH MaPMT Place MaPMT order and start production Apr-15 8  
Changed:
<
<
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9  
>
>
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9 scheduled between 13-17 July
 
VELO sensors Sensor and thinned bump bonding EDR May-15 10  
Changed:
<
<
CALORIMETER Front-End ASIC EDR May-15 11  
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12  
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13  
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14  
>
>
CALORIMETER Front-End ASIC EDR May-15 11 was 24 April
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12 Scheduled for 18-23 June
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13 Scheduled for 18-23 June
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14 Scheduled for 18-23 June
 
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15  
SCIFI Fibres, mats, modules Joint EDR Jul-15 16  
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17  
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18  
VELO cooling substrate Cooling Substrate EDR Jul-15 19  
Changed:
<
<
MUON nSYNC EDR Jul-15 20  
MUON nODE EDR Jul-15 21  
MUON nPDM EDR Jul-15 22  
MUON nSB EDR Jul-15 23  
>
>
MUON nSYNC EDR Jul-15 20 to be moved to October
MUON nODE EDR Jul-15 21 to be moved to October
MUON nPDM EDR Jul-15 22 to be moved to October
MUON nSB EDR Jul-15 23 to be moved to October
 
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Aug-15 24  
VELO electronics ASIC, hybrid EDR Aug-15 25  
MUON nSYNC prototype submission Aug-15 26  
Line: 108 to 107
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
milestones 2 2 2 5 6 8 11 15 23 27 28 32 39 42 44 49 55 59 60 63 66 70 70 73 74 75 79 79 80 80 80 81 81 81 81 81 82 82 82 82 82 82 82 82 82 82 88 91 91 91 91 94 94 94 94 94 94 94 94 94 94 94 94 95 95 95 95
Changed:
<
<
milestones achieved 2 2 2 3
>
>
milestones achieved 2 2 2 3 3 4
 

Revision 82015-03-16 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
Added:
>
>
* Milestones as project planning
 
System item milestone date number comments
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1 https://indico.cern.ch/event/344190/
<!-- /editTable -->

Revision 72015-03-11 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"

System item milestone date number comments
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2 https://indico.cern.ch/event/344560/
<!-- /editTable -->
Changed:
<
<
RICH CLARO + Front-End Board PRR Feb-15 3  
RICH Elementary Cell PRR Feb-15 4  
>
>
RICH CLARO + Front-End Board PRR Feb-15 3 will be moved
RICH Elementary Cell PRR Feb-15 4 will be moved
 
RICH Digital board EDR DB hardware with basic firmware + ECS Feb-15 5  
Changed:
<
<
MUON Spare MWPC start production (PRR) Mar-15 6  
>
>
MUON Spare MWPC start production (PRR) Mar-15 6 Feb-15
 
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7  
RICH MaPMT Place MaPMT order and start production Apr-15 8  
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9  
Line: 106 to 106
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
milestones 2 2 2 5 6 8 11 15 23 27 28 32 39 42 44 49 55 59 60 63 66 70 70 73 74 75 79 79 80 80 80 81 81 81 81 81 82 82 82 82 82 82 82 82 82 82 88 91 91 91 91 94 94 94 94 94 94 94 94 94 94 94 94 95 95 95 95
Changed:
<
<
milestones achieved 2 2
>
>
milestones achieved 2 2 2 3
 

Revision 62015-02-12 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
Changed:
<
<
<!-- /editTable -->
>
>
<!-- /editTable -->
 
