AB Safety Unit
Meeting 22 01 2009:
Present: Ghislain Roy; Isabel Brunner; Luca Bruno; ; Markus Widorski; Fabrice Chapuis; Jose-Luis Duran-Lopez; Roberto Bonzano; ; Idelette Floret; Steve Hutchins.
Excusés : ,
GR reorganisation
IF stockage RP? BF saFETY SPECIALISTS BEEAM
tour de table:
GR: ventilation BA80, procedure with beam permit , RP keeps ventilation key, OP soft interlock on air flow
LB: TAN concption weak, Atlas ok CMS next week
LB: NTOF ventilation, control of emmisions. RB to check interlocks
LB: source berylium needs recycling
IF: PS port materiel ? Procedure TSO : no guardien, CSA control? Jose to verify with R.Brown
IF: access 4
FC: Linac4/linac2 interlocks, LB: shielding calcule, 20cm extra found 40cm more needed. Interlock on source, IF to call meeting
GR: radioprtection courses not followed: will change rule, also prp11 escorted visitor procedure
GR: reorganisation BFSP, DSOs in sector, task force accesibility LHC
--
SteveHutchins - 22 Jan 2009