RAT_20071704.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x18x13x15/RAT_20071704.pdf
**********************************
**********************************
In the Minutes:
* Resume of the two 8hr heat runs
* List of the contact people of the concerned system during the 24hr heat run
**********************************
**********************************
Schedule:
22.03 |
DONE |
Polarity Check |
30.03 |
DONE |
CCC tests: preparation for the 8hr run |
16.04 |
DONE |
First 8hr HEAT RUN ; re-scheduled |
17.04 |
DONE |
Second 8hr HEAT RUN |
18.04 |
- |
CCC tests: preparation for the 24hr run |
19.04 |
- |
24hr HEAT RUN |
20.04 |
- |
AUG - UPS test |
21.05 |
- |
EE 4hr run |