Preparation of Cool-Down in Sector 78, 16 Nov

PDF RAT_20061116.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x11x16x17x00/RAT_20061116.pdf

Comments:

  • Open Issues
    • 13.11.06 Cryo. Valves manipulation on the DFBMH, DFBAN and DFBAO
    • 13.11.06 Non-conformity of the mini-crates of cryo instrumentation
    • 13.11.06 Cabling non-conformity affecting QPS and 60A Orbit Correctors IST
    • 13.11.06 WRL DFBAO missing support LSS8L
    • 13.11.06 3 x 600 A power cable positioning LSS8L
    • 13.11.06 BPM connection in Q2, Q3, Q4, Q5, Q6, Q7
    • 13.11.06 ElQA-TP4-A in the DFBAO, DFBAN, DFBAX
    • 13.11.06 LSS8L Q6-Q7 bake-out
    • 13.11.06 120 A Cables connection in DFBMC, DFBMA and DFBX LSS8L
    • 13.11.06 6 kA and 13 kA cables positioning at DFBMA and DFBMC
    • 13.11.06 Quench protection continuity tests and cables assignment LLS7R (DFBMH, DFBAN) and LSS8L (DFBMC, DFBMA and DFBX)
    • 13.11.06 DS7R and DS8L leak test
    • 13.11.06 Leak in R7
    • 13.11.06 Galvanic Insulation 600 A, 6 kA, 13 kA for LSS8L and LSS7R available
    • 15.11.06 Leak in arc
    • 15.11.06 Leak test to be performed after the replacement of bellows

-- Main.MirkoPojer - 16 Nov 2006 - 17:52

Topic attachments
I Attachment History Action SizeSorted ascending Date Who Comment
PDFpdf RAT_20061116.pdf r1 manage 41.7 K 2006-11-16 - 17:02 UnknownUser  
Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r2 - 2006-11-16 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login