RAT_20070509.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x09x10x31/RAT_20070509.pdf
Energy Extraction 600A; Individual Tests are completed. 3 minor problems found (on 16 systems and not 48 as mentionned). Interlock and powering tests completed. Currently installation of temperature- and voltage-probes is on-going. Expected to be completed on May 9. Gert Coelingh
-- Main.BorisBellesia - 09 May 2007