TWiki home Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Minutes

Back to overview

YOU ARE VIEWING BlogEntryPoint5x2006x12x07x12x32

RAT for Point 5 in CCC, Dec 7

PDF RAT_20061207.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x07x12x32/RAT_20061207.pdf

Comments: Next meeting in CCC on Monday Dec,11.

Open Issues

  • 22.11 Fire detection – awaiting certification
  • 01.12 Short cables on 13 kA EE to be changed later on (temporary solution in place)
  • 06.12 Permanent labels for RQ converters in RR57 (according to ECR)
  • 07.12 Cables re-distribution for 600 A
  • 07.12 Access key to electrical distribution room in UJ56

Heat Runs and Test Schedule

  • 07.12 Fire detection test
  • 08.12 Full power ventilation tests in RR57 – from 8:30 till 12:00
  • 08.12 Afternoon: Polarity Test_1st part
  • 11.12 10am: 24-h heat run
  • 12.12 UPS test.
  • 13.12 Electric cut (AUG simulation).
  • 13.12 Polarity Test_2nd part
  • 14.12 13kA energy extraction test.

Topic attachments
I Attachment History Action Size Date Who Comment
PDFpdf RAT_20061207.pdf r1 manage 36.3 K 2006-12-07 - 12:33 MirkoPojer  
Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2006-12-07 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login