YOU ARE VIEWING BlogEntryPoint8x2006x11x24x20x25

RAT_20061124.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x11x24x20x25/RAT_20061124.pdf
Comments:
Open Issues:
- AC non-conformity
- 21.11.06 Transport and installation of the heater system of the current leads for RR77 and UA83 (P.Chambouvet: about 2 weeks of work starting Mon 27 Nov)
- 21.11.06 Non-conformity on instrumentation cables (temperature sensors on current leads) (A.Suraci: 4 cables are in repair)
- 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current) (A.Suraci: ready next year)
- 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL, orbit corrector power converters & VAC.
- DC cabling
- 23.11.06 Cable temporary positioning on the transport side of the tunnel (A.Vergara: next year)
- 22.11.06 Pre-connection of 120A cables in LSSR7
- 20.11.06 Galvanic insulation installation on all DFBs
- 13.11.06 Non-conformity of the DC cabling of the orbit corrector power converters
- 13.11.06 6 kA and 13 kA cables positioning at DFBAO, DFBMA and DFBMC
- Assembly -
- Vacuum -
- Cryogenics
- 22.11.06 Cryo-valves remote control in CCC by AB/CO
- 22.11.06 Control of quench valve
- 20.11.06 DFB instrumentation cables to be connected (D.Bozzini: 80% done)
- 17.11.06 Instrumentation cable HV tests in LSS8L (A.Suraci: 4 cables to be tested)
- DFB Commissioning
- 13.11.06 ElQA-TP4-A for all DFBs between 7 and 8 (D.Bozzini: ongoing according to schedule; next week will begin ElQA-TP4-B, i.e. HV tests)
- 17.11.06 Pumping of insulation vacuum for all DFBs between 7 and 8 (P.Chambouvet: DFBAN done)
- Safety
- General remark: written communication in advance to announce operations!!!
- 23.11.06 Wooden structure for UA access restriction (that will allow transport).
- 23.11.06 Preparation of a prototype insulating protection (derived from a plastic tube) of the monorail by J.C.Guillaume and approval by J.Etheridge.
- 23.11.06 Water leak on the tunnel concrete wall to be fixed (33L8).
- 23.11.06 Planning of consignations/deconsignations
- 16.11.06 Cool down safety procedure & access conditions
- Preparation of powering test
- 22.11.06 Pretest of 60A converters in sector 78, location C16L8. (B.Bellesia: stopped due to LQA hardware problems; expected end by Tuesday 28 Nov)
- 22.11.06 Installation of flexible cables by CV (UA83)
- 16.11.06 Water circulating in UA83 for the Powering Procedure Test: filters need to be checked.
- AOB
- 13.11.06 BPM connection in Q2, Q3, Q4, Q5, Q6, Q7
- 13.11.06 Quench protection continuity tests and cables assignment LLS7R (DFBMH, DFBAN) and LSS8L (DFBMC, DFBMA and DFBX)