- Point 2
Most of the lost raw data from the 900 GeV run has been recovered by the CERN IT department. There has been no data taking with stable beams since 5. June
because of machine commissioning. Physics data taking is expected to resume tonight. All subsystems have been requested to provide a Heavy-Ion like configuration
for tests (i.e. a configuration which provides approximately the same event size as in heavy-ion collisions). PHOS has done this and has taken part in several technical
runs with this configuration.
- RCU
The connection to Branch A, RCU0 on Module 3 was lost after the access during the technical stop 31/5 - 2/6. Presumably someone went under Module 3 and touched the
RCU which led to it being disconnected. This was fixed during an access on 8/6 (Sasha and Oystein). The same problem appeared again yesterday, again following an
access into L3 on Tuesday. It has still not been recovered. Access is needed.
- DCS
The HV server was down for 3 days without anyone noticing. It should be part of the daily routine of the PHOS On Call to check this connection at least once daily.
- Trigger
The TRU fakealtro data from the test setup in Bergen can be read back. There are problems with generating a signal in the test setup so the timing issue has not yet
been studied.
- LTU
The LTU lent to the TPC people has been returned.
- PHOS Shifter/OnCall manual
A new version is available from the ALICE Run pages (Joakim, Sergey).
27 May 2010 PHOS Commissioning Meeting
Minutes
- Point 2
The raw data from the 900 GeV runs taken about 3 weeks ago have been lost. New 900 GeV runs are being taken now. There will be a
technical stop next week 31/5 - 2/6.
- Shifts
The PHOS shifts were cancelled from 17/5. No problems encountered so far.
- Electronics
A new RCU firmware version from Attiq is available. It will be installed and tested during the technical stop next week. It
should hopefully reduce the dead-time significantly.
- Trigger
A global run (120967) with PHOS triggered by PHOS when the LED system was running was taken yesterday. The fakealtro
data were written out. An analysis of this data did not show any signal in the fakealtro data, however. This is being investigated
by Lijiao and Dong.
- DCS
There was a problem with the LED VME crate during last weekend. What caused it is unknown. The problem fixed itself
It is being followed up by Alexandre Vinogradov.
- LTU
No news.
6 May 2010 PHOS Commissioning Meeting
Minutes
- Point 2
Running at 900 GeV during the previous weekend. 7 M events were recorded. The plans for LHC are to do machine development during the day and physics
running (7 TeV) during the night.
- DCS
Alexander Mamonov has been working on the implementation of the LED system in PVSS. He is also working on updating the text
for the PHOS alarms and improving the PHOS alarms mailing list. At the moment, only an interlock for the cooling plant generates a mail, but
in the future any hardware or software interlock will send a mail to the alarm list. The changes to the FEE control done by Kyrre last week
will also be included in the PVSS.
- Shifts
Progress on writing of documentation for global shifters and PHOS On Call:
DCS (Alexander Mamonov) - in progress;
DQM (Oystein, Yuri Kharlov) - in progress;
On Call (Joakim) - Included in the new version of the shift manual.
Sergey Nikolaev is working on updating the PHOS manual to incorporate the latest changes to the DCS system.
- LTU
No news. Bernhard will check.
29 april 2010 PHOS Commissioning Meeting
Minutes
- Point 2
20 Mevents were recorded last weekend. The total number of recorded events is now more than 35 M. One run with 100,000 physics triggers
has been taken with the PHOS TRUs being read out. There has been a technical stop Mon-Wed this week. The LHC is recovering and the first stable
beams are expected Saturday evening. The goal is then to collect 10 Mevents at 900 GeV before continuing running at 7 TeV.
- DCS
Henrik and Kyrre have been working on implementation of FEE control this week. It is now possible to configure from PVSS, but the actual configuration commands
are not yet implemented. The temperatures can only be read from about half of the FEE cards. Alexander Mamonov has also made several updates to the DCS systems
but since he is not present at the meeting the details are not available.
- Shifts
We still keep PHOS shifts during day and evening. A set of instructions for global DCS shifter (Alexander Mamonov), DQM shifter (Yuri Kharlov, Oystein Djuvsland),
PHOS On Call (Joakim Nystrand) have to be written before the shifts can be cancelled. The current plan is to cancel shifts from 15. May.
Alexei Kuryakin has created a mailing list for notification in case of an cooling interlock.
- Cooling system
The cooling system has been reconnected to the UPS. The reset button in CR-4 has been checked.
15 april 2010 PHOS Commissioning Meeting
Minutes
- Point 2
Commissioning of the accelerator during the day; physics running during the night. PHOS remains stable in the runs.
- Trigger
Tests of trigger timing module by module. Two TRUs have had to be masked out.
- DCS
Alexander Mamonov is now at CERN until 16 May. He will work on improving the PHOS DCS
and PHOS in the Alice Configuration Tool (ACT). Kyrre and Henrik will go to CERN for the
technical stop 26-28 April to work on the Intercom layer.
