TWiki home | Point 1 | Point 2 | Point 3 | Point 4 | Point 5 | Point 6 | Point 7 | Point 8 | Minutes |
EE - IST | ||
13kA EE | DONE | 16-04-07 |
600A EE | DONE | 23-04-07 |
Circuits >2kA | ||
Powering tests PC 4-8kA | - | 11-05-07 |
8h run 4-8kA | ON GOING | 29-05-07 |
Interlock tests RQD&F | ONGOING | 02-05-07 |
Powering tests RQD&F | - | 24-05-07 |
Preparation RB.A23 | ON GOING | 19-04-07 |
Interlock tests RB.A23 | - | 29-05-07 |
Powering tests RB.A23 | - | 30-05-07 |
8h run >= 8kA | - | 04-06-07 |
Circuits < 2kA | ||
120A powering tests | DONE | 03-05-07 |
600ANOEE powering tests | ON GOING | 08-05-07 |
600A-EE interlock tests | ON GOING | 03-05-07 |
600A-EE powering tests | DONE | 18-05-07 |
8 hr run PC < 2kA | - | 29-05-07 |
24hr heat run test | - | 07-06-07 |
Polarity Check < 8KA | - | 30-05-07 |
AUG- UPS test | - | 08-06-07 |
I | Attachment | History | Action | Size | Date | Who | Comment |
---|---|---|---|---|---|---|---|
![]() |
RAT_20070523.pdf | r1 | manage | 43.0 K | 2007-05-23 - 12:22 | BorisBellesia | |
![]() |
SOC_UA27_8hrheatrun.xls | r1 | manage | 74.0 K | 2007-05-23 - 12:22 | BorisBellesia |