Note that next 16th May, there will not be powering tests and the PIC interface tests will take place as well as an intervention of the geometers in the UA27 along the day.
Note as well that next 18th a WiFi intervention will take place in the morning. During this intervention a lost of the signal is foreseen during about 15 minutes.
|
|
|
13kA EE |
DONE |
16-04-07 |
600A EE |
DONE |
23-04-07 |
|
|
|
Circuits >2kA |
|
|
Powering tests PC 4-8kA |
ON GOING |
09-05-07 |
8h run 4-8kA |
- |
24-05-07 |
Interlock tests RQD&F |
- |
16-05-07 |
Powering tests RQD&F |
- |
23-05-07 |
Preparation RB.A23 |
ON GOING |
19-04-07 |
Interlock tests RB.A23 |
- |
29-05-07 |
Powering tests RB.A23 |
- |
30-05-07 |
8h run >= 8kA |
- |
04-06-07 |
Pic interface test |
- |
16-06-07 |
Circuits < 2kA |
|
|
120A powering tests |
DONE |
03-05-07 |
600ANOEE powering tests |
ON GOING |
08-05-07 |
600A-EE interlock tests |
- |
16-05-07 |
600A-EE powering tests |
DONE |
08-05-07 |
8 hr run PC < 2kA |
- |
24-05-07 |
|
|
|
24hr heat run test |
- |
07-06-07 |
Polarity test < 8KA |
- |
25-05-07 |
Polarity Check > 8KA |
- |
05-06-07 |
AUG- UPS test |
- |
08-06-07 |