Short Circuit Tests in UA27 - 25th May

PDF RAT_20070525.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x25x11x30/RAT_20070525.pdf

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA DONE 11-05-07
8h run 4-8kA - 29-05-07
Interlock tests RQD&F ONGOING 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 DONE 25-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests DONE 08-05-07
600A-EE interlock tests DONE 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Topic attachments
I Attachment History ActionSorted ascending Size Date Who Comment
PDFpdf RAT_20070525.pdf r1 manage 30.5 K 2007-05-25 - 11:33 BorisBellesia  

This topic: HCC > WebHome > BlogEntryPoint2x2007x05x25x11x30
Topic revision: r1 - 2007-05-25 - BorisBellesia