YOU ARE VIEWING BlogEntryPoint8x2006x11x29x18x25

Preparation for Cool Down sec.78 - Nov 29

PDF RAT_20061129.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x11x29x18x25/RAT_20061129.pdf

Mpp Sector_78_Preparation_of_Cool_Down_w48.mpp:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x11x29x18x25/Sector_78_Preparation_of_Cool_Down_w48.mpp
UPDATED PLANNING (comments are welcome!)

Open Issues:

AC non-conformity

  • 21.11.06 Non-conformity on instrumentation cables (temperature sensors on current leads) (A.Suraci: 3 cables are in repair-Wed.29th)
  • 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current) (A.Suraci: ready next year)
  • 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL, orbit corrector power converters & VAC.
DC cabling
  • 25.11.06 Functional test on the leads heaters: DFBAO, DFBMA, DFBMC, DFBXG
  • 22.11.06 Pre-connection of 120A cables in LSSR7 (TS/EL)
  • 20.11.06 Galvanic insulation installation on all DFBs (AT/MEL)
  • 13.11.06 Non-conformity of the DC cabling of the orbit corrector power converters
  • 13.11.06 6 kA and 13 kA cables positioning at DFBAO, DFBMA, DFBMC, DFBAN (Flohe)
Assembly - Vacuum - Cryogenics
  • 22.11.06 Cryo-valves remote control in CCC by AB/CO
  • 22.11.06 Control of quench valve
  • 20.11.06 DFB instrumentation cables to be connected (A.Suraci: 80% done)
  • 17.11.06 Instrumentation cable HV tests in LSS8L (A.Suraci: 4 cables to be tested)
DFB Commissioning
  • 29.11.06 Definition of owner of activity and pumping needs for current leads insulation vacuum (DFBX)
  • 29.11.06 Pumping of insulation vacuum for DFBX
  • 13.11.06 ElQA-TP4-A for all DFBs between 7 and 8 (D.Bozzini: next(w48): DFBAO HC module, DFBMA, DFBMC, DFBX))
Safety General remark: written communication in advance to announce operations!!!
  • 25.11.06 ElQA-TP4B safety procedure (1900 volts tests!).
  • 23.11.06 Wooden structure for UA access restriction (that will allow transport).
  • 23.11.06 Preparation of a prototype insulating protection (derived from a plastic tube) of the monorail by J-C.Guillaume and approval by J.Etheridge.
  • 23.11.06 Water leak on the tunnel concrete wall to be fixed (33L8).
  • 16.11.06 Cool down safety procedure & access conditions
Preparation of powering test
  • 22.11.06 Pretest of 60A converters in sector 78, location C16L8. (B.Bellesia: stopped due to LQA hardware problems; expected end by Tuesday 28 Nov)
  • 22.11.06 Installation of flexible cables by CV (UA83)
  • 16.11.06 Water circulating in UA83 for the Powering Procedure Test: filters need to be checked.
AOB
  • 13.11.06 BPM connection in Q2, Q3, Q4, Q5, Q6, Q7–wk49 (J-C.Guillaume & R.Jones)
  • 13.11.06 Quench protection continuity tests and cables assignment LLS7R (DFBMH, DFBAN) and LSS8L (DFBMC, DFBMA and DFBX)

Topic attachments
ISorted ascending Attachment History Action Size Date Who Comment
Unknown file formatmpp Sector_78_Preparation_of_Cool_Down_w48.mpp r1 manage 364.5 K 2006-11-29 - 18:44 MircoCoccoli UPDATED PLANNING (comments are welcome!)
PDFpdf RAT_20061129.pdf r3 r2 r1 manage 52.5 K 2006-11-29 - 19:51 MircoCoccoli  
Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r3 - 2006-12-08 - MircoCoccoli
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login