TWiki home Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Minutes

Back to overview

YOU ARE VIEWING BlogEntryPoint5x2006x12x12x15x08

RAT for Point 5 in CCC, Dec 12

PDF RAT_20061212.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x12x15x08/RAT_20061212.pdf

PDF UJ56-RR57_IR-Report_2006-12-12_24H-Burnin.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x12x15x08/UJ56-RR57_IR-Report_2006-12-12_24H-Burnin.pdf

Comments: NEXT MEETING WILL BE HELD ON DEC,18 AT POINT 5

Please, find also included the IR analysis rapport, kindly provided by Jeff Thomsen.

Open Issues

  • 01.12 Short cables on 13 kA EE to be changed later on (temporary solution in place)
  • 06.12 Permanent labels for RQ converters in RR57 (according to ECR)
  • 07.12 Access key to electrical distribution room in UJ56

Heat Runs and Test Schedule

  • 01.12 Squeeze test DONE (all the power converters involved have been tested)
  • 06.12 8-h heat run DONE
  • 07.12 Fire detection test DONE
  • 08.12 Full power ventilation tests in RR57 – from 8:30 till 12:00 DONE
  • 08.12 Afternoon: Polarity Test_1st part TO BE RE-SCHEDULED
  • 11.12 10am: 24-h heat run DONE
  • 13.12 9.00: UPS test and Electric cut (AUG simulation).
  • 13.12 Polarity Test_2nd part TO BE RE-SCHEDULED
  • 14.12 13kA energy extraction test
  • 15.12 14.00: New sequencer test

Topic attachments
I Attachment History Action Size Date Who Comment
PDFpdf RAT_20061212.pdf r1 manage 37.2 K 2006-12-12 - 15:09 MirkoPojer  
PDFpdf UJ56-RR57_IR-Report_2006-12-12_24H-Burnin.pdf r1 manage 1759.7 K 2006-12-12 - 15:19 MirkoPojer  
Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2006-12-12 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login