- Shifts
The proposal to end PHOS shifts by 1. May is being considered.
8 april 2010 PHOS Commissioning Meeting
Minutes
- Point 2
First pp collisions at 7 TeV occured on 30 March. Since then about 8 Mevents have been accumulated. PHOS has been
very stable and has participated in all runs taken. Today there is access. More collisions are expected on Saturday and
Sunday.
- Gain settings
The first analysis of the new data at 7 TeV taken with fixed pedestals indicate that the current calibration is off by a
factor 2.5. We have to decide as soon as possible if we should keep the current gain or reduce it.
- Trigger
The new trigger firmware was tested on Sunday. The signal from PHOS now arrives earlier than the other subsystems.
There is a larger jitter now (3-4 beam clocks) than before. This is not expected to be a serious problem but Anton will
be consulted.
See timing plots here
orbit1orbit2
- DCS
There remains work to be done on ACT and on implementation of control of FEE in PVSS. The LHC schedule should be
investigated so that people can plan their travel to CERN.
- Shifts
A discussion of when it is time to cancel shifts should be started. At the last PHOS meeting it was proposed to end
shifts at the end of April. It is important that experts sign up for On Call shifts for PHOS.
- PHOS lab
The missing LTU is still missing.
18 march 2010 PHOS Commissioning Meeting
Minutes
- Point 2
Cosmic data have been accumulated with the TRU trigger during the last week. About 700,000 events
have been recorder. Collisions at 900 GeV now expected on Sunday (21/3), starting at midnight 00:00.
- Pulse shape
Problem with 2-peak structure has been solved by introducing fixed pedestals. Luciano has an explanation
why the two-peak structure can appear if the automatic pedestal calculation is interrupted by a
signal.
The stability of the pedestal has been checked. The difference between pedestals taken 3 days
apart are very small; the mean has changed by roughy 0.1 unit or less depending on Module and the
RMS is also low, roughly 0.1 unit or less. There are some outliers, but those are all associated with
channels that are already in the bad-channel map.
See Oystein's presentation here
http://indico.cern.ch/getFile.py/access?resId=1&materialId=slides&confId=88546
- Results from cosmic runs
Results from Boris. Good matching with TPC tracks, = 2.5 cm. The energy spectrum
shows a nice mip-like peak with a mean, however, at 770 MeV. This would correspond to a APD
gain of about 150 rather than the expected 50. This is not understood.
See Boris' plots here
http://indico.cern.ch/getFile.py/access?resId=0&materialId=slides&confId=88546
- Trigger
Because of the work with the pulse shape and implementation of fixed pedestals it has not been
possible to test the new trigger firmware. It should be done as soon as possible.
- DCS
The ACT problem for LED runs persists.
- Shifts/OnCall
The night shifts have been replaced by OnCall. Most subsystems, most likely also PHOS,
will cancel all shifts from mid-April. People are encouraged to get trained and sign up for
shifts for the global systems like DCS.
- PHOS lab
An LTU is still missing. Oystein will look into it. A new VME crate is needed. Iouri will change it.
11 march 2010 PHOS Commissioning Meeting
Minutes
- Point 2
Beams are circulating in the machine most of the time. Collisions at 900 GeV are planned
for 3 shifts on Friday 19 March. Collisions at 7 TeV are expected before the end of this month.
- Trigger
A new version has been developed which meets the 800 ns time limit for L0 input to the CTP.
The time sum has been removed and the signal is extracted from a single 50ns time bin.
Space sum is still performed.
- DCS
There is still a small memory leak present when opening the LV panels.
There are still problems with handling LED runs in the ACT (ALICE Configuration
Tool).
- Raw data
Dmitri reported on the details of the problem with corrupted data when PHOS is triggered
by the CTP. His report is available here
http://indico.cern.ch/conferenceDisplay.py?confId=87896
Oystein described the progress made in implementing reading of fixed pedestals and
loading them into the ALTRO. It is expected that this will fix the corruption problem.
- PHOS lab
Date has been updated on the pc in the PHOS lab. One LTU is still missing.
- Shifts
The need for people to serve as PHOS OnCall was reiterated.
4 march 2010 PHOS Commissioning Meeting
Minutes
- Point 2
Circulating beams are expected next week.
- Trigger
The TED test last Friday showed that the PHOS trigger works but that it is delayed by
5-6 beam clocks (about 150 ns). Firmware with a new trigger algorithm is being developed
to make it faster.
It has been found that LED signals and signals from Cosmics taken with the PHOS trigger
are corrupted and show a two-peak structure rather than the expected Gamma-2 shape.
The cause for this is being investigated.
- DCS
Thanks to the work of Alexander, Kyrre, and Jiro several problems have been
fixed. The memory leak when opening the LV panel is now gone. The fluctuating
HV states have been fixed by changing the FSM logic.
- FEE
The PC aldaqpc019 in the PHOS lab will be upgraded and a new version of date (DAQ)
will be installed.
- Shifts
Since PHOS runs stably and there is not much to do during the night, all or most night shifts
can be cancelled and replaced by having people OnCall.
- Cooling system
The cooling system will be removed from the UPS; only the control system will be connected
to UPS.
25 Feb 2010 PHOS Commissioning Meeting
Minutes
- Point 2
Last Thursday evening there were beam splashes on the TED. PHOS took data. More splashes are expected
tomorrow, Friday 26/2.
- Trigger
The tests of the PHOS trigger during the TED dumps were
inconclusive because of secondary triggers generated by the read out. This was fixed on Sunday. Since then, cosmics
have been collected with the PHOS trigger during the nights. On Wednesday (24/2) PHOS was for the first time used to
trigger the ALICE experiment in a clusted which included PHOS and the TPC.
- PVSS
Kyrre will work with Marco on Monday to solve the remaining ACT problems. The problems with fluctuating (HV) states
have been traced to the ISEGs. One feature is that the clock is shifted by 15 min per day. A memory leak has been
spotted which leads to a frozen LV display if it is kept open for more than 1-2 mins.
- FEE
Repair of FEEs in PHOS lab. The PC in the phos lab (aldaqpc019) has to be upgraded to SLC5 in order to get the
latest version of DAQ (date). Users who want to save their data on the disk should make backups.
18 Feb 2010 PHOS Commissioning Meeting
Minutes
- Trigger
6 good TRUs yesterday, today 1 or 2.
m4 TRUs un-configured state after data taking
LED only one module?
- Cooling
stable
- RCU
- IntercomLayer
New java icl is installed, works better than the old one. Need to reduce the number of services. Re-programming the RCU not working with new FeeServer.
"no link" seen in PVSS.
- PVSS
ALICE Configuration Tool test. LED - not working, PHYSICS - working.
Kyrre working on solutions to problems.
11 Feb 2010 PHOS Commissioning Meeting
Minutes
- Point 2
The L3 magnet will close at 17:00 today and the field will be turned on at 18:00. The ALICE cavern will close on 15. February.
PHOS would like to participate if there are runs with dumps on TED. This will probably happen next week.
- Trigger
Lijiao presented results from the trigger tests. When the LED system is run at 20 Hz one can read back a stable trigger rate
of 20 Hz from TOR. The background rate is below 1 Hz. The trigger threshold is set at x100. The influence of a possible LED
phase shift between modules was discussed but no firm conclusion was reached. The next step in the trigger commissioning
will be to set up a global partition with a PHOS trigger from the CTP. Lijiao's presentation is here
http://indico.cern.ch/materialDisplay.py?materialId=slides&confId=84724
- LED
Most of module 3 has now been illuminated by the LED system but there are still some bugs in the LED firmware or software.
- Cooling
Monday, Wednesday, Thursday this week there have been interventions to the PHOS crystal cooling plant. On Monday a broken power
supply was replaced. Hopefully the intervention today will be the last one before the closing of the ALICE cavern. In the future,
these interventions have to be announced further in advance, for example at the commissioning meetings.
- RCU
The PHOS busy time is now 830 microsec, down from 1400 microsec last year. There is hope that it can be reduced by another 100-200 microsecs
through upgrades of the RCU firmware.
- FEE
Bernhard and Iouri will start repairing the 28 broken spare FEEs on Monday.
- AMORE
The functionality should be tested.
- Intercom layer
A new java-based version of the Intercom layer has been installed by Kyrre with help from Oystein and
Timur. It remains to get the database lists in correctly and it still kills the FEE servers occasionally,
- PVSS
The PHOS PVSS system stores too much information on temperatures and voltages. In fact, the volume from
PHOS is larger than from all other subsystems combined. This must be reduced. The best way would be to implement
smoothing, i.e. only save a value if it deviates significantly from the previous reading. Kyrre, Serguei, Yuri, and Alexander
are looking into this.
28 Jan 2010 PHOS Commissioning Meeting
Minutes
- Point 2
The main activity during the past week has been trigger develpoment work done from Bergen. From Wednesday afternoon
around 4 PM PHOS has been off because of the UPS intervention.
- Trigger/TRU
The tests by Jiri, Dong, and Lijiao on the test bench in Bergen have been successful. The next step is to take pedestal
data at Point 2 and find a map of noisy channels to mask out. Then one can test to trigger on a LED signal.
- LED
LED data have been taken for most parts of module 3. The missing parts are due to a bug in the LED software
which should be fixable. From LED data from Module 2, Yuri has found that the some of the APDs in that module
appear to be overcalibrated.
- Sparse read-out
Sparse read-out now works for EmCal, but improvements in the RCU firmware for increased speed is still
being worked on. The implementation of sparse read-out in EmCal only involved changes to the RCU firmware.
The same (or very similar) changes should be tested and implemented for PHOS.
- FEE
There are 28 FEE cards that need to be repaired. Iouri will come to CERN next week to work on that. A RCU is
needed for testing the cards.