System item milestone date number comments
Changed:
<
<
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2
RICH CLARO + Front-End Board PRR Feb-15 3
RICH Elementary Cell PRR Feb-15 4
RICH Digital board EDR DB hardware with basic firmware + ECS Feb-15 5
MUON Spare MWPC start production (PRR) Mar-15 6
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7
RICH MaPMT Place MaPMT order and start production Apr-15 8
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9
VELO sensors Sensor and thinned bump bonding EDR May-15 10
CALORIMETER Front-End ASIC EDR May-15 11
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15
SCIFI Fibres, mats, modules Joint EDR Jul-15 16
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18
VELO cooling substrate Cooling Substrate EDR Jul-15 19
MUON nSYNC EDR Jul-15 20
MUON nODE EDR Jul-15 21
MUON nPDM EDR Jul-15 22
MUON nSB EDR Jul-15 23
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Aug-15 24
VELO electronics ASIC, hybrid EDR Aug-15 25
MUON nSYNC prototype submission Aug-15 26
UPSTREAM TRACKER Sensor type A prepr subm. Aug-15 27
RICH Digital board PRR Sep-15 28
VELO cooling substrate Colling Substrate PRR Oct-15 29
VELO cooling Cooling EDR Oct-15 30
CALORIMETER Front-End ASIC PRR Oct-15 31
CALORIMETER Front-End board (FEB) EDR Oct-15 32
UPSTREAM TRACKER Sensor 128 CH HYBRID EDR Nov-15 33
UPSTREAM TRACKER Integration Cooling EDR Nov-15 34
VELO sensors Sensor PRR Nov-15 35
VELO detector base, hood Detector base, hood and evaporator EDR Nov-15 36
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Nov-15 37
MUON additional shielding EDR Nov-15 38
RICH RICH1 Mirrors + Supports PRR Nov-15 39
VELO module Module EDR Dec-15 40
RICH RICH mechanics EDR, incl Gas encl., Phot boxes, Phot funnel Interfaces Dec-15 41
UPSTREAM TRACKER Sensor 128 ch asic hybrid submission Dec-15 42
SCIFI SiPM + Electronics + ROB Joint EDR Jan-16 43
UPSTREAM TRACKER Sensor SENSOR PRR Jan-16 44
SCIFI   Fibre mats PRR Feb-16 45
UPSTREAM TRACKER ELECTRONICS FLEX CABLE PRR Feb-16 46
CALORIMETER Front-End board (FEB) PRR Feb-16 47
CALORIMETER Control Board (CB) EDR Feb-16 48
CALORIMETER HV , Monitoring, Calib, GBT EDR Feb-16 49
SCIFI   ROB PRR Mar-16 50
VELO detector base hood Detector base, hood & Evaporator PRR Mar-16 51
DATA PROCESSING Generic readout board preseries completed and qualified Mar-16 52
DATA PROCESSING Optical fibres Long distance operational reliability Mar-16 53
MUON additional shielding launch order (PRR) Mar-16 54
UPSTREAM TRACKER Mechanics and cooling Instrumented stave PRR Mar-16 55
SCIFI   Module PRR Apr-16 56
UPSTREAM TRACKER SALT Chip SALT PRR Apr-16 57
UPSTREAM TRACKER Integration UT Box and frame EDR Apr-16 58
VELO electronics ASIC, hybrid PRR Apr-16 59
VELO electronics Velopix Submission 2.1 (PRR) May-16 60
UPSTREAM TRACKER Sensor 128 CH HYBRID PRR Jun-16 61
DATA PROCESSING Event-building Software scalability 600 nodes Jun-16 62
DATA PROCESSING Trigger 1st Bi-annual update (CPU growth, code performance, strategy, alternative plateforms, review optimisation tasks, bandwidth optimization) Jun-16 63
UPSTREAM TRACKER ELECTRONICS PEPI/LV PRR Jul-16 64
MUON electronics Full electronics chain tested Jul-16 65
RICH RICH mechanics PRR Jul-16 66
SCIFI   SIPM PRR Aug-16 67
VELO module Module PRR Aug-16 68
CALORIMETER Control Board (CB) PRR Aug-16 69
CALORIMETER HV, Monitoring, Calib, GBT PRR Aug-16 70
SCIFI   PACIFIC PRR Oct-16 71
VELO RF foil RF foil PRR Oct-16 72
VELO cooling Cooling PRR Oct-16 73
SCIFI Frames EDR Nov-16 74
SCIFI cooling cooling plants PRR Dec-16 75
MUON nSYNC Final submission (PRR) Jan-17 76
MUON nODE start production (PRR) Jan-17 77
MUON nPDM start production (PRR) Jan-17 78
MUON nSB start production (PRR) Jan-17 79
DATA PROCESSING Computing TDR Mar-17 80
DATA PROCESSING Farm and Data centre Conteiner selected; start construction of data centre building Jun-17 81
DATA PROCESSING Event-building Test in HPC, 400 nodes at least 20 Tb/s Nov-17 82
CALORIMETER Installation ready for installation Sep-18 83
DATA PROCESSING Computing Computing model for the Run 3 Sep-18 84
MUON Installation ready for installation Sep-18 85
RICH Installation ready for installation Sep-18 86
SCIFI   ready for installation Sep-18 87
VELO Installation ready for installation Sep-18 88
DATA PROCESSING Farm and Data centre Decide on readout network technology Oct-18 89
DATA PROCESSING Trigger 2nd Bi-annual update (CPU growth, code performance, strategy, alternative platforms, review optimisation tasks, bandwidth optimization) Oct-18 90
DATA PROCESSING Trigger Decision on output bandwidth and on output data flows Oct-18 91
DATA PROCESSING Installation Online ready for sub-detectors commissioning Feb-19 92
DATA PROCESSING Trigger Trigger configuration for startup Feb-19 93
UPSTREAM TRACKER Installation ready for installation Feb-19 94
DATA PROCESSING Installation Online system ready for data-taking Feb-20 95
>
>
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1 https://indico.cern.ch/event/344190/
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2 https://indico.cern.ch/event/344560/
RICH CLARO + Front-End Board PRR Feb-15 3  
