Project Milestones

Message Brokers

  • September 2008
    • Single broker set up DONE prod-grid-msg.cern.ch
  • January 09
    • Network of brokers running DONE CERN/SRCE
      • COMMENT:: Some problems in getting good operations preocedures for network of brokers (e.g. restarts, config upgrades, removing problem brokers). Waiting on adding more until we have more experience. Target: June for 2 more brokers (INFN, AUTH ???)

NCG

  • December 2008
    • GOCDB integration via Oracle DB – DONE
    • Integrated via XML interface to GOCDB – DONE Mid January 2009
    • Yaim modules for ROC level – DONE at start
    • Specific doc for a ROC – DONE at start
    • Full integration with MSG - DONE Mid January 2009
    • MSG → Nagios – DONE Mid January
  • February 2009
    • feedback link from ROC to Site Nagios – DONE
      • PENDING - end may ?
    • Support for multiple VOs – DONE
  • March 2009
    • Integration with JSON-based metric database – DONE
  • April 2009
    • Integration with Metric Store (DONE) and new Topology Providers - no interface yet - still open
  • May 2009
    • Implementation of NCG cache (NCG as Nagios check)

Regional Monitoring

  • December 08
    • SAM ready to use Message Bus - DONE
      • SAM client on UI and WNs uses msg-publisher
      • Msg-consume2oracle used to retrieve messages from a topic and insert in SAM DB
      • Everything tested in Validation
    • Have Nagios equivalents of current SAM sensors used for WLCG/EGEE Availability calculations –
      • SRMv2; CE & CREAM CE; sBDII
      • NCG templates available
        • Dec - SRMv2, CE DONE. sBDII waiting on gstat developer
        • COMMENT: April - Site BDII tests are now ok. WN tests (CE) are now ok
  • January 09
    • Test at CERN a full nagios monitoring system –
      • Pushed back to Feb due to delay in hardware request
      • (April 09) - 11 machines now setup
  • April 09
    • Design of new SAM portal completed –
      • Feb - UNDER CONSIDERATION
      • April - Decision to try and use MyOSG as the DB against nagios data
    • Integration with new availability calculation at same level as current system
      • Pending on Gridview -
  • June 09
    • Switch Regional Nagios metric publication to new metric store
    • Inegrated with Regionalized Dashboard alarm system
    • Adapt submission framework to use new aggregate topology provider
    • SAM portal layered on new metric store
    • 3rd party tool selected/customized for viewing NDO database

Project level repositories

  • April 2009
    • 1st implementation of Metric store, aggregate topology provider and Metric Description Database
      • ATP -
        • 23 April - syncronizers nearly done. DB Schema done, history tables to be done
        • 7 May - syncronizers finished this week. Need to know the information that NCG will need.
      • MDDB - first version ready, integrated with NCG
      • Metric Store - early vrsion based on NDOUtils - under revision - may change schema.
  • October 09
    • Aggregate topology provider packaged for easy deployment in regions

  • December 09
    • Regional version of metric store available to function along with regional availability calculator

SLA Calculation

  • March 2009
    • Test new metrics with old availability algortiihm (in old SAM SB)
      • April - PENDING
  • June 2009
    • single availability algorithm calculated per VO with new metric store (e.g. functional equiv. of current system)
  • August 2009
    • multiple availability calculations
    • Visualisation of Availability in web portal * December 2009
    • Regional version of availability calculation available

GOCDB

More details (including tasks dependencies) are available from https://wiki.egi.eu/wiki/GOCDB

  • Feb 09
    • GOCDB-PI is available in a prototype state with certificate based authentication. DONE
    • A first test DB model is deployed DONE
    • Basic set of information to be contained in GOCDB-4 is defined DONE
    • First "region1" regional use case is defined. DONE

  • Mar 09
    • GOCDB-PI read functions are in production. DONE
    • GOCDB-4 schema designed and deployed for testing purposes DONE

  • April 09
    • A first API is implemented to interface new DB model. DONE
    • Data sets injected into new schema for test and validation. DONE

  • May 09
    • First set of write function available in GOCDB-PI. DONE

  • June 09
    • Basic APIs are available for tool developers that need to migrate to GOCDB-PI. DONE
    • A basic web interface is available in a prototype state to centrally access GOCDB new model. DONE
    • We have a "region1" use case deployed DONE

  • Aug 09
    • A simple "GOCDB regional instance" test module is available for the regions that want to try it. DONE
    • GOCDB interactions with messaging system defined. DONE

  • Sept 09
    • Scripts for large scale data migration from GOCDB3 to GOCDB4 are ready. DONE
    • interfaces to "region3" model are defined. DONE

  • Oct 09
    • Access to GOCDB is only done through GOCDB-PI. DONE

  • Nov 09
    • GOCDB4 central read-only web portal in beta version along with GOCDB3. DONE
    • GOCDB-PI is ready to access GOCDB4 data. DONE

  • Dec 09
    • GOCDB4 central read/write portal in beta version. DONE
    • Beta regional package officially distributed through standard channels. DONE
    • GOCDB-PI production system accesses GOCDB4. DONE
    • Plans for GOCDB integration with messaging system finalized.

  • Jan 10
    • GOCDB3 deprecated - GOCDB4 is the only production system
    • SOAP interface implemented.
    • Regional instances and central instance work in parallel in a prototype state

  • Feb 10
    • Production quality regional package officially distributed through standard channels

  • Mar 10
    • First regional usecases deployed as test/pilots enter production

Gstat

  • March 09
    • Finish software requirements analysis and design - Done
    • Finish prototyping new model - Done
    • Regional use-cases Study - In progress
  • September 09
    • GStat core components deployment ready.
      • GLUE and Topology models with associated import scripts
      • GStat validation scrips ready and initial feedback from deployment
      • GStat BDII monitoring probes ready and initial feedback from deployment
    • Prototype portal pages ready.
    • Start to investigate the migration plan and preparing for software transition
  • December 09
    • GStat version 2.0 in production
    • Work well underway on enhancements.

Regional Dashboard

  • July 09
    • Regionalized dashboard interfaced with Regional Nagios raising alarms based on Nagios
  • Jan 10
    • Regional dashboard based on a Regional Nagios suitable for deployment at a region

Quality Metrics Portal

  • Sep 09
    • Initial version of portal (infrastructure, common functionality ) - DONE - based on CESGA accounting portal
    • usage.1, usage.4, size.1 - DONE - based on GOCDB-PI
  • Nov 09
    • operations.3, user-support.1, user-support.2 - In progress
  • Nov 09
    • user-support.{345} - In progress
  • Dec 09
    • operations.4
  • Jan 10
    • operations.{12}, size.2

Accounting

  • March 09
    • Create Central infrastructure for ActiveMQ
      • Install a message broker - DONE
      • Install an Accounting Archiver (consumer) - DONE
  • April 09
    • Publisher written - DONE
  • July 09
    • Distribute an APEL publisher that uses ActiveMQ as the transport mechanism
  • April 09
    • Implement the APEL publisher
    • Create new APEL package
  • June 09
    • Test version in different sites in parallel with R-GMA
    • Submit patch for g-Lite certification
    • Gather requirements/information from existing interfaces (OSG, NDGF and DGAS) configurable for different regions/sensors
  • July 09
    • Implement APEL publisher configurable for different regions/sensors
  • August 09
    • Implement consumer configurable for different regions/sensors
  • October 09
    • Package publisher configurable for different regions/sensors for distribution
  • December 09
    • Test publisher with other regions
  • April 10
    • Create a package for the regionalised Accounting Servers ready for distribution

Accounting Portal

  • September 2009
    • Detailed CSV in global View. -*DONE in develop portal*

  • October 2009
    • Migration to new GOCDB-PI interface.
    • Create a new branch to support EELA project. - DONE in development portal
    • Create a chart for each country to show the percentage of jobs runned by foreign people.
    • Create a chart with the percentage of sites that publish their DN.

  • November 2009
    • Add user DN tree.
    • Clean Global view.
    • Create report with contributed CPU.
    • Show installed capacity and resource usage by VO's at sites.

  • December 2009
    • Remove unregistered sitenames like '%test%'.
    • Show RB related information.

  • February 2010
    • Regionalize the EGEE accounting portal.

  • Pending Date
    • Show HEP Spec related data.

Projects with no milestones attached

Operations Portal

SAMAP

Worker Node configuration (JobWrapper tests)

Site Nagios

Middleware event publication (L&B, FTS, Gridftp log parsing)

Edit | Attach | Watch | Print version | History: r27 < r26 < r25 < r24 < r23 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r27 - 2011-06-20 - AndresAeschlimann
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    EGEE All webs login

This site is powered by the TWiki collaboration platform Powered by Perl This site is powered by the TWiki collaboration platformCopyright &© by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Ask a support question or Send feedback