- AMORE
Amore now works if an environment variable is set correctly. This will be done in the login script once the daq
computers are back after the upgrade.
- Shifts
Day and evening PHOS shifts will start from Monday morning.
21 Jan 2010 PHOS Commissioning Meeting
Minutes
- Point 2
A pedestal run was taken on Thursday (14/1) and the pedestal RMSs were identical to what was seen at the end
of last year (Mod. 2: 0.93, Mod. 3: 0.84, Mod. 4: 0.70).
Oystein has changed the read-out order from the RCU so that it now alternates between the two branches. This had
the effect of reducing the PHOS busy time to below 1 ms and thus enabling running at rates of 1 kHz. This is
great progress! It means that we don't have to cut out any PHOS channels to achieve low enough busy time.
- LED system
Yuri and Sasha have worked on the LED system. On module 4, a bad connection to the "black box"
on the module was found. After it was reconnected, the LED system again works in Module 4 (except
for some well know L-shaped areas). All LEDs in Module 3 can be fired provided that one runs with a
single 16x2 band of LEDs at a time. Yuri's presentation is here
http://indicobeta.cern.ch/getFile.py/access?contribId=0&resId=1&materialId=slides&confId=81872
- RCU extension on module 3
Bernhard and Sasha have been working on this for the last week, but no solution has been found. It must
most likely wait until the module is taken out of the pit.
- FEEs in PVSS
A new Intercom layer is being developed and is currently tested by the TPC and TRD. When it is
ready for PHOS, the implementation of control of the PHOS FEEs in PVSS can start. Also the FEE
temperatures will then be included in PVSS.
- AMORE
The PHOSagent doesn't work in the latest version. Yuri is working on it.
- Other topics
The weekly SRC meetings will start next Tuesday, 26/2. The daily meetings at Point 2 will
start on 1. Feb.
PHOS commissioning in 2009
19 Nov 2009 PHOS Commissioning Meeting
Minutes
- Point 2
The reset of the trigger clock at start of run has been removed. This was the main reason for
PHOS going busy earlier. A new ramping sequence for Module 2 has been found. It brings
up Module 2 with low noise levels after a power cycle. The ramping sequences are different
for Module 2 and Modules 3,4.
- LED
There are problems with the LED system in Module 3. It was decided to reboot the LED
system later today at 5 PM.
- APD
Dmitri Peressounko presented some investigations of the noise levels in Module 4
for different voltages and APD settings. See his presentation
http://prsnko.web.cern.ch/prsnko/APDsettingsMod4.pdf
- PVSS
Alexander Mamonov listed some of the tasks that should be improved in PVSS:
-Add cooling loop status
-Update existing interlocks
-Update the shift instructions for how to handle interlocks
-data to offline database
It was decided, however, to not implement any of these changes at the moment because
of the short time expected before the first collisions. The development during next week
will probably make the situation clearer and it will then be possible to decide when they
can be implemented.
Some settings in PVSS will, however, be changed. The ramping speed when switching off the
HV in emergencies will be reduced from 50 V/s to 10 V/s. The maximum allowed
temperature for the FEE cards will be reduced from 50 C to 35 C.
12 Nov 2009 PHOS Commissioning Meeting
Minutes
- Point 2
Access yesterday by Iouri and Dmitri. The LED box on Module 3 was replaced. All the TRUs on
Module 4 now work. In preparation for the UPS intervention on Wednesday and Thursday the cooling was
switched off. It was switched on again after the tests.
- RCU
The noise situation has improved considerably in Modules 2 and 3. The main reason for
this is the fix by Iouri and Dmitri of the input LV last week. The pedestal RMS are now
0.92 in Module 2, 0.86 in Module 3, and 1.68 in Module 4. The event sizes in empty
events are around 2 kByte/LDC with ZS threshold 3, corresponding to a total PHOS
event size of about 12 kByte/event. This is when the latest firmware, which includes
zero-skipping, is used on all RCUs.
Øystein found that by turning off one FEE card on the outermost RCU of Module 4 the noise
level of that RCU improved considerably. There are still some bad channels in Module 4.
Dmitri Peressounko has investigated the behaviour of the bad channels when lowering the HV.
The study is still ongoing.
-TRU
The signals from the TRU/TOR should be checked and compared with the LED trigger signals at the CTP.
-ERP tests
PHOS has performed without problems in the last 3 ERP tests. There is still an issue
with PHOS going busy. The problem has been solved for the EMCAL, however, by
removing the TTCrx reset from the CTP start of run sequence. The same solution
should work for PHOS and should be implemented as soon as possible.
5 Nov 2009 PHOS Commissioning Meeting
Minutes
- Point 2
The steel pipes which were dicscovered above Module 2 last week have been rerouted.
Several things were done by Iouri and Dmitri during the access yesterday. An attempt was made to reconnect
the TRU on the dead branch on Module 4. This was unsuccessful. The LV output was checked and in particular
on the 13V channel for Module 3 and 4 large oscillations were detected. The configuration of the Wiener PWS
was changed to fix this. The LED box on Module 3 was found to be cold, indicating that it was not working. By
disconnecting and reconnecting the cable it came back to life.