RICH Elementary Cell PRR Feb-15 4  
RICH Digital board EDR DB hardware with basic firmware + ECS Feb-15 5  
MUON Spare MWPC start production (PRR) Mar-15 6  
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7  
RICH MaPMT Place MaPMT order and start production Apr-15 8  
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9  
VELO sensors Sensor and thinned bump bonding EDR May-15 10  
CALORIMETER Front-End ASIC EDR May-15 11  
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12  
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13  
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14  
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15  
SCIFI Fibres, mats, modules Joint EDR Jul-15 16  
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17  
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18  
VELO cooling substrate Cooling Substrate EDR Jul-15 19  
MUON nSYNC EDR Jul-15 20  
MUON nODE EDR Jul-15 21  
MUON nPDM EDR Jul-15 22  
MUON nSB EDR Jul-15 23  
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Aug-15 24  
VELO electronics ASIC, hybrid EDR Aug-15 25  
MUON nSYNC prototype submission Aug-15 26  
UPSTREAM TRACKER Sensor type A prepr subm. Aug-15 27  
RICH Digital board PRR Sep-15 28  
VELO cooling substrate Colling Substrate PRR Oct-15 29  
VELO cooling Cooling EDR Oct-15 30  
CALORIMETER Front-End ASIC PRR Oct-15 31  
CALORIMETER Front-End board (FEB) EDR Oct-15 32  
UPSTREAM TRACKER Sensor 128 CH HYBRID EDR Nov-15 33  
UPSTREAM TRACKER Integration Cooling EDR Nov-15 34  
VELO sensors Sensor PRR Nov-15 35  
VELO detector base, hood Detector base, hood and evaporator EDR Nov-15 36  
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Nov-15 37  
MUON additional shielding EDR Nov-15 38  
RICH RICH1 Mirrors + Supports PRR Nov-15 39  
VELO module Module EDR Dec-15 40  
RICH RICH mechanics EDR, incl Gas encl., Phot boxes, Phot funnel Interfaces Dec-15 41  
UPSTREAM TRACKER Sensor 128 ch asic hybrid submission Dec-15 42  
SCIFI SiPM + Electronics + ROB Joint EDR Jan-16 43  
UPSTREAM TRACKER Sensor SENSOR PRR Jan-16 44  
SCIFI   Fibre mats PRR Feb-16 45  
UPSTREAM TRACKER ELECTRONICS FLEX CABLE PRR Feb-16 46  
CALORIMETER Front-End board (FEB) PRR Feb-16 47  
CALORIMETER Control Board (CB) EDR Feb-16 48  
CALORIMETER HV , Monitoring, Calib, GBT EDR Feb-16 49  
SCIFI   ROB PRR Mar-16 50  
VELO detector base hood Detector base, hood & Evaporator PRR Mar-16 51  
DATA PROCESSING Generic readout board preseries completed and qualified Mar-16 52  
DATA PROCESSING Optical fibres Long distance operational reliability Mar-16 53  
MUON additional shielding launch order (PRR) Mar-16 54  
UPSTREAM TRACKER Mechanics and cooling Instrumented stave PRR Mar-16 55  
SCIFI   Module PRR Apr-16 56  
UPSTREAM TRACKER SALT Chip SALT PRR Apr-16 57  
UPSTREAM TRACKER Integration UT Box and frame EDR Apr-16 58  
VELO electronics ASIC, hybrid PRR Apr-16 59  
VELO electronics Velopix Submission 2.1 (PRR) May-16 60  
UPSTREAM TRACKER Sensor 128 CH HYBRID PRR Jun-16 61  
DATA PROCESSING Event-building Software scalability 600 nodes Jun-16 62  
DATA PROCESSING Trigger 1st Bi-annual update (CPU growth, code performance, strategy, alternative plateforms, review optimisation tasks, bandwidth optimization) Jun-16 63  
UPSTREAM TRACKER ELECTRONICS PEPI/LV PRR Jul-16 64  
MUON electronics Full electronics chain tested Jul-16 65  
RICH RICH mechanics PRR Jul-16 66  
SCIFI   SIPM PRR Aug-16 67  
VELO module Module PRR Aug-16 68  
CALORIMETER Control Board (CB) PRR Aug-16 69  
CALORIMETER HV, Monitoring, Calib, GBT PRR Aug-16 70  
SCIFI   PACIFIC PRR Oct-16 71  
VELO RF foil RF foil PRR Oct-16 72  
VELO cooling Cooling PRR Oct-16 73  
SCIFI Frames EDR Nov-16 74  
SCIFI cooling cooling plants PRR Dec-16 75  
MUON nSYNC Final submission (PRR) Jan-17 76  
MUON nODE start production (PRR) Jan-17 77  
MUON nPDM start production (PRR) Jan-17 78  
MUON nSB start production (PRR) Jan-17 79  
DATA PROCESSING Computing TDR Mar-17 80  
DATA PROCESSING Farm and Data centre Conteiner selected; start construction of data centre building Jun-17 81  
DATA PROCESSING Event-building Test in HPC, 400 nodes at least 20 Tb/s Nov-17 82  
CALORIMETER Installation ready for installation Sep-18 83  
DATA PROCESSING Computing Computing model for the Run 3 Sep-18 84  
MUON Installation ready for installation Sep-18 85  
RICH Installation ready for installation Sep-18 86  
SCIFI   ready for installation Sep-18 87  
VELO Installation ready for installation Sep-18 88  
DATA PROCESSING Farm and Data centre Decide on readout network technology Oct-18 89  
DATA PROCESSING Trigger 2nd Bi-annual update (CPU growth, code performance, strategy, alternative platforms, review optimisation tasks, bandwidth optimization) Oct-18 90  
DATA PROCESSING Trigger Decision on output bandwidth and on output data flows Oct-18 91  
DATA PROCESSING Installation Online ready for sub-detectors commissioning Feb-19 92  
DATA PROCESSING Trigger Trigger configuration for startup Feb-19 93  
UPSTREAM TRACKER Installation ready for installation Feb-19 94  
DATA PROCESSING Installation Online system ready for data-taking Feb-20 95  
 
