Powering Tests: 16 May 2007

Program for 16.05.2007 - afternoon

14:00 PCC for Q5
15:00 PIC2 for D2,Q4,Q5: Ivan and Boris from the CCC, the rest in the FCC If things go smoothly
16:00 Start P2N, preferably Q5, final decision around 15:00. In the sequence a quench at 1000A will be provoked (if we reach this far)