TWiki> HCC Web>BlogEntryPoint8x2006x11x23x14x53 (revision 1)EditAttachPDF
TWiki home Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Minutes

Back to overview

YOU ARE VIEWING BlogEntryPoint8x2006x11x23x14x53

Preparation for Cool-Down Sec78 - Thu Nov, 23rd

PDF RAT_20061123.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x11x23x14x53/RAT_20061123.pdf

Comments:

    • AC non-conformity
  • 21.11.06 Transport and installation of the heater system of the current leads for RR77 and UA83
  • 21.11.06 Non-conformity on instrumentation cables (temperature sensors on current leads)
  • 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current)
  • 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL, orbit corrector power converters & VAC.

    • DC cabling
  • 23.11.06 Cable temporary positioning on the transport side of the tunnel
  • 23.11.06 Adjustment of cable length on DFBAO
  • 22.11.06 Missing labels on DFBAO instrumentation cables
  • 22.11.06 Pre-connection of 120A cables in LSSR7
  • 20.11.06 Galvanic insulation installation of 600 A cables to the DFBAO
  • 13.11.06 Non-conformity of the DC cabling of the orbit corrector power converters
  • 13.11.06 6 kA and 13 kA cables positioning at DFBAO, DFBMA and DFBMC
    • Assembly: -

    • Vacuum: -

    • Cryogenics
  • 22.11.06 Cryo-valves remote control in CCC by AB/CO
  • 22.11.06 Control of quench valve
  • 20.11.06 DFB instrumentation cables to be connected
  • 17.11.06 Instrumentation cable HV tests in LSS8L

    • DFB Commissioning
  • 13.11.06 ElQA-TP4-A in the DFBAO, DFBAN, DFBAX
  • 17.11.06 Pumping of insulation vacuum DFBAN, DFBAO, DFBMC, DFBMA, DFBXG

    • Safety: -

    • General remark: written communication in advance to announce operations!!!
  • 23.11.06 Wooden structure for UA access restriction (that will allow transport).
  • 23.11.06 Preparation of a prototype plastic protection or the monorail (protection derived from a plastic tube) by J.C.Guillaume and approval by J.Etheridge.
  • 23.11.06 Water leak on the tunnel concrete wall to be fixed (33L8).
  • 23.11.06 Planning of consignations/deconsignations
  • 16.11.06 Cool down safety procedure & access conditions

    • Preparation of powering test
  • 22.11.06 Pretest of 60A converters in sector 78, location C16L8.
  • 22.11.06 Installation of flexible cables by CV (UA83)
  • 16.11.06 Water circulating in UA83 for the Powering Procedure Test: filters need to be checked.

    • AOB
  • 13.11.06 BPM connection in Q2, Q3, Q4, Q5, Q6, Q7
  • 13.11.06 Quench protection continuity tests and cables assignment LLS7R (DFBMH, DFBAN) and LSS8L (DFBMC, DFBMA and DFBX)

-- Main.MircoCoccoli - 23 Nov 2006 - 14:55

Topic attachments
I Attachment History Action Size Date Who Comment
PDFpdf RAT_20061123.pdf r1 manage 54.8 K 2006-11-23 - 15:23 MircoCoccoli  
Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r1 - 2006-11-23 - MircoCoccoli
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login