- TRU
The right firmware is now installed on all the TRUs on Module 2 and 3. 4 out of the 8 TRUs on Module 2
have been tested with LED signals. Only branch A of the TRUs can be read-out, however. The sending
of a PHOS trigger signal to the CTP should be tested and the timing should be checked.
-Pedestals
After the reconfiguration of the Wiener PWS the pedestal RMS is now much lower in Module 3. One
does not observe any events where the pedestal baseline is shifted by a large amount from one event to another.
- LED system
Yuri has analysed some LED runs. The output from Module 2 shows some holes with ADC<10
in both the high gain and low gain channels. In Module 3, signals are only seen in less than 1/4 of
the module.
29 Oct 2009 PHOS Commissioning Meeting
Minutes
- Point 2
During the access it was discovered that 10 steel pipes with diameter 1 cm had been installed in front of
PHOS Module 2. The Technical coordinators have been notified. These pipes have to be rerouted before
the start of the run.
The PHOS HV crate turns itself off without warning. It happened around 8 AM yesterday (28/10), at about the
same time today (29/10), and at 5 PM today (right after the meeting). It is not clear why this happens. Andre
Agustinus will connect the power supply to an UPS to see if that helps.
During the access today, the polarity of the Trigger Level 1 cable with wrong polarity was switched.
- APD
A bug was found by Oystein in the setting of the APDs for module 3. After it was fixed, the noise is
lower in Module 3.
- TRU
A bug has been found in the TRU firmware. 3 TRUs in Module 2 now deliver stable triggers in LED runs.
- HLT
The geometrical projection trigger is being tested, but there are memory leaks.
- AOB
Joakim informed about the new PHOS Run Coordinator page
https://aliceinfo.cern.ch/Collaboration/Technical_Coordination/ALICE_Project/PHOS/PHOS_shifts/index.html
22 Oct 2009 PHOS Commissioning Meeting
Minutes
- Point 2
As a result of the access yesterday, all RCUs are now installed. The complete Module 3 can be read out,
including the bad branch, but the data in that branch appears to be corrupt. The power trips when the TRUs
on Module 2 are turned on. One of the L1 cables going from PHOS to CTP has the wrong polarity, which
has to be reversed.
- Cooling
The crystals are now at -25 C, the design temperature. When the LV was switched off during the access
yesterday, it was noted that the temperature in the warm volume saturated around 5-7 C.
- APD
New APD settings are being calculated by Hisa. They should be for gain 50 at -25 C. The settings for
Module 4 should be calculated for 380 V.
- DCS
A fix to leave the HV on when in the state "beam tuning" has been implemented by Kyrre.
- HLT
The geometrical projection trigger is available and ready for testing.
- AOB
Dmitri presented a first list of tasks for shifters.
15 Oct 2009 PHOS Commissioning Meeting
Minutes
- Cooling
Cooling is progressing faster than anticipated last week. The modules are currently at about -7 C and are
approaching -15 C. The humidities are 22% in Phos2, 27% in Phos3, 24% in Phos4.
- RCU
One RCU (90) was removed from Module 4 during the access yesterday. It will be tested in the lab and
put back next Wednesday.
- HV
As the temperature is now rather rapidly approaching -25 C, the need for APD settings for intermediate
temperatures is less urgent. New settings should be calculated for Module 4, however, since it is operating
at 380 V (not 395 V).
- DCS
The problems with the intercom layer persist.
- Analysis of data from cosmic and injection test runs
Yuri reported on an analysis of data from the beam injection test 3 weeks ago. The presentation is
available from the link below. Boris has looked at the cosmic data and analysed about 3 Mevents. There
appears to be some noise also in module 2, see figure below. It was not clear if this amount of noise is
what is expected with the observed RMS and threshold settings (For Module 2, pedestal RMS 2, threshold 4).
Distribution of clusters in Module 2 for cosmic data (Boris Polichtchouk):
08 Oct 2009 PHOS Commissioning Meeting
Minutes
- Status at Point 2
During the access yesterday (7/10/09) the problem with the LED signals in Module 3 was found and solved. The
cable between the racks and the module had to be replaced. The pulse1 LED cable now goes to Module 3.
- Cooling
The reason for the crash last week has been understood and taken care of. A new interlock for the temperature of
the compressor has been installed. It is estimated that it will take 2-3 weeks to cool the modules down to -25 C.
When the cooling will start has not yet been decided. Next week one hopes to get a better estimate of the current
leakage rate.
-RCU
Parts of all modules are now normally included in the global runs during the evening and night shifts.
Mod. 2: All RCUs OK.
Mod. 3: 3 RCUs OK, but noisy at the moment.
Mod. 4: 2 RCUs OK, but one of them has a dead branch.