<!--edittable1-->

ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.

Revision 52015-02-12 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
Changed:
<
<
<!-- /editTable -->
>
>
<!-- /editTable -->
 
Changed:
<
<
System item milestone date number
>
>
System item milestone date number comments
 
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2
RICH CLARO + Front-End Board PRR Feb-15 3

Revision 42014-12-09 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"

<!-- /editTable -->
Line: 103 to 103
 ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.
Changed:
<
<
>
>
 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
milestones 2 2 2 5 6 8 11 15 23 27 28 32 39 42 44 49 55 59 60 63 66 70 70 73 74 75 79 79 80 80 80 81 81 81 81 81 82 82 82 82 82 82 82 82 82 82 88 91 91 91 91 94 94 94 94 94 94 94 94 94 94 94 94 95 95 95 95

Revision 32014-12-09 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"

<!-- /editTable -->
Line: 94 to 94
 
DATA PROCESSING Farm and Data centre Decide on readout network technology Oct-18 89
DATA PROCESSING Trigger 2nd Bi-annual update (CPU growth, code performance, strategy, alternative platforms, review optimisation tasks, bandwidth optimization) Oct-18 90
DATA PROCESSING Trigger Decision on output bandwidth and on output data flows Oct-18 91
Changed:
<
<
DATA PROCESSING installation Online ready for sub-detectors commissioning Feb-19 92
>
>
DATA PROCESSING Installation Online ready for sub-detectors commissioning Feb-19 92
 
DATA PROCESSING Trigger Trigger configuration for startup Feb-19 93
UPSTREAM TRACKER Installation ready for installation Feb-19 94
DATA PROCESSING Installation Online system ready for data-taking Feb-20 95
<!--edittable1-->

ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.

