6.03 | DONE | 600A EE systems IST - DFBLC |
12.03 | DONE | 600A EE systems IST - DFBAE |
16.03 | DONE | 600A EE systems IST - DFBM |
6.03 | ON GOING | 13kA EE systems IST - L7 |
13.03 | DONE | 13kA EE systems IST - R7 |
14.03 | ON GOING | 600A no EE PC – IST |
15.03 | ON GOING | 600A-EE interlock tests |
15.03 | ON GOING | 600A-EE PC - IST |
20.03 | - | 600A no EE PC – IST |
23.03 | - | 600A-EE Interlock tests |
23.03 | - | 600A-EE powering |
28.03 | - | 120A – powering |
29.03 | - | 120A - DFBM - powering |
29.03 | - | 600A-EE interlock tests |
29.03 | - | 600A-EE powering |
2.04 | - | 600A - Warm magnets |
4.04 | - | 120A – powering |
5.04 | - | 8hr HEAT RUN |
6.04 | - | CCC tests |
10.04 | - | 24hr heat run test |
2.04 | - | Polarity Check |
12.04 | - | EE 4hr run |
13.04 | - | AUG- UPS test |
I | Attachment | History | Action | Size | Date | Who | Comment |
---|---|---|---|---|---|---|---|
![]() |
RAT_20070315.pdf | r1 | manage | 73.2 K | 2007-03-15 - 18:47 | BorisBellesia |