Number |
Title |
Due date |
Description |
Status |
MJRA1.1 |
Middleware support web page |
May 2008 |
Deploy a web site with the relevant information needed by middleware users (including other project activities). It should include links to support contacts to be kept up to date during the life of the project. |
|
MJRA1.2 |
Activity Quality Assurance and measurement plan |
June 2008 |
Definition of the activity-internal QA measurements and procedures. This will provide input to DNA1.2 |
|
MJRA1.3.1 |
Functional Description of Grid Components and associated Work Plan |
July 2008 |
Functional description of services reengineered by JRA1 in response to TMB requirements including initial design and associated work plans. A live version of the work plans will be maintained on the Middleware web page |
|
MJRA1.4 |
gLite Security Architecture |
August 2008 |
Overall (global) security architecture of the gLite middleware. This document will summarize the current situation and describe the foreseen evolution during the lifetime of the project |
|
MJRA1.3.2 |
Update of Functional Description of Grid Components and associated Work Plan |
March 2009 |
Update of Grid Components functional description and associated Work plan |
|
MJRA1.5 |
Establish the gLite Open Collaboration |
October 2009 |
Establish a legal entity for the gLite Collaboration. |
|
MJRA1.6 |
gLite Open Collaboration website |
October 2009 |
Establish gLite Collaboration a website (www.glite.org?) referencing the partners within the consortium and the work of the consortium. The list of components in the consortium may diverge from those on the production infrastructure - the current definition of gLite. |
|