RAT_20070117.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x01x17x11x19/RAT_20070117.pdf
Open Issues
- 17.01 Broken thermostat on 13 kA EE
- 12.01 Power cut in ERD-R13
- 12.01 Cleaning of filters by CV (planned for 17.01)
- 10.01 QPS racks connection
- 08.01 EE fan rotation problem – all ring
- 21.12 Aluminum panel for the cables ducts/ shipping and install.
- 21.12 HV Insulation test of the DQS poles
Heat Runs and Test Schedule
08.01 |
ON GOING |
600A and 13 kA EE system IST |
08.01 |
ON GOING |
RB IST |
11.01 |
DONE |
120A powering tests. |
15.01 |
DONE |
2 kA powering tests. |
17.01 |
ON GOING |
PIC-PC-QPS Interface tests. |
19.01 |
DONE |
600A powering tests. |
23.01 |
- |
600A-EE powering tests. |
26.01 |
- |
120A-600A-2kA 8h heat run. |
30.01 |
- |
RQD&F powering tests. |
02.02 |
- |
RB powering tests. |
07.02 |
- |
RQ&RB 8h heat run. |
12.02 |
- |
24h heat run test. |
14.02 |
- |
AUG&UPS test. |
14.02 |
- |
Polarity test. |