RAT Point 8 - 12 February 2007

Main activities ongoing (check meeting minutes for further details):

  • LHCCOOL cards needed to access sector 78

  • Cooldown of Sec78 from 80K to 20K planned for this week

  • Cryo-leak being repaired in magnet 3002. The problem appeared also in other magnets (SSS349).

  • Powering Procedure Test from Wednesday 14th

  • Warm Magnets powering tests ongoing this week in LSS8L an LSS8R

PDF RAT_20070212_WithPPT_planning.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x02x12x14x24/RAT_20070212_WithPPT_planning.pdf