Back to overview
YOU ARE VIEWING BlogEntryPoint8x2007x05x24x18x26
The day was fully devoted to perform tests on Q4, which had experienced an unexpected quench at 300 A on Monday (after ramping at 600 A).
The following tests have been executed on Q4 (MANUAL execution, due to change in procedure):
- ramp to 600 A with 5 A/s and quench driven by QPS, generating an artificial quench signal from one current lead detector; the test was successful;
- ramp of B1 power converter to nominal current (3610 A) with 10 A/s ramp rate and simultaneous ramp of B2 power converter to 2000 A with nearly 5 A/s (unbalanced configuration):
- when B1 current reached 1025 A, its reference current went anormally down to 0;
- later analysis showed that a fault was sent from the converter and a consequent FPA was started;
- PO attempt to get control of B2 power converter, to ramp it down contemporarily to 0, provoked a sudden voltage peak in B1, which initiated a quench;
- at 11.48 (according to PIC supervision) a power cut occured on the general services of UA83, which eventually provoked the loss of controls on cryogenics and lead heating system;
- after waiting for the good cryo conditions to be recovered, and in agreement with PO, QPS and MPP experts, we decided to ramp again Q4 with the same unbalanced cycle:
- B1 at 3610 A with 10 A/s ramp rate and B2 to 2000 A with a nearly 5 A/s ramp rate;the test was successful and NO quench was activated;
- while ramping B2 power converter to the same current as B1 (the idea was to stay on plateau for half an hour and then provoke a quench), and with a current in B2 of 2900 A, a quench generated; preliminary analysis indicated that it was started in B1, possibly due to electromagnetic coupling (this configuration has never been tested before).
- end of the tests due to long recovery time.
Proposal for the activity of tomorrow.
- Continue powering Q4 and D2.
- Continue installation of plastic bags on 600 A current leads.
- Lower the temperature on the 13 kA leads to check the absence of condensation with AT/MEL copper laminations.
- ElQA on the selected circuits: list will be provided during the morning.