Beam Dump System Commissioning - RAT of April 17, 2007.

Mpp LSS6_v2.mpp:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x04x19x18x50/LSS6_v2.mpp

PDF RAT_20070417.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x04x19x18x50/RAT_20070417.pdf

PLANNED INTERVENTIONS IN THE AREA

  • The bake-out of the whole MKDs-to-MKDs sector will be completed by w28.
  • A cabling campaign (including fire detection system) is foreseen for w16 to w19. No interferences have been pointed out during the inspection visit of AB/BT, TS/EL and TS/HDO.
  • A water maintenance intervention has been scheduled for the w18 to w20 (demineralised water, cryogenic services and iced water will be affected).
  • Test of the MSD foreseen for w.29-30.
  • Cool-down of sector 5-6 for mid August.
  • Cool-down of sector 6-7 for mid October.
Open Issues
  • 10.04 Installation of BPMSD AB/BI
  • 10.04 Installation of BCTFD AB/BI
  • 10.04 Modifications on PDC of MKB-67 requested by Norisko AB/BT
  • 10.04 Mounting and alignment of beam dump line in RA63 AT/VAC
  • 10.04 Installation of MKD magnets in RA63 AB/BT
  • 10.04 Installation of junction modules between MKDs in RA67 AT/VAC
  • 03.04 Inspection by Norisko on PDC of UA63
  • 03.04 Assembly of PDC for MKDs in UA63 AB/BT
  • 03.04 Assembly of PDC for MKDs in UA67 AB/BT
  • 20.03 Mismatch between TCDS and MSD AT/VAC&AB/BT
  • 13.03 Grounding of instrumentation/after deconsignation AB/BT
  • 27.02 TCS: installation on w.18
  • 27.02 Vacuum tube between carbon window and TDE (fabrication on going-ready for the end of June) AB/ATB
  • 27.02 VMTAB bellows are needed for w18 AB/BT
  • 20.02 VAC: bake-out of MKD-6R AT/VAC
  • 20.02 TDE in UD68 ready for end of June
  • 20.02 BPM installation AB/BI
  • 20.02 Vacuum pipe on Q4 AT/VAC-AB/BT
  • 20.02 Safety inspection by Norisko on PDC for MKD63 and MKB63
  • 20.02 Optical fibers for pulsing K. Loukili-TS/EL
Closed Issues
  • 17.04 VAC: bake-out of MKD-6L 20.02
  • 10.04 Beam dump line in TD62 10.04
  • 10.04 BLMs integration 13.03
  • 10.04 Smoothing of the MSD 10.04
  • 03.04 Assembly of PDC for MKBs in UA63 03.04
  • 27.03 Safety inspection by Norisko on power distr.rack (MKB67) 20.02
  • 27.03 Grounding of instrumentation/before deconsignation 13.03
  • 10.04 Mounting supports for second beam (on drawings) (6L&R) 13.03
  • 27.03 Place for storing MKDs in UX65 20.03
  • 20.03 Grounding of magnets 13.03
  • 13.03 Intermediate bellows availability 27.02
  • 13.03 Interference between vacuum support and MKD 27.02
  • 27.02 Space in UJ62 and UJ67 for installation of spare TDE (and transport equipment) - late installation of that part of dump line 20.02

Topic attachments
I Attachment History Action Size Date Who Comment
Unknown file formatmpp LSS6_v2.mpp r1 manage 377.0 K 2007-04-19 - 19:02 MirkoPojer  
PDFpdf RAT_20070417.pdf r1 manage 40.5 K 2007-04-19 - 18:54 MirkoPojer  
Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-04-19 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login