Changed:
<
<
>
>
ChartPlugin error:
parameter table is not valid table;
the specified table 'milestones
upgrade' does not exist.

 
year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
milestones 2 2 2 5 6 8 11 15 23 27 28 32 39 42 44 49 55 59 60 63 66 70 70 73 74 75 79 79 80 80 80 81 81 81 81 81 82 82 82 82 82 82 82 82 82 82 88 91 91 91 91 94 94 94 94 94 94 94 94 94 94 94 94 95 95 95 95
milestones achieved 2 2
Added:
>
>

  -- RolfLindner - 2014-12-08

Revision 22014-12-09 - RolfLindner

Line: 1 to 1
 
META TOPICPARENT name="TWiki.WebPreferences"
Changed:
<
<
<!-- /editTable -->
>
>
<!-- /editTable -->
 
System item milestone date number
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2
Line: 12 to 13
 
RICH MaPMT Place MaPMT order and start production Apr-15 8
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9
VELO sensors Sensor and thinned bump bonding EDR May-15 10
Changed:
<
<
>
>
CALORIMETER Front-End ASIC EDR May-15 11
UPSTREAM TRACKER SALT Chip SALT EDR Jun-15 12
UPSTREAM TRACKER ELECTRONICS FLEX CABLE EDR Jun-15 13
UPSTREAM TRACKER Mechanics and cooling Stave EDR Jun-15 14
RICH RICH1 Mirrors and Supports EDR, spherical and flat mirrors with their supports Jun-15 15
SCIFI Fibres, mats, modules Joint EDR Jul-15 16
UPSTREAM TRACKER Sensor SENSOR EDR Jul-15 17
UPSTREAM TRACKER ELECTRONICS PEPI/LV EDR Jul-15 18
VELO cooling substrate Cooling Substrate EDR Jul-15 19
MUON nSYNC EDR Jul-15 20
MUON nODE EDR Jul-15 21
MUON nPDM EDR Jul-15 22
MUON nSB EDR Jul-15 23
UPSTREAM TRACKER SALT Chip 128 ch. ASIC submission Aug-15 24
VELO electronics ASIC, hybrid EDR Aug-15 25
MUON nSYNC prototype submission Aug-15 26
UPSTREAM TRACKER Sensor type A prepr subm. Aug-15 27
RICH Digital board PRR Sep-15 28
VELO cooling substrate Colling Substrate PRR Oct-15 29
VELO cooling Cooling EDR Oct-15 30
CALORIMETER Front-End ASIC PRR Oct-15 31
CALORIMETER Front-End board (FEB) EDR Oct-15 32
UPSTREAM TRACKER Sensor 128 CH HYBRID EDR Nov-15 33
UPSTREAM TRACKER Integration Cooling EDR Nov-15 34
VELO sensors Sensor PRR Nov-15 35
VELO detector base, hood Detector base, hood and evaporator EDR Nov-15 36
DATA PROCESSING Event-building Event-building with 32-port switch in at least one technology Nov-15 37
MUON additional shielding EDR Nov-15 38
RICH RICH1 Mirrors + Supports PRR Nov-15 39
VELO module Module EDR Dec-15 40
RICH RICH mechanics EDR, incl Gas encl., Phot boxes, Phot funnel Interfaces Dec-15 41
UPSTREAM TRACKER Sensor 128 ch asic hybrid submission Dec-15 42
SCIFI SiPM + Electronics + ROB Joint EDR Jan-16 43
UPSTREAM TRACKER Sensor SENSOR PRR Jan-16 44
SCIFI   Fibre mats PRR Feb-16 45
UPSTREAM TRACKER ELECTRONICS FLEX CABLE PRR Feb-16 46
CALORIMETER Front-End board (FEB) PRR Feb-16 47
CALORIMETER Control Board (CB) EDR Feb-16 48
CALORIMETER HV , Monitoring, Calib, GBT EDR Feb-16 49
SCIFI   ROB PRR Mar-16 50
VELO detector base hood Detector base, hood & Evaporator PRR Mar-16 51
DATA PROCESSING Generic readout board preseries completed and qualified Mar-16 52
DATA PROCESSING Optical fibres Long distance operational reliability Mar-16 53
MUON additional shielding launch order (PRR) Mar-16 54
UPSTREAM TRACKER Mechanics and cooling Instrumented stave PRR Mar-16 55
SCIFI   Module PRR Apr-16 56
UPSTREAM TRACKER SALT Chip SALT PRR Apr-16 57
UPSTREAM TRACKER Integration UT Box and frame EDR Apr-16 58
VELO electronics ASIC, hybrid PRR Apr-16 59
VELO electronics Velopix Submission 2.1 (PRR) May-16 60
UPSTREAM TRACKER Sensor 128 CH HYBRID PRR Jun-16 61
DATA PROCESSING Event-building Software scalability 600 nodes Jun-16 62
DATA PROCESSING Trigger 1st Bi-annual update (CPU growth, code performance, strategy, alternative plateforms, review optimisation tasks, bandwidth optimization) Jun-16 63
UPSTREAM TRACKER ELECTRONICS PEPI/LV PRR Jul-16 64
MUON electronics Full electronics chain tested Jul-16 65
RICH RICH mechanics PRR Jul-16 66
SCIFI   SIPM PRR Aug-16 67
VELO module Module PRR Aug-16 68
CALORIMETER Control Board (CB) PRR Aug-16 69
CALORIMETER HV, Monitoring, Calib, GBT PRR Aug-16 70
SCIFI   PACIFIC PRR Oct-16 71
VELO RF foil RF foil PRR Oct-16 72
VELO cooling Cooling PRR Oct-16 73
SCIFI Frames EDR Nov-16 74
SCIFI cooling cooling plants PRR Dec-16 75
MUON nSYNC Final submission (PRR) Jan-17 76
MUON nODE start production (PRR) Jan-17 77
MUON nPDM start production (PRR) Jan-17 78
MUON nSB start production (PRR) Jan-17 79
DATA PROCESSING Computing TDR Mar-17 80
DATA PROCESSING Farm and Data centre Conteiner selected; start construction of data centre building Jun-17 81
DATA PROCESSING Event-building Test in HPC, 400 nodes at least 20 Tb/s Nov-17 82
CALORIMETER Installation ready for installation Sep-18 83
DATA PROCESSING Computing Computing model for the Run 3 Sep-18 84
MUON Installation ready for installation Sep-18 85
RICH Installation ready for installation Sep-18 86
SCIFI   ready for installation Sep-18 87
VELO Installation ready for installation Sep-18 88
DATA PROCESSING Farm and Data centre Decide on readout network technology Oct-18 89
DATA PROCESSING Trigger 2nd Bi-annual update (CPU growth, code performance, strategy, alternative platforms, review optimisation tasks, bandwidth optimization) Oct-18 90
DATA PROCESSING Trigger Decision on output bandwidth and on output data flows Oct-18 91
DATA PROCESSING installation Online ready for sub-detectors commissioning Feb-19 92
DATA PROCESSING Trigger Trigger configuration for startup Feb-19 93
UPSTREAM TRACKER Installation ready for installation Feb-19 94
DATA PROCESSING Installation Online system ready for data-taking Feb-20 95
 
