RAT_20070115.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x01x15x11x07/RAT_20070115.pdf
Open Issues:
- 15.01 Loosen bolts on RCBYH4.R6B1 and RCBYV4.R6B2 PCs.
- 12.01 Power cut in ERD-R13
- 12.01 Cleaning of filters by CV (planned for 17.01)
- 10.01 QPS racks connection
- 21.12 Aluminum panel for the cables ducts/ shipping and install.
- 21.12 HV Insulation test of the DQS poles
Heat Runs and Test Schedule:
- 08.01 600A and 13 kA EE system IST. ON GOING
- 08.01 RB IST. ON GOING
- 11.01 120A powering tests. COMPLETED
- 15.01 2 kA powering tests. ON GOING
- 17.01 PIC-PC-QPS Interface tests.
- 19.01 600A powering tests. COMPLETED
- 23.01 600A-EE powering tests.
- 26.01 120A-600A-2kA 8h heat run.
- 30.01 RQD&F powering tests.
- 02.02 RB powering tests.
- 07.02 RQ&RB 8h heat run.
- 12.02 24h heat run test.
- 14.02 AUG&UPS test.
- 14.02 Polarity test.