RAT for SCT in UA67/UJ67 - Jan, 15

PDF RAT_20070115.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x01x15x11x07/RAT_20070115.pdf

Open Issues:

  • 15.01 Loosen bolts on RCBYH4.R6B1 and RCBYV4.R6B2 PCs.
  • 12.01 Power cut in ERD-R13
  • 12.01 Cleaning of filters by CV (planned for 17.01)
  • 10.01 QPS racks connection
  • 21.12 Aluminum panel for the cables ducts/ shipping and install.
  • 21.12 HV Insulation test of the DQS poles
Heat Runs and Test Schedule:
  • 08.01 600A and 13 kA EE system IST. ON GOING
  • 08.01 RB IST. ON GOING
  • 11.01 120A powering tests. COMPLETED
  • 15.01 2 kA powering tests. ON GOING
  • 17.01 PIC-PC-QPS Interface tests.
  • 19.01 600A powering tests. COMPLETED
  • 23.01 600A-EE powering tests.
  • 26.01 120A-600A-2kA 8h heat run.
  • 30.01 RQD&F powering tests.
  • 02.02 RB powering tests.
  • 07.02 RQ&RB 8h heat run.
  • 12.02 24h heat run test.
  • 14.02 AUG&UPS test.
  • 14.02 Polarity test.

- Main.MirkoPojer - 15 Jan 2007 - 11:15

Topic attachments
I Attachment History Action Size Date Who Comment
PDFpdf RAT_20070115.pdf r1 manage 39.4 K 2007-01-15 - 11:15 MirkoPojer  
Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-01-15 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login