DJRA1.6.1 - Integration Work Plan and Status Report

Due Date

03 July 2010

JRA1 Internal Process

Review tracking

  • 18/10/10 - M. Riedel informs PO v4 ready for review: (DOC)(PDF)
  • 18/10/10 - v4 sent to F. Giacomini, A. Aimar, B. Konya and PEB for review; deadline 26/10
  • 27/10/10 - Reminder sent to reviewers
  • 27/10/10 - A. Aimar, M. Alandes Pradillo, J. Cernak (SA2) sent review
  • 29/10/10 - B. Konya sent review
  • Waiting for revised version from authors; SA1 will review revised version
  • Revised version expected 19/11
  • 22/11/10 - M. Riedel sent v5
  • Massimo as reviewer dropped due to major revision anyway for Balazs and Maria
  • 24/11/10 SA2 highlighted issues to be addressed before a new version is release; see SA2 review page
  • 26/11/10 - M. Sgaravatto/SA1 will review revised version
  • 28/11/10 - A. Di Meglio sent revised structure of DJRA161 (DOC)
  • Revised DJRA161 following template expected 17/12
  • Following request from author, revised document expected 20/12
  • 03/01/11 - v0.5 received from A. Giesler
  • 06/01/11 - v0.5 sent to M. Sgaravatto (SA1), A. Aimar, M.Alandes Pradillo, J.Cernak (SA2), B. Konya and PEB for review; deadline 14/01
  • 11/01/11 - Pending clarification on how v5 review comments have been addressed in v0.5.
  • 12/01/11 - A. Giesler has updated reviewers' wikis; B. Konya review expected 19/01; M Sgaravatto review expected18/01
  • 18/01/11 - M. Sgaravatto sent review
  • 27/01/11 - J. Cernak sent review; B Konya expected 28/01
  • 28/01/11 - B. Konya sent review
  • Updated DJRA161 incorporating SA1, SA2 and TD comments expected 04/02
  • Extension request from A. Giesler: I'll update the document regarding the reviewer's comments. However, because of a project meeting at Milan from the 1st to the 4th of February I'm very likely not able to complete it this week by 04/02. So, I'd like to ask you to extend the deadline to the 08/02.
  • 08/02/11 - A. Giesler sent v1.0 taking into account reviewers comments
  • Pending reviewers' acceptance of v1.0 due 15/02
  • 09/02/11 - B. Konya: I am not fully satisfied, however taking into account the difficult circumstances around the integration task and appreciating all the effort Andre invested into this deliverable i approve the latest version.

Reviewers

Topic attachments
I Attachment History Action Size Date Who Comment
Microsoft Word filedoc EMI_Integration_Plan-v0.1.doc r1 manage 149.0 K 2010-11-29 - 09:37 UnknownUser revised DJRA161 structure from ADM
Microsoft Word filedoc EMI_Integration_Plan-v0.5.doc r1 manage 1088.0 K 2011-01-06 - 14:42 UnknownUser v0.5 for review
PDFpdf EMI_Integration_Plan-v0.5.pdf r1 manage 2496.5 K 2011-01-27 - 11:23 UnknownUser v0.5 pdf for review
Microsoft Word filedoc EMI_Integration_Plan-v1.0.doc r1 manage 1093.5 K 2011-02-10 - 18:20 UnknownUser v1.0 for reviewers' approval
Edit | Attach | Watch | Print version | History: r36 | r34 < r33 < r32 < r31 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r32 - 2011-02-10 - unknown
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    EMI All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2021 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback