Preparation Cool-Down Sector 78-RAT 19th Dec

PDF RAT_20061219.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x12x19x11x13/RAT_20061219.pdf

Open Issues:

AC non-conformity

  • 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current) (A.Suraci: ready next year)
  • 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL & VAC.
DC cabling
  • 30.11.06 Non conformity temperature sensor cables need repair LSS7R (D.Bozzini, A.Suraci)
  • 22.11.06 Pre-connection of 120A cables in LSSR7 (TS/EL) – PC Non conformities (H.Thiesen)
Instrumentation Cabling
  • 15.12.06 DFBXG non-conformity on the current lead heater cables (P.Chambouvet-J-C.Guillaume)
Cryogenics
  • 22.11.06 Instrumentation and remote control not fully stable (P.Gayet - F.Millet)
DFB Commissioning
  • 29.11.06 DFBX Pumping of Current Leads insulation vacuum (S.Feher)
13 kA EE Systems
  • 16.12.06 Calibration of the Arc Detectors on the 13 kA EE System (K.Dahlerup-Petersen)
Safety General remark: written communication in advance to announce operations!!!
  • 23.11.06 Water leak on the tunnel concrete wall to be fixed (C33L8).
Preparation of powering test
  • 30.11.06 El_QA performed on C16L8. ICC test showed reversed sequence of V-taps on circuit RCBV16.L8B1 (D.Bozzini)
AOB
  • 13.11.06 BPM connection in Q2 (R.Jones) – waiting for Inner Triplet to be repaired

MircoCoccoli - 19 Dec 2006 - 11:56

Topic attachments
I Attachment History Action Size Date Who Comment
PDFpdf RAT_20061219.pdf r1 manage 62.8 K 2006-12-19 - 12:00 MircoCoccoli  
Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2006-12-19 - MircoCoccoli
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login