PriorityBug: Savannah Statistics Example

For this example we want to see what the average time to close a critical bug was between 1/1/2009 and 10/9/2010 in gLite. AverageTimeToFixABug.png
The value of average time greater than 100 days for a critical bug is totally unacceptable.
To ascertain the cause of these huge delays in bug fixing, we need to look at these results in conjunction with BugSeverityDistribution

-- EamonnKenny - 09-Sep-2010


This topic: EMI > WebHome > EmiProjectStructure > SA2 > EmiSa2MetricsGenerationGuidelines > EmiSa2MetricsGuidelines > PriorityBug