This main purpose of this action plan is to define the actions the timelines and the responsible ROCs/people so that the EGEE SLA/SLAs is defined by the end of the year 2007. A first draft of the SLA should be ready by the end of summer, thus beginning of September.

The action plan should be finalized and discussed in the ROC managers meeting on the 10th of July.

The identified tasks for the preparation of the SLD are:

T1. Define initial Table of Contents

T2. Define a basic set of Metrics

T3. Discuss with MIG about the feasibility of metrics implementation and if the metric produced by MIG are consistent with the SLD metrics.

T4. Decide on the existence of one or more SLDs

T5. Draft text for the contents of the SLD.

T6. Iterate and discuss the contents of the SLD.

T7. Prepare the first draft before by the end of summer.

T8. Produce some initial reports based in the SLD metrics and the metrics produced by MIG to estimate the conformance of the SLA by sites.

T9. Iterate and discuss the SLD.

T10. Finalize draft.

In order to have a draft SLD by the end of summer T1 to T6 should be done by end of August 2007.

Timeline:

T1: by 17th of July

T2: by 24th of July

T3: by 24th of July

T4: from 24th of July to 6thth of August

T5-T6: by 7th of September

Note that August is a month that most of people are on holidays for an extended period of time.

Code Description Start Date End Date Responsible
T1 Define initial Table of Contents 17 Jul 2007
T2 Define a basic set of Metrics 24 July 2007
T3 Discuss with MIG about the feasibility of metrics implementation and if the metric produced by MIG are consistent with the SLD metrics 24 July 2007
T4 Decide on the existence of one or more SLDs 24 July 2007 06 Aug 2007
T5 Draft text for the contents of the SLD 7 Aug 2007
T6 Iterate and discuss the contents of the SLD Aug 07
T7 Prepare the first draft before by the end of summer 7 Sep 07
T8 Produce some initial reports based in the SLD metrics and the metrics produced by MIG to estimate the conformance of the SLD by sites Autumn 2007
T9 Iterate and discuss the SLD Autumn 2007
T10 Finalize draft Autumn 2007
Edit | Attach | Watch | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r4 - 2007-07-10 - unknown
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    EGEE All webs login

This site is powered by the TWiki collaboration platform Powered by Perl This site is powered by the TWiki collaboration platformCopyright &© by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Ask a support question or Send feedback