Minutes BWS Upgrade: Electro-Mechanical Design Meeting #17 -- 28th November 2016 --

Participants: R. Veness, F. Roncarolo, J. Emery, P. Andersson, D. Gudkov, W. Andreazza, J.L. Sirvent, C. Vulliez, A.Goldblatt

Agenda (https://indico.cern.ch/event/569142/)

1. Potential issues for EYETS installation

1.1 Glass Encoder Disk: Situation and options (Dmitry & Jose)
  • Delay on Encoder Disk due to bad adherence of chrome on glass (raw material send to provider)
  • Disks need to be re-coated ( potential schedule risks if they have more problems...)
  • Disk must be ready 5th Dec.
  • Ideal needs for testing disks prior to installation:
    • 1. Mount on holder and optical bench for a quick functional validation
    • 2. Clean disks before mounting on PSB Prototype
    • 3. Mount disk on prototype and single scanns for alignment and test.
    • 4. Ideal would be to perform calibration with laser system (possible?).
  • Same disk for all operations or parallel work? : Validation on bench and on PSB Proto must be same disk.
  • Metallic disk situation:
    • Sent without the diamond turning (in error). They will do this week.
    • Probably we will not get engraved disks this year (1-2 weeks to get engraved in NL)
    • If received W48 must be ready W50
1.2 Bearings (Dmitry)
  • Current installed bearings have heduced clearance (very hard to move, friction) this one was accepted by Vacuum.
  • Standard bearings (SPS type) are now at CERN, but need to be tested.
  • Need 0.4-0.5 Nm to rotate curent bearings. Thinks it will be better but not necesarily zero.
  • Agreed (William/Dmitry) to install on the ML instrument.
  • Bearings performance compared by Jonathan on other test-bench
  • Check precission on standard clearance bearings. (need calibration bench for this?)
  • New bearings need to be cleaned and send for vacuum acceptance (William). Potential schedule risk.
1.3 Vacuum Acceptance (William)
  • 2 measurements done of the whole instrument (Bad results)
  • Opened and re-assembled
  • VSC Think there is an issue of cleaning with is interfering with the measurement.
  • Not 3rd cleaning and will re-measure
  • Cleaning service changed products?
  • Tank was fully accepted by VSC and can be installed
  • Macor connector was accpeted in the SPS
    • Ray will talk to Giuseppe/Jose?
    • In theory, it will not stop installation.
    • We may have to add a pump.
  • Wire qualification:
    • Request made by Jonathan
    • William will help on follow-up.

1.4 Callibration (Jonathan/Federico/Aurelie/Jean)
  • Infrastructure is ready (stages and scopes acquisitions)
  • Control system is not ready for calibrations (Jonathan)
    • Other possibility using other system ? (Federico)
    • In theory yes, quick (but not optimal) solution with DSpace system displacement to 867, required modifications for triggering system. (Jonathan)
    • 1 month of work required for needed modifications and controller paramaters extraction.
  • We'll like to put the scanner on calibration bench prior to installation on PSB and perform a first calibration.
  • A big amount of time required for such work. Potential blocking point.

1.5 Cable installation (Federico/Jonathan)
  • Normally we should make some test scans as soon as we install. (Federico)
  • Approval for cabling is agreed but date is not known . (William will check)
  • Jonahtan has installed 3 racks, but they have not planed to install power and network on the racks.
    • Done 2 weeks ago, some checks are still needed for the installations. Aurelie will help here .
1.6 Any others?
  • No announcements done here.
  • Latest date for installation in PSB will be ~10th Feb.

2. Initial budget estimates

  • Federico will send Excelsheet with cost for acquisition and control electronics. (Jonathan's excelsheet)

3. Agreements

  • Installation of tank and support (but not instrument) on the 15th December
  • Installation of the instrument 10th February.
    • Hope to be able to calibrate and operate in the tunnel.
    • If we have a complete working instrument that has been tested on the bench then we will install it.

4. Detected installation blocking points:

  • Test with new bearings
    • Dmitry to send a mail when the scanner is assembled with new bearings.
    • Jonathan to communicate wen it has been tested.
    • William to update us on vacuum acceptance test of bearings.
  • Glass encoder disc.
    • Jose Send mail when disk arrives - Check if possible to collect it
    • Jose will make normal acceptance test and let know the results.
    • Also some testing will be done to test the disk mechanical resistance (some cycles)
  • Vacuum acceptance:
    • William will let know when the hole instrument is accepted for installation.
  • Defined priorities for Jonathan are:
    • test the bearings
    • prepare d-space system
    • racks and system (first check the installation dates). Aurelie has offered to help here.
Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2016-11-29 - unknown
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    BWSUpgrade All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2022 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback