Powering Tests in Sector 7-8: activity of Tuesday 22/05.

The Powering to Nominal procedure was started fro the following circuits:

  PNO.1 PNO.2
RCBCH5.L8B1 O O
RCBCv5.L8B1 O O
RCBYH4.L8B2 O O
RCBYHS4.L8B1 O O

Several problems were faced:

  • cryogenics instabilities which delayed the CRYO START signal:
    • oscillating level on DFBMC
    • high temperature on the first 6 kA in DFBMA (54 K)
  • delay for PNO.2 step for RCBYH4.L8B2, whose origin was:
    • hardware limitation of the PC, which blocked the cycle to 52 A; the PC went on fault and the current drop to zero (intervention of PO to remove the limitation)
    • probably due to the problem just mentioned, a very long PM file was produced which was preventing the cycle from being restarted (manual reset of the PC was needed)
  • RCBYHS4.L8B2 showed a possible NON-CONFORMITY: while preparing this circuit for PNO.1, a high voltage value was detected on a lead (250 mV); a verification of PO showed that this is probably due to an open voltage tap. The circuit has been removed from the SOC.

PROPOSAL FOR WEDNESDAY 23/05:

  • continuation of tests on RCBCH5.L8B1, RCBCv5.L8B1, RCBYH4.L8B2 and RCBYHS4.L8B1;
  • Powering to Nominal procedure for circuits RCBYV4.L8B1, RCBYVS4.L8B1 and RCBYVS4.L8B2;
  • continuation of tests on Q4 and Q5 if released by MPP;
  • continuation of tests on D2.

POSSIBLE SCENARIOS FOR NEXT WEEK (N.B.: PC, PIC, QPS, EE systems and experts have to be ready for next Tuesday!!!)

RB.A78, RQF.A78 (?), RQD.A78 (?) Powered by their own converter DFBA, QPS, EE, PC, PIC Preparation (this week)
ARC @ 1.9K ElQA @ 1.9K RB & RQD
QPS Heater Discharge
PIC1 RB & RQF
Connection DC cable - lead
PC_CONFIG RQ - 350A
PIC 2 RQ - 350A
PC_CONFIG RB - 350A
PIC 2 RB - 350A
P2N RQ - Max 760A
P2N RB - Max 760A
 
Powered by a 120A converter DFBA, QPS, EE, PC, PIC Preparation (this week)
ARC @ 4.5K PIC1 RB & RQD - Without Quench Heaters
Connection DC cable - lead
PC_CONFIG RQ - 100A
PC_CONFIG RB - 100A
 
600A Circuits - Priority 1, 25 Circuits ARC @ 4.5K or 1.9K DFBA, QPS, EE, PC, PIC Preparation (this week)
ElQA @ 4.5K-1.9K first Circuits
QPS Last Conditioning
PC_CONFIG first circuits
ARC @ Superfluid Helium DFBA, QPS, EE, PC, PIC Preparation (this week)
ElQA @ 4.5K-1.9K All Circuits
QPS Last Conditioning
PIC2 First Circuits
PCS First Circuits
PC_Config, PIC2, PCS rest of circuits - Parallel

Comments:

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-05-22 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login