-HLT
An HLT trigger for tracks entering PHOS is being implemented.
01 Oct 2009 PHOS Commissioning Meeting
Minutes
-Status at Point 2
Last night PHOS ran stable in the global partition with 2 modules (2 and 3, one branch excluded) for 12 h. This is the
first time more than one module has been included in the global partition. Module 3 runs fine but is hard to get started
after the low voltage has been switched off.
-cooling
Cooling started on Monday (28/9) and +5 C was reached on Tuesday. The humidity in Mod. 4 was then between 25-40%, in Mod. 3 around 22%,
and in Mod. 2 12-14%. The temperature remained at +5 C until this morning (1/10) when there was a hardware problem and the cooling was turned
off. The problem was fixed and cooling resumed at around 11:00. The modules are now again approaching +5 C.
-RCU
The missing RCU on Mod. 3 was reinstalled during the access on Wednesday (30/9). One of the branches appears OK but the
other seems to produce only garbage output. Implementation of zero-skipping on the RCU is under way. This should significantly
reduce the PHOS event size.
-HV
Mod. 4 is now running with 380 V. New APD settings should be produced for this voltage. Since we don't know at what temperature
the cooling will stop, it would be good to have APD settings for a few different temperatures, for example -5, -10, -15, -20 C.
-DCS
Timur is working on the intercom layer and its inclusion in PVSS. Problems were encountered. An expert on the intercom layer in
PVSS should be contacted.
-Trigger
Oystein reported that he can now generate Level-0 triggers in LED runs.
-Analysis of data from beam injection test
Joakim has looked at some of the events from the beam injection test last weekend. One can see what appears to be clear
signals when looking at the pulses from individual cells. The amplitudes are always very low, seldom above 10-15 ADC counts
in the High Gain channel. The signals also appear later than expected by about 10-15 timebins (1.0-1.5 microsec). Further
studies are necessary.
17 Sep 2009 PHOS Commissioning Meeting
Minutes
- cooling
The humidity is going down, but Module 4 (or at least one of its sensors) shows a strange behaviour.
Cooling expert should arrive on Sunday.
- RCU
The missing RCU will be installed tomorrow. Bernhard arrived with extension cable.
The prospects for implementing sparse read-out on the RCUs are good and test will
begin next week.
- HV
The channel that tripped on Module 3 was fixed during the access on Monday. The problem
was a broken lemo connection. The HV channels on Module 4 are OK as long as the voltage
is below 380 V.
- DCS
Kyrre and Timur are working on debugging the Intercom layer.
- Trigger
A fix has been found for the EmCal trigger which reduces the noise. The same fix
should be applicable for PHOS and would improve the trigger noise situation.
- Cosmics
Boris has analysed some 2000 of the events that were recorded in the global physics
run with PHOS. No MIP peak has been observed, but that is not expected for that
number of events.
- Transfer line test 25-28 September
The current plan is to have PHOS ON during the transfer line test next week. This was done
last year without problems. But the potential risks for the detector should be considered before
the final decision is made.
03 Sep 2009 PHOS Commissioning Meeting
Minutes
- cooling
After the latest magnet access the water cooling is now in a good state.
Drying still ongoing.
- RCU
We have 11 DCS boards. One RCU+DCS is now out and is waiting for extention cable. Want to install next
Wednesday
Zero suppression and sparse readout tests ongoing.
- FEE
As reported before, one branch is dead, and one card is missing on module 4. Everything else seems fine.
- DAQ
Problems with the DDLs on the two lower RCUs on module 4. Investigation together with DAQ.
- DCS
All HW and SW interlocks are in place and displayed in PVSS.
Run control unit needs to be fixed to facilitate for different run types (LED system on/off)
- Trigger
One TRU cannot be programmed with new firmware if needed
Noisy triggers from TRUs
TOR tested together with DAQ
TIN server in place.
- HLT
Running with PHOS
Online display used for commissioning
- Plan for cosmic data.
When we are ready for running in global partition we will discuss our
trigger input.
TRU is probably not useful before the modules are cold
- People
Boris will come 1.Sep, Yuri will come to CERN 21.Sep.
Hisa will leave 31.Aug and Lijiao will leave on 5.Sep, Misha will leave in the beginning of Octorber.
Timur probably come next week.
27 Aug 2009 PHOS Commissioning Meeting
Minutes
- cooling
Water cooling leackage was fixed. Now running stably.
Humidity is ~10%, ~25%, ~30%.
- RCU
We have 11 DCS boards. One RCU+DCS is now out and is waiting for extention cable.
One RCU is missing jtag connection, needs test next Monday.
New firmware is under testing.
New Mapping was commited yesterday.
- FEE
As reporeted before, one branch is dead.
Another branch is missing connection probably week GTL connection, needs check next Monday.
Can't read version from 15 TRUs.
- DAQ
DAQ trouble, for example, one missing LDC. We probably can fix with expert's help on surface.
- DCS
More hadware&software interlock are visible in PVSS.
