Back to overview
YOU ARE VIEWING BlogEntryPoint7x2007x03x01x15x39

RAT_20070301.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint7x2007x03x01x15x39/RAT_20070301.pdf
********************************************
* All converters in RR73 and UJ76 VALIDATED during 24hr heat run
********************************************
07.02 |
DONE |
Water circuit filters cleaning in RR73 |
12.02 |
DONE |
ERD1 powering, FGCs configuration and first tests in RR73 |
13.02 |
DONE |
120A (RR73) powering tests |
14.02 |
DONE |
600A (RR73) powering tests |
14.02 |
DONE |
Full power ventilation test |
15.02 |
DONE |
600A-EE interlock and powering tests |
15.02 |
DONE |
600A-EE interlock tests |
20.02 |
DONE |
600A (UJ76) powering tests |
21.02 |
DONE |
Water circuit filters cleaning in UJ76 |
22.02 |
DONE |
Polarity test |
23.02 |
DONE |
8h heat run in RR73 and UJ76 |
26.02 |
DONE |
Water circuit filters cleaning in RR73/UJ76 |
27.02 |
DONE |
CCC test for 24h run |
28.02 |
DONE |
24h heat run test |
01.03 |
DONE |
Electrical services-Inom-Imax |
01.03 |
DONE |
EE-QPS test at Imax |
02.03 |
- |
13kA EE tests |
02.03 |
- |
AUG&UPS |