RAT_20061219.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x12x19x11x13/RAT_20061219.pdf
Open Issues:
AC non-conformity
- 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current) (A.Suraci: ready next year)
- 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL & VAC.
DC cabling
- 30.11.06 Non conformity temperature sensor cables need repair LSS7R (D.Bozzini, A.Suraci)
- 22.11.06 Pre-connection of 120A cables in LSSR7 (TS/EL) – PC Non conformities (H.Thiesen)
Instrumentation Cabling
- 15.12.06 DFBXG non-conformity on the current lead heater cables (P.Chambouvet-J-C.Guillaume)
Cryogenics
- 22.11.06 Instrumentation and remote control not fully stable (P.Gayet - F.Millet)
DFB Commissioning
- 29.11.06 DFBX Pumping of Current Leads insulation vacuum (S.Feher)
13 kA EE Systems
- 16.12.06 Calibration of the Arc Detectors on the 13 kA EE System (K.Dahlerup-Petersen)
Safety
General remark: written communication in advance to announce operations!!!
- 23.11.06 Water leak on the tunnel concrete wall to be fixed (C33L8).
Preparation of powering test
- 30.11.06 El_QA performed on C16L8. ICC test showed reversed sequence of V-taps on circuit RCBV16.L8B1 (D.Bozzini)
AOB
- 13.11.06 BPM connection in Q2 (R.Jones) – waiting for Inner Triplet to be repaired
MircoCoccoli - 19 Dec 2006 - 11:56