Comments: 8-H HEAT RUN ON GOING
Next meeting: Thursday, 7 at 8.30 in CCC.
Open Issues
- 22.11 Fire detection – awaiting certification
- 01.12 Short cables on 13 kA EE to be changed later on (temporary solution in place)
Heat Runs and Test Schedule
- 07.12 Fire detection test
- 08.12 Full power ventilation tests in RR57 – from 8:30 till 12:00
- 11.12 10am: 24-h heat run
- 12.12 UPS test.
- 13.12 Electric cut (AUG simulation).
- 13.12 Polarity Test
- 14.12 13kA energy extraction test.