Different configurations are available.
Nice temperature and humidity panels are avalable.
- Trigger
TOR's DCS is missing connection and needs to be checked next Monday.
Kyrre and Dominik are working integration of the TOR in PVSS.
- HLT
Not much progress. Just need data.
- Plan for cosmic data.
Some discussions was on e-mail.
- Peoples
Boris will come 1.Sep, Yuri will come to CERN 21.Sep.
Hisa will leave 31.Aug and Lijiao will leave on 5.Sep, Misha will leave in the beginning of Octorber.
20 Aug 2009 PHOS Commissioning Meeting
Minutes
- Cooling
The humidity is decreasing constantly after the dried air (or nitrogen) started five days ago.
We probably need to wait for 3 weeks in order to fix water cooling leackage because of L3 magnet.
- DCS
Svain and Alexander has worked since last week and PVSS is close to what we need now.
DCS for LED system is running successfully.
New cooling panel in PVSS.
We need the state machine for FEE systems, which Timor can handle in the future.
- RCU
RCU firmware v3 is now working.
There happens a corraption of ALTRO data for both TPC and us, which experts are working for.
8 DCS boards needs to be reinitialized.
- FEE
New mapping are on trunk.
- DAQ
1.2kHz with busy box is promissing.
- HLT
Two triggers, high energy threshold trigger and mip trigger, are implemented, tested, and submitted by Svain.
- Trigger
TRU+TOR is going to L0.
L1 needs to be tested in the future by Lijiao and Yusuke.
- Plan for cosmic runs
Let's wait for cooling.
Need input how many days of cosmic runs is needed for calibration.
- Man-power at CERN
Timor is at Oslo now and will come to CERN soon but not next week.
Bernhard, Oystein, Svain, Lijiao, Sasha, Misha, Alexander, Yaping, Fumihiro, Yusuke, Hisa are at CERN now.
Svain will leave at the end of next week.
Fumihiro will leave this Saturday. Hisa will leave at the end of August.
Lijiao will leave on 5th/September.
Yuri and Boris has called in.
13 Aug 2009 PHOS Commissioning Meeting
Agenda
Minutes
- DCS
Svain and Alexander need to work together. Oystein will come to CERN and arrange the job.
- FEE
Mapping for DCS is not yet fixed.
New RCU firmware work. The sparse readout must be tested soon.
DAQ integration test is planned tomorrow, this Friday.
Trigger things need to be tested.
- DAQ
Need test high trigger DAQ next week.
- Cooling
Cooling pipes were disconnected for installation of PHOS#2&1
- Plan for cosmic runs.
We are ready. Need to discuss about shifts
- HLT
Creat a componenet of energy threshold trigger and will ask to implement the working one.
- PHOS#1&2
PHOS#1 was transferred to P2 and will be installed tomorrow.
PHOS#2 is being installed now!!! Let's hear more update from Sasha.
PHOS#1 at build167 had 2 bad FEEs and 1 bad branch.
- Peoples
Oystein will reach at the Geneve this afternnon.
Svain will be at CERN for 2-3 weeks depending on the update.
Yuusuke has just come to CERN and stay for 2 months.
Hiro will leave CERN on 22.08 and Hisa will leave on 31.08.
Yaping is at CERN.
6 Aug 2009 PHOS Commissioning Meeting
Agenda
Minutes
- DCS
Kyrre and Alexander need to communicate remotely what's done before.
- FEE
Mapping between DDL to DAQ are good, but the mapping for DCS is not yet fixed and will be fixed this afternoon by Svein.
New RCU firmware are not working for both PHOS and EMCAL.
Need update about the PHOS trigger.
DAQ integration is planed on Friday next week, and then trigger integration test will follow.
PHOS#1 has 32 bad channels including 2 suspicious T-cards and all TRU are working
- DAQ
Need test >200Hz with busy box. We could read 1.4kHz before.
- Cooling
Cannot start cooling down before at least mid-September.
- Plan for cosmic runs
Basically we are ready for cosmic runs. Need to discuss about shifts.
- HLT
Need proper mapping.
- PHOS#2 schedule
Will be installed after extra 5 days.
- Peoples Schedule
Timor will start for the database in three weeks.
Oystein will be absent from tomorrow for a week.
Dong and Lijiao has left CERN.
Kyrre will come to CERN 10.08 and Alexander will leave CERN on 13.08, so both have overlapp.
Yaping will continue the trigger works.
Hiro will leave CERN on 22.08 after PHOS#1 installation.
29 July 2009 PHOS Commissioning Meeting
Agenda
I propose that we follow Yuri's list for the discussion (with some additions):
1) DCS: a list of DCS integration tasks was presented in Serguei's talk at the last PHOS meeting, Kyrre was working on it in July, today the DCS experts from Sarov are expected to arrive to CERN. Tomorrow the DCS integration session should be held with PHOS in ACR. How far is PHOS from the full integration?
2) FEE: what is the status of the FEE configuration in detector configuration DB, and the procedures to load the configuration from it?
The RCU firmware v.3 should be tested and compared with similar data taken with the old RCU firmware. RCU trailer registers could be discussed and loaded to RCU. Shall we run with zero suppression by default?
The status of the mapping of the channels? Bad channel maps?
3) TRU: is it ready for MIP selection? Can it be already used for cosmic run with PHOS as a trigger detector? Does Dong et al. need any special LED runs to set TRU thresholds and active channel list?
4) DAQ: online monitoring in AMORE can be tested again, as soon as DAQ experts fix the problem with PHOS QA module.
5) ECS: are we happy with 2 standalone run types (PEDESTAL and LED), or any additional run types are needed? For example, does TRU need any dedicated run types? Besides, ECS should be equipped by a script to stop LED after the LED run, otherwise LED will continue flashing for the next runs.
6) Colling: when PHOS can be cooled down to -25 degrees? Will it be ready before the cosmic run which starts on 22 August?
7) Plans for cosmic runs: we definitely should participate in it, either worm or cold. One has to foresee the breaks between the physics runs to have LED runs (at least, once per day, but better every shift). We could discuss what is needed for the full-dress rehearsal of the data processing, starting from the start of run and finishing the raw data reconstruction and OCDB filling with the calibration parameters.
Minutes
See Indico page
As we agree, we continue the (definitely short) PHOS commissioning meeting every Thursday from 10am. Here is the minutes for today, 29.07.09
- DCS
The DCS integration test finished succesfully yesterday, on 28.07.
Some improvement is necessary, but our system passed their criteria.
Some issues; Specific LV-power-up procedure is necessary in PVSS. Central
message connection to ECS system is needed.
Presentation at DCS meeting this afternoon.
Kyrre is working at CERN. Alexander Mamonov has just arrived at CERN.
- FEE&RCU
The configuration data base basically exists
Some information must be transferred in OCDB, which is not in highest
priority.
RCU firmware v3 doesn't work, doesn't take any data from FEE properly. An
expert will come to help us.
Zero suppression mode is default for physics runs. During commissioning and
cosmic runs, we should take with/without zero suppression, someone should
compare them.
Some system (DA and online monitoring) needs zero suppression flag, zero
suppression offset and zero suppression threshold, Oystein tested zero
suppression info into RCU trailer. What we have in current RCU trailer; zero
suppression flag, total number of samples, number of readout samples,
sampling frequency. Dieter's comment; the zero suppression offset and
threshold must be fixed through all runs once we know the noise situation.
New channels mapping is coming for FEE, and is ready for TRU.
Timor is supposed to come to CERN for PHOS for finish the configuration
database.
- TRU
One PHOS trigger is already in the global trigger system.
We need test with LED flushing. The 2x4 LED channels is the minimum LED
unit.
TRU and TOR needs the feeserver upgrade.
Dong has left CERN and Lijiao will be leaving today.
Need man-power.
Timor plans to work for the feeserver.
- DAQ
We couldn't take >200Hz even with zero-suppression. DAQ provided 6 LDCs
instead of 3 LDCs, we will see the limitation tomorrow.
Once ECR people started AMORE, someone should test the online monitoring
again.
Need DAQ integration test after DCS PVSS implementation.
Need man-power.
- HLT
Clusterization and inputting into ESD is working 1kHz.
A PHD student, Svein Lindal, started to implement the trigger feature.
Online monitoring of QA is not yet connected to AMORE.
- ECS
Additional run modes in addition to LED and PEDESTAL runs is not needed.
PVSS should control on/off the LED system, so such a physics run with LED
flushing should not occur.
- Cooling
In phos meeting this afternoon.
- Plan for cosmic runs
PHOS is not declared as a part of global partition during global cosmic
runs.
We have to be part of global runs. What we need at first is to test in
standalone mode.
Let's discuss in phos meeting this afternoon and in e-mails. Oystein will
contact Jan.
- PHOS#2&1 at PHOS lab
Noise is surprisingly small. PHOS#2 is basically ready for installation.
Yaping and Fumihiro will take electrical test for PHOS#2.
PHOS commissioning in 2007
27 Nov 2007 / J. Alme / Electronics / DCS and Actel firmware upgrade
The upgrade of the DCS board firmware to v2.8 and Actel fw to v1.4 went without problems yesterday on RCUs of the 1st PHOS module. The reason for the upgrade is bug that makes the RCU Xilinx be reprogrammed from the RCU Flash whenever the DCS board reboots. More details concerning the new versions can be found at the Bergen ALICE Wiki. Note that a script (S31_setOldMode) in /etc/boot/ has been added to make the DCS firmware backwards compatible with the current RCU Xilinx firmware. This script must be removed when the new RCU firmware is ready.
22 Nov 2007 / B. Skaali / Electronics / GTL strips
Tests on a revised GTL strip will start in beginning of December in Oslo. The exact date can not be given today due to high work load together with illness at the Electronics Lab.