SECTOR45
General planning:
- W41-W42: L5 to 80K
- W42-W43: Cool-down of the whole sector from 80K up to 4.5K
- W44: Cool-down of the arc45 from 4.5K up to 1.9K / ElQA of the Circuits of the matching sections / Powering tests of the matching sections
- W45: ElQA of the circuits of the arc and Powering tests of the matching sections
- W46: Powering tests of the circuits of the arc
Activitites - w41:
- Today -09/10 - cooldown L5 to 80K
- Sector closed since 08/10
- Access allowed with key and tokens except RE52-UL55
- See document LHC-S-ES-0017 for particular access conditions
- ElQA break-down monitoring all along cooldown; AT-MEL
- QPS activities; AT-MEL
- CMS vacuum installation/tests; AT-VAC
- Magnet alignment; TS-SU
- Cable campaign point5; TS-EL
- Inner triplet interconnection; AT-MCS
Open Issues + Long term activitites:
- Swapped cables of RB circuit on DFBA RR53
- Cleaning – W43/44
- Collimator installation W44
- CMS-ZDC optical fiber installation; W44
SECTOR34
General planning+Activities:
- W40: Pressure test of the arc / DSL still disconnected
- W41-W42:
- Consolidation
- All lines under nominal pressure up to Wed. 10/10 - AT-VAC/ACR
- Cryo-valves reconfiguration Thu.-Fri. 11-12/10 - AT-ACR
- Opening and repairs of leaks (two leaks found: 7R4 ~2*10^-6 [mbar*l/s] and 7L4 ~10^-5 [mbar*l/s]) - AT-MCS/VAC
- Checks the jacks - stable pressure conditions needed - 2 days needed - date to be decided, possibly on Friday 12/10 - TS-IC
- ElQA.DOC from Wed. 10/10 - AT-MEL
- Manometer installation on the ceiling at the level of RE38 – trolley passage difficult – TS-IC
- W43: DFBLC-DSLC-DFBAF interconnections start (possibility to start during W42 if compatibility with consolidation)
- W50: Flushing