<!--edittable1-->
Added:
>
>

year Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
milestones 2 2 2 5 6 8 11 15 23 27 28 32 39 42 44 49 55 59 60 63 66 70 70 73 74 75 79 79 80 80 80 81 81 81 81 81 82 82 82 82 82 82 82 82 82 82 88 91 91 91 91 94 94 94 94 94 94 94 94 94 94 94 94 95 95 95 95
milestones achieved 2 2
 -- RolfLindner - 2014-12-08

Revision 12014-12-08 - RolfLindner

Line: 1 to 1
Added:
>
>
META TOPICPARENT name="TWiki.WebPreferences"

System item milestone date number
RICH CLARO + Front-End Board EDR 7th of Oct Nov-14 1
RICH Elementary Cell EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" Nov-14 2
RICH CLARO + Front-End Board PRR Feb-15 3
RICH Elementary Cell PRR Feb-15 4
RICH Digital board EDR DB hardware with basic firmware + ECS Feb-15 5
MUON Spare MWPC start production (PRR) Mar-15 6
RICH Photon Detector Module EDR Optoelectronic chain module + assembly Apr-15 7
RICH MaPMT Place MaPMT order and start production Apr-15 8
SCIFI prototype module Large size prototype module (>= 2.5 x 0.54 m2) May-15 9
VELO sensors Sensor and thinned bump bonding EDR May-15 10
<!-- /editTable -->

<!--edittable1-->

-- RolfLindner - 2014-12-08

 