60A converter tests - Tuesday 5th Dec.

60A tests advancements

Advancement of today:

  • AB-PO performed its tests on C24-26-28-30-32_L8
  • Polarity tests on C22-24_L8
  • TS-MME activities on C12-14_L8
  • AT-MEL activities on cells C12-14L8
  • Positioning of the Cable in sector 7-8 finished at 11:30.

Tomorrow activities:

  • AB-PO activities on cells C34_L8 - C34-32-30-28_R7 no problems for co activities.
  • TS-MME activities on C18-20-22-24-26_L8 no problems for co activities
  • Polarity tests on C28-34_L8 no problems for co activities.