AC non-conformity
- 07.12.06 Non conformity in DFBMH, DFBAN and DFBXG current lead heaters (P.Chambouvet-J-C.Guillaume)
- 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current) (A.Suraci: ready next year)
- 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL & VAC.
DC cabling
- 30.11.06 Non conformity temperature sensor cables need repair LSS7R (D.Bozzini, A.Suraci)
- 25.11.06 Functional test on the leads heaters: DFBAO, DFBXG (P.Chambouvet)
- 22.11.06 Pre-connection of 120A cables in LSSR7 (TS/EL) – PC Non conformities (H.Thiesen)
Vacuum
-
Cryogenics
- 22.11.06 Cryo-valves remote control in CCC by AB/CO (F.Millet)
- 22.11.06 Control of quench valve (F.Millet)
DFB Commissioning
- 29.11.06 Pumping of Current Leads insulation vacuum for DFBX (S.Feher)
Safety
General remark: written communication in advance to announce operations!!!
- 23.11.06 Wooden structure for UA access restriction (that will allow transport).
- 23.11.06 Water leak on the tunnel concrete wall to be fixed (C33L8).
Preparation of powering test
- 30.11.06 El_QA performed on C16L8. ICC test showed reversed sequence of V-taps on circuit RCBV16.L8B1 (D.Bozzini)
AOB
- 13.11.06 BPM connection in Q2, Q3, Q4, Q5, Q6, Q7–wk50 (J-C.Guillaume & R.Jones)