Start a run from DCA
Instructions for DAQ shifter
pdf-file
--
PetraRiedler - 07 Mar 2008
Start LTU panel on alidcscom026
Temporary instructions on re-starting a run in case of DAQ failure for the cosmic coincidence run (28/05/2008)
Procedure to follow to stop and re-start a data acquisition run while running in local mode.
If the detector DCS status stays
READY
one needs to restart the run after resetting the front end readout electronics:
- Stop the CTP emulator from the CTP emulator panel, click
Quit emulation
- CTP emulator window is opened from the ltu client (Trigger control) window
- Stop the data acquisition (if not already stopped by itself) by clicking on
Stop
in the DAQ - Run Control window
- Reset the readout electronics
- In the Detector Control system right click on
spdFEE electronics
in the hierarchy on the left side
- Click on
Autoconfig Routers
- Click on
Reset DPI for all
- Reset the DPM for each router
- Go back to the LTU control panel, click on configuration and select
ttcFEEreset
- Start again the data acquisition run in the DAQ - Run Control
- Click
Start processes
, wait for LDCs states to reach RUNNING and then click the Start
button
- Start the CTP emulation on the CTP emulator control by clicking on
Start emulation
--
GianlucaAglieriRinella - 27 May 2008