23.05 MORNING | Verification signalization in the tunnel. Consignation all TI8 LHC PC. Disconnection of the DC cables to the TI8 LHC PC. WELQA on the MSI magnets |
|
23.05 AFTERNOON | WELQA on the rest of the TI8 LHC magnets. Connection of the DC cables to the TI8 LHC PC. Déconsignation all TI8 PC. |
|
24.05 MORNING | Verification signalization in the tunnel. Repeat the WELQA in the circuits where it could not be completed. Connection of the DC cables to the TI8 LHC PC. Déconsignation all TI8 PC. Polarity check TI8 LHC magnets. From 13:00 to 14 :30 Déconsignation PC compensators 1. RPTN.SR8.RBXWSH.L8 1. RPTN.SR8.RBXWH.L8 Switch on RPTN.SR8.RBXWSH.L8 and verification at the magnet level. Switch off RPTN.SR8.RBXWSH.L8 Switch on RPTN.SR8.RBXWH.L8 and verification at the magnet level. Switch off RPTN.SR8.RBXWH.L8 |
From 13:00 to 14:30 No work around the ANY compensator magnets |
24.05 AFTERNOON | Start 24h Heat Run (TI8 LHC + COMPENSATORS L8) (I ultimate) | No work around the compensator magnets |
25.05 MORNING |
24h Heat Run ongoing Temperatures measurements at the end 24h Heat Run |
No work around the compensator magnets |
25.05 AFTERNOON |
Turn on all TI8 magnets PC, RPTN.SR8.RBXWSH.L8 and RPTN.SR8.RBXWH.L8. Start 1st Interferences Evaluation Start solution on non conformity on power converter of MQIF87800 (3e-4 ripple) |
No work around the compensator magnets |