07.02 | DONE | Water circuit filters cleaning in RR73 |
12.02 | DONE | ERD1 powering, FGCs configuration and first tests in RR73 |
13.02 | DONE | 120A (RR73) powering tests |
14.02 | DONE | 600A (RR73) powering tests |
14.02 | DONE | Full power ventilation test |
15.02 | DONE | 600A-EE interlock and powering tests |
15.02 | DONE | 600A-EE interlock tests |
20.02 | DONE | 600A (UJ76) powering tests |
21.02 | DONE | Water circuit filters cleaning in UJ76 |
22.02 | DONE | Polarity test |
23.02 | DONE | 8h heat run in RR73 and UJ76 |
26.02 | DONE | Water circuit filters cleaning in RR73/UJ76 |
27.02 | DONE | CCC test for 24h run |
28.02 | ON GOING | 24h heat run test |
01.03 | - | Electrical services-Inom-Imax |
01.03 | - | EE-QPS test at Imax |
01.03 | - | AUG&UPS |