Comments: NEXT MEETING WILL BE HELD ON DEC,18 AT POINT 5
Please, find also included the IR analysis rapport, kindly provided by Jeff Thomsen.
Open Issues
- 01.12 Short cables on 13 kA EE to be changed later on (temporary solution in place)
- 06.12 Permanent labels for RQ converters in RR57 (according to ECR)
- 07.12 Access key to electrical distribution room in UJ56
Heat Runs and Test Schedule
- 01.12 Squeeze test DONE (all the power converters involved have been tested)
- 06.12 8-h heat run DONE
- 07.12 Fire detection test DONE
- 08.12 Full power ventilation tests in RR57 – from 8:30 till 12:00 DONE
- 08.12 Afternoon: Polarity Test_1st part TO BE RE-SCHEDULED
- 11.12 10am: 24-h heat run DONE
- 13.12 9.00: UPS test and Electric cut (AUG simulation).
- 13.12 Polarity Test_2nd part TO BE RE-SCHEDULED
- 14.12 13kA energy extraction test
- 15.12 14.00: New sequencer test