Activities foreseen in sector 45 from Monday 2nd July up to the cooldown

Activities in sector 45 from Monday 2nd July

  • CRYO
    • Purging on Friday 29th evening and all the week end long;
    • Refilling on Monday 2nd July;
  • ElQA-TP4B and Monitoring installation
    • On Tuesday 3th July, once 6Bar conditions are reached, ElQA will be repeated (only on RB) maybe from 8am to 1pm. RESTRICTED ACCESS.
  • CRYO-instrumentation
    • Coherence test of all the valves in ARC and LSS (Thursday 28th and Friday 29th);
    • Commissioning;
    • Initialization of the CV910 valves on Tuesday 26th and Wednesday 27th;
  • TS/EL intervention
    • Changing of the connectors of a BPM (LSS4R);
    • Connection check of the instrumentation cables of BCT;
  • TIM camera
    • General check on Monday 2nd July;
    • Run from P4 to P5, during the Cryo Patrouille the morning of the start of the cool-down;
  • Safety Inspection
    • Monday 2nd July at 2pm;
  • AT/ACR Patrouille
    • A Patrouille will be carried out on Wednesday 4th July just before the cooldown.
  • AT/VAC
    • Short access to LSS4R and LSS5L on Monday 2nd July.
  • AB/BI
    • LSS4R short intervention on the BI (capeau).

Comments:

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-06-29 - MatteoSolfaroli
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login