TWiki home Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Minutes

Back to overview

YOU ARE VIEWING BlogEntryPoint2x2007x05x04x19x14

Short Circuit Test in UA27- Schedule:

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA - 11-05-07
8h run 4-8kA - 29-05-07
Interlock tests RQD&F - 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests ON GOING 03-05-07
600ANOEE powering tests - 08-05-07
600A-EE interlock tests ON GOING 03-05-07
600A-EE powering tests - 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-05-04 - BorisBellesia
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login