DJRA1.2.2 – Data Area Work Plan and Status Report (M12)

Data Area Work Plan and Status Report: This deliverable contains the detailed work plan of the Data Services technical area compliant with the overall EMI Technical Development Plan. The plan is released early in the project life and updated every year including a status report on the achievements of the past 12 months compared to the planned objectives. The status report at M03 will cover the state-of-the art while the work plan at M36 will provide recommendations for further work. (M12)

This deliverable is an update of DJRA1.2.2 (M3)

Schedule

  • Author sends ToC to PEB 08-Apr
  • Author sends high quality complete WP-leader approved first draft of deliverable for review 18-May
  • Reviewers send comments on first draft 22-May
  • Author sends second draft for reviewers' acceptance 24-May
  • Reviewers acceptance of second draft or critical comments that must be addressed in the final draft 26-May
  • Author sends final draft to PO 27-May

JRA1 internal

  • Proposed TOC Revision 0.1
  • Patrick will upload TOC in the afternoon of 2011-04-08
  • Patrick uploaded TOC at 11:30
  • Second revision of TOC available. The GUNTT chart it not yet finished. It will look very similiar to that one.
  • May 18 10:00 Section 3 (Work in in EMI-1) ready for review.
  • May 22 9:00 Secion 4 ready for review: Missing : 'executive summary' and the responce to Marias review'
  • May 23, 17:30 V6 including Maria's suggestions.
  • May 29 : Version 0.8
    • Included Marias review suggestions on section 4 and created Marias review track page
    • Double checked against DNA 1.3.2
      • Objective phrasing unified between both.
      • One objective was missing in DJRA 1.2.2, fixed. (DNA1.3.2-X1)
      • One objective missing in DNA1.3.2. (DJRA1.2.2-9.0). Informed Balazs.
      • One objective phrasing has to be slightly changed in DNA1.3.2-D16. Informed Balazs.
      • Executive summary still missing.
  • May 31 : Version 0.9: References moved from 5.0 to 1.5 as requested by Jedrzej.

Review Tracking

  • 08/04/11 ToC available for review
  • 15/04/11 ToC sent to reviewers for comments; deadline 19/04
  • 18/05/11 Chapter 3 sent to reviewers for early feedback; deadline 19/05
  • 19/05/11 Maria's comments to Chapter 3.
  • 23/05/11 Chapter 4 sent to reviewers for early feedback; deadline 24/05
  • 24/05/11 Maria's comments to Chapter 4.
  • 24/05/11 M. Alandes has accepted v0.6 which has addressed her Chapter 3 comments
  • Reminder sent to A. Taga, comments by COB 25/05 if any
  • 26/05/11 A. Taga review comments received

Reviewers

GANTT Work

Topic attachments
I Attachment History Action Size Date Who CommentSorted ascending
PDFpdf 2011-05-31_DJRA122_v0_8_GANTT.pdf r1 manage 227.1 K 2011-05-31 - 12:53 MorrisRiedelExCern Final GANTT diagram in-line with deliverable DJRA1.2.2 version 0.8 from Patrick
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.6.docx r1 manage 351.8 K 2011-05-24 - 01:18 PatrickFuhrmann Fixes recommended by Marias review.
PDFpdf 2011-05-17_DJRA122_v0_0.pdf r1 manage 241.5 K 2011-05-17 - 17:26 MorrisRiedelExCern Initial GANTT diagram with information got via e-mail from Patrick on 2011-05-15
Microsoft Word filedoc EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.1.doc r1 manage 184.5 K 2011-04-08 - 18:21 MorrisRiedelExCern  
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.8.docx r1 manage 363.6 K 2011-05-29 - 11:57 PatrickFuhrmann  
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.2-toc.docx r1 manage 78.2 K 2011-05-16 - 12:45 PatrickFuhrmann Reviews ToC (May 16)
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.5.docx r1 manage 341.0 K 2011-05-22 - 15:51 PatrickFuhrmann Sec 3 and 4
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.2-section3only_ataga.docx r1 manage 113.2 K 2011-05-26 - 06:38 AdrianTaga Section 3 comments
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.2-section3only_maria.docx r2 r1 manage 113.7 K 2011-05-19 - 18:19 MariaALANDESPRADILLO Section 3 comments
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.6_ataga.docx r1 manage 351.8 K 2011-05-26 - 06:40 AdrianTaga Section 4 comments
Unknown file formatdocx EMI-DJRA1.2.2-0000000-Data_Area_Work_Plan_v0.5_maria.docx r1 manage 355.0 K 2011-05-24 - 13:45 MariaALANDESPRADILLO Section 4 comments.
Unknown file formatxlsx final-objective-table-v3.xlsx r1 manage 81.7 K 2011-05-19 - 15:21 PatrickFuhrmann Simple GUNTT chart (used in the deliverable)
Edit | Attach | Watch | Print version | History: r39 | r30 < r29 < r28 < r27 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r28 - 2011-05-31 - MorrisRiedelExCern
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    EMI All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2023 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback