Open Issues
- 17.01 Broken thermostat on 13 kA EE
- 10.01 QPS racks connection
- 08.01 EE fan rotation problem – all ring
- 21.12 Aluminum panel for the cables ducts/ shipping and install.
Heat Runs and Test Schedule
08.01 |
DONE |
600A and 13 kA EE system IST. |
08.01 |
DONE |
RB IST. ON GOING |
11.01 |
DONE |
120A powering tests. |
15.01 |
DONE |
2 kA powering tests. |
15.01 |
DONE |
600A powering tests. |
17.01 |
DONE |
600A-EE powering tests. |
22.01 |
- |
PIC-PC-QPS Interface tests. |
23.01 |
- |
RQD&F powering tests. |
24.01 |
- |
RB powering tests. |
26.01 |
- |
120A-600A-2kA-RQD/F-RB 8h heat run. |
05.02 |
- |
24h heat run test. |
07.02 |
- |
Polarity test. |
14.02 |
- |
AUG&UPS test. |
- Main.MirkoPojer - 19 Jan 2007 - 11:28