Status | Last changed | Responsible | Item | Description |
---|---|---|---|---|
In Work | Gutleber/Watson P.Saiz G. Simonetti for computing T. Otto for safety | Site platform and landscaping | Access building at the entrance of the of the site, can be integrated with other buildings. Medical First-aid room in or close to access building. 8 m x 5 m x 2.5 m 50 m2 Control Room for the accelerator, including technical consoles and equipment. 100 m2 - 200 m2 footprint. Up to 800 m2 total floor space if used as multi-functional building. - Modifications required for HH configuration: | |
Accesses to the site | - Modifications required for HH configuration: | |||
To be studied | 22/10/2021 | C Colloca | Roads |
General access for construction phase and for goods:
|
In Work | Gutleber/Watson | Parking areas | Staff parking: 50 cars peak occupancy. Car and bike parkings can be distributed over the site. Should be permeable, not sealing the ground. Visitor parking: 2 buses space, Can serve also as a shared parking of multiple cars. Can be offsite. - Modifications required for HH configuration: | |
To be studied | 24/01/2022 | C Colloca, R. Rinaldesi T. Otto for safety | Storage and unloading areas | Pavement with heavy load transport means capacity: 25 m x 40 m. Equipment for underground handling: 10 m x 12 m x 10 m. Safety / Heliport: At perimeter boundary of site, with free access by air. 15 m x 15 m concrete slab. Needs to be checked with civil aircraft regulations or with REGA - Modifications required for HH configuration: |
In Work | Fences | Fence around the site must protect the installations, but must be permeable for small animals due to the ecological corridor constraint. - Modifications required for HH configuration: | ||
Footpaths | - Modifications required for HH configuration: | |||
Technical galleries | - Modifications required for HH configuration: | |||
Portable water network | - Modifications required for HH configuration: | |||
Sewage network | - Modifications required for HH configuration: | |||
Industrail watewater netrwork | - Modifications required for HH configuration: | |||
Rainwater network | - Modifications required for HH configuration: | |||
Earthing grid | - Modifications required for HH configuration: |
Items | Electricity and Energy Management | Cooling and Ventilation | Safety | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Builnding Name | SF | SUM | SU | ||||||||||||||
Function | Electrical substation area | Energy storage | Power transformer | Double busbar system | Primary water pumping station | Cooling plant (baseline with evaporation towers) | Chilled and mixed water production station | Demineralised water production | Water filtering plant | Evaporation tower reject water treatment | Water intake pumping station | Retention basin | Tunnel ventilation | Ventilation station for service areas | Radiological clearance centre for measuring equipment | Buffer zone(s) for equipment transit from radiation areas | Central storage for radioactive objects shared by all equipment groups |
Status | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | To be studied | Stable | Stable | Stable |
Last changed | 27/04/2022 | 27/04/2022 | 27/04/2022 | 27/04/2022 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 10/11/2021 | 01/03/2022 | 01/03/2022 | 01/03/2022 |
Responsible | J-P Burnet | J-P Burnet | J-P Burnet | J-P Burnet | G Peon | G Peon | G Peon | G Peon | G Peon | G Peon | G Peon | G Peon | G Peon | G Peon | T Otto | T Otto | T Otto |
Design Life | |||||||||||||||||
Interfacing Systems | Building integrated with cooling tower construction | ||||||||||||||||
Interfacing Building / Civil Structures | Power quality : New SVC / harmonics filters 600m2 New SE building 400 m2 New diesel generators and tank 400 m2 Secure network building, emergency power / UPS 400 m2 |
As close to shaft and ventilation building as possible | As close to shaft as possible | Close to or integrated with pumping station building | Building close to demineralised water production | Close to de-mineralised water production | Close to service cavern access shaft | Close to chilled water production | |||||||||
FCC-ee Dimensions (W x L x H) | 40 m x 100 m | 40 m x 25 m | 20 m x 30 m | 20 m x 30 m | 7 m x 14 m x 10 m | 7 m x 14 m x 10 m | 20 m x 15 m x 15 m | 10 m x 20 m x 5 m | 14 m x 7 m x 5 m | 30 m x 20 m x 15 m (2 levels, to be checked) | 20 m x 15 m x 15 m (2 levels, to be checked) | 5 m x 20 m x 2 m | 2.5 m x 4 m x 2 m | ||||
FCC-hh Dimensions (W x L x H) or modifications required for hh configuration |
space for FCC-hh doubles | 20 % more space reqired for FCC-hh | |||||||||||||||
Specific loading (i.e. outside norms) | Floor loads: Internal wall loads: External wall loads: Crane loads: Roof loads: Other loads: |
||||||||||||||||
Structural requirements | Air insulated on surface. Avoid paved ground where possible. | Fenced with option for shielding walls (concrete) | |||||||||||||||
Thermal insulation requirements | |||||||||||||||||
Acoustic requirements | |||||||||||||||||
Shielding requirements | |||||||||||||||||
Fire protection requirements | |||||||||||||||||
Sanitary water drainage requirements | |||||||||||||||||
Industrial water drainage requirements | |||||||||||||||||
Rainwater drainage requirements | |||||||||||||||||
Occupational Health and Safety requirements | |||||||||||||||||
Hazardous material use or storage requirements | |||||||||||||||||
Access requirements | |||||||||||||||||
Architectural requirements (external and internal) | |||||||||||||||||
Operationnal requirements | |||||||||||||||||
Maintenance requirements | |||||||||||||||||
Decommissioning requirements | |||||||||||||||||
Applicable codes and standards |