MJRA1.17 -Test suites of compliance checks in place
This milestone indicates the existence of testsuites for standard compliance checks that can be actually used by the quality control task.
Standard compliance test suites tracked
here.
Milestone Tracking
- 28/10/11 JKN: The plan is the following:
- Define the available test suits (jra1 survey will be finished today)
- Define development tasks for the missing standards test suites (at PTB level)
- The milestone will be updated and will contain the 6-7 available test suites and links to the tracked, to-be-developed test suites
So in the end, we expect this milestone to be finished by 11 November.
- 11/11/11 JKN: Sent report to PEB for review
- 11/11/11 ADM: The milestone is called “Standards Testsuite in Place”. Currently the situation is that there are couple of available but hardly used testsuites, some documentation about work in progress in some standardization body and a list of testsuites to be developed before EMI 3, which very likely will not be developed 5we cannot even develop the functionality, go figure whether the testsuites will be developed). In addition I cannot judge whether the planned testsuites cover all needs or not, for example I see EMI-ES JSDL mentioned, is that the JSDL part only? What about the EMI-ES itself? I know the situation is not easy to handle, but I don’t think we can say the milestone has been reached. I would suggest to state that after having assessed the situation, we consider the milestone unreachable until probably (hopefully) PM 30 or so rather than trying to stretch the definition of the deliverable to close it now at all costs.
- 12/10/12 JKN: Unfortunately no new test suits have yet been finalized and there have been no efforts available so far. It would be nice to have test suites at least for CAR, StAR, delegation, EMI-ES and Glue2 but we need to find someone to write them. There will be a dedicated session on standard compliance test suites in the Budapest AHM
and hopefully we can find someone to write the needed tests there. If so, the tests will be in place earliest by end of November with milestone delivery by December.
- 23/01/13 JKN: New testsuites available for CAR, StAR and EMI ES. Only waiting for link to the implementation of EMI ES delegation port type before milestone can be considered reached.
- 29/01/13 JKN: All planned test suite implementations finished. Attached version 1.1 of report.
Documents
version 1.1
Review tracking
PEB Review comments
--
AleksandrKonstantinov - 13